BRR : 60719
Tender Brief : For The Work Against Sanctioned Package No. 60 / 2022-23 ( Under Deposit Scheme ) Under Electricity Urban Distribution Division-Iii, Gorakhpur- 2 Supply Offollowing Material / Fitting Complete In All Respect :- 3 11 Kv Xlpe 3X185 Sqmm 4 Cable Jointing Kit 3X185 Sq Mm 5 Stp Pole 9 Mtr 6 11 Kv Top Channel 7 11 Kv Dropper Channel 8 Stay Complete 9 Earthing Complete 10 Clamps For Top Droper Etc 11 Nut & Bolt 12 G.I Pipe 6 Inch 13 Route Marker Stone For Ug Cable 14 The Excavation Of 2 No Foundation Pit Of Size 750Mmx450mm And Having Depth Of 1 / 6Th Of The Full Le... Read More
Tender Value
₹
Ref. Document
Contract Value
₹ 37,39,350
Submission Date
21-07-2022
Contract Date
19-09-2022
Completion Date
60 days
Participated Bidder List
3 No of Bidder(s)
| Sr No. | Bidder Name | Bid Analytics | Technical Bid | Financial Bid | AOC | Bid Value | Rank |
|---|---|---|---|---|---|---|---|
| 1 | cnet-technologies | Bid Analytics | 37,39,350 | L1 | |||
| 2 | cnet-technologies | Bid Analytics | 38,50,565 | L2 | |||
| 3 | cnet-technologies | Bid Analytics | 39,03,900 | L3 |
Work Detail
for the work against sanctioned package no. 60 / 2022-23 ( under deposit scheme ) under electricity urban distribution division-iii, gorakhpur- 2 supply offollowing material / fitting complete in all respect :- 3 11 kv xlpe 3x185 sqmm 4 cable jointing kit 3x185 sq mm 5 stp pole 9 mtr 6 11 kv top channel 7 11 kv dropper channel 8 stay complete 9 earthing complete 10 clamps for top droper etc 11 nut & bolt 12 g.i pipe 6 inch 13 route marker stone for ug cable 14 the excavation of 2 no foundation pit of size 750mmx450mm and having depth of 1 / 6th of the full length of the pole. fabrication & erection of double pole with fixing of necessary clamps & accessories ( top channel, dropper angle etc. ) as per required. all required materials such as holding clamp / stp clamp, nuts & bolts off size etc will be provided by the contractor.grouting of pole in cc 1:4:8 ( cement, sand & 40 mm brick ballast ) , grouting will be done in the block ofsize 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc ( material provided by contractor ) .making plinth around pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. all work will be done as per respo norms & relevent is specification. 15 laying and dressing of under ground 11 kv xlpe 3x185 sq mm by horizontal drilling method as per respo norms. the depth of horizontal drilling shall be between 2 to 3 meters or as per site required. 16 erection of 11 kv xlpe cable 3x185 mm² jointing kit with complete work 17 painting of pole by double coating aluminum & red oxide paint. paint will beprovided by contractor 18 earthing of st pole by ms earthing rod & 6 swg earthing wire as per respo norms. 19 erection and grouting of stay in cc ratio 1:4:8 of cement, sand and stone ballast including cost of grouting material with nozelling and binding of stay wire ( complete work ) 20 erection of route marker stone ( complete work )
View Original Notice/Document
Result Documents
Tender Documents
| Download | File Name | File Description |
|---|---|---|
| Download | 24a78663-8b1d-4f0a-8ac9-df5962ad9552 |
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender
✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount :
₹
1,00,00,000