BRR : 4538700
Click Here To View Tendering Authority. Aoc City/State :  AMBALAMEDU, Kerala
Tender Brief : Replacement Of Various Drive Motors , Gearboxes , Trunnion Rollers , Thrust Rollers Etc . In Np And Off Site Area , Fact Cd . , Replacement Of Various Drive Motors , Gearboxes , Trunnion Rollers , Thrust Rollers Etc . In Np And Off Site Area , Fact Cd . , Replacement Of Gear Box Of Dryer A Or B In N P Plant . Work Involves: The Required Site Arrangements Shall Be Done For The Replacement Of Gear Box Of Dryer A Or B In Np Plant . The Tools And Tackles Shall Be Arranged . Foundation Bolts Of The Existing Gear Box Shall Be Loosened / Removed And Lead / Transported To M... Read More
Tender Value
Ref. Document
Contract Value
₹ 9,47,000
Submission Date
29-06-2020
Contract Date
18-07-2020
Completion Date
365 days
Participated Bidder List
4 No of Bidder(s)
Sr No. Bidder Name Bid Analytics Technical Bid Financial Bid AOC Bid Value Rank
1 cnet-technologies Bid Analytics 12,38,000 L4
2 cnet-technologies Bid Analytics 9,94,000 L3
3 cnet-technologies Bid Analytics 9,49,000 L2
4 cnet-technologies Bid Analytics 9,47,000 L1
Work Detail
replacement of various drive motors , gearboxes , trunnion rollers , thrust rollers etc . in np and off site area , fact cd . , replacement of various drive motors , gearboxes , trunnion rollers , thrust rollers etc . in np and off site area , fact cd . , replacement of gear box of dryer a or b in n p plant . work involves: the required site arrangements shall be done for the replacement of gear box of dryer a or b in np plant . the tools and tackles shall be arranged . foundation bolts of the existing gear box shall be loosened / removed and lead / transported to mechanical work shop . the new / spare gear box shall be transported to site . the gear box shall be kept in position and insert the foundation bolts , after cleaning the base plate . rigging assistance shall be provided for the alignment of gear box . the out side surface area of the damaged gear box shall be cleaned properly , at mechanical work shop . , replacement of motor of dryer a or b in n p plant . work involves: the required site arrangements shall be done for the replacement of motor of dryer a or b in np plant . the tools and tackles shall be arranged . foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop . the new / spare motor shall be transported to site . the motor shall be kept in position and insert the foundation bolts , after cleaning the base plate . rigging assistance shall be provided for the alignment of motor . , replacement of trunnion roller of dryer a or b in n p plant . work involves: the required site arrangements shall be done for the replacement of trunnion roller of dryer a or b in np plant . the tools and tackles shall be arranged . foundation / jack bolts of the existing damaged trunnion roller shall be loosened / removed and lead / transported to mechanical work shop . the new / spare trunnion roller shall be transported to site from store / work shop . the trunnion roller shall be kept in position and insert the foundation bolts , after cleaning the base plate . after checking the measurement and alignment of the trunnion rollers , the foundation / jack bolts shall be tightened properly . if required , the thrust roller shall be re-arranged . the out side surface area of the damaged trunnion roller shall be cleaned properly , at mechanical work shop . , replacement of thrust roller of dryer a or b in n p plant . work involves: the required site arrangements shall be done for the replacement of thrust roller of dryer a or b in np plant . the tools and tackles shall be arranged . foundation / jack bolts of the existing damaged thrust roller shall be loosened / removed and lead / transported to mechanical work shop . the new / spare thrust roller shall be transported to site from store / work shop . the thrust roller shall be kept in position and insert the foundation bolts , after cleaning the base plate . after checking the measurement / alignment of the thrust rollers , the foundation / jack bolts shall be tightened properly . the out side surface area of the damaged thrust roller shall be cleaned properly , at mechanical work shop . , replacement of motor of product cooler a or b in n p plant . work involves: the required site arrangements shall be done for the replacement of motor of product cooler a or b in np plant . the tools and tackles shall be arranged . foundation bolts of the existing product cooler motor shall be loosened / removed and lead / transported to electrical work shop . the new / spare motor shall be transported to site . the motor shall be kept in position and insert the foundation bolts , after cleaning the base plate . rigging assistance shall be provided for the alignment of product cooler motor . , replacement of gear box of product cooler a or b in n p plant . work involves: the required site arrangements shall be done for the replacement of gear box of product cooler a or b in np plant . the tools and tackles shall be arranged . foundation bolts of the existing gear box shall be loosened / removed and lead / transported to mechanical work shop . the new / spare gear box shall be transported to site . the gear box shall be kept in position and insert the foundation bolts , after cleaning the base plate . rigging assistance shall be provided for the alignment of gear box . the out side surface area of the damaged gear box shall be cleaned properly , at mechanical work shop . , replacement of motor of granulator a or b in n p plant . work involves: the required site arrangements shall be done for the replacement of motor of granulator a or b in np plant . the tools and tackles shall be arranged . foundation bolts of the existing granulator motor shall be loosened / removed and lead / transported to electrical work shop . the new / spare motor shall be transported to site . the motor shall be kept in position and insert the foundation bolts , after cleaning the base plate . rigging assistance shall be provided for the alignment of product cooler motor . , replacement of trunnion roller of granulator a or b in n p plant . work involves: the required site arrangements shall be done for the replacement of trunnion roller of granulator a or b in np plant . the tools and tackles shall be arranged . foundation / jack bolts of the existing damaged trunnion roller shall be loosened / removed and lead / transported to mechanical work shop . the new / spare trunnion roller shall be transported to site from store / work shop . the trunnion roller shall be kept in position and insert the foundation bolts , after cleaning the base plate . after checking the measurement and alignment of the trunnion rollers , the foundation / jack bolts shall be tightened properly . if required , the thrust roller shall be re-arranged . the out side surface area of the damaged trunnion roller shall be cleaned properly , at mechanical work shop . , replacement of trunnion roller of product cooler a or b in n p plant . work involves: the required site arrangements shall be done for the replacement of trunnion roller of product cooler a or b in np plant . the tools and tackles shall be arranged . foundation / jack bolts of the existing damaged trunnion roller shall be loosened / removed and lead / transported to mechanical work shop . the new / spare trunnion roller shall be transported to site from store / work shop . the trunnion roller shall be kept in position and insert the foundation bolts , after cleaning the base plate . after checking the measurement and alignment of the trunnion rollers , the foundation / jack bolts shall be tightened properly . if required , the thrust roller shall be re-arranged . the out side surface area of the damaged trunnion roller shall be cleaned properly , at mechanical work shop . , replacement of thrust roller of granulator / cooler a or b in n p plant . work involves: the required site arrangements shall be done for the replacement of thrust roller of granulator / cooler a or b in np plant . the tools and tackles shall be arranged . foundation / jack bolts of the existing damaged thrust roller shall be loosened / removed and lead / transported to mechanical work shop . the new / spare thrust roller shall be transported to site from store / work shop . the thrust roller shall be kept in position and insert the foundation bolts , after cleaning the base plate . after checking the measurement / alignment of the thrust rollers , the foundation / jack bolts shall be tightened properly . the out side surface area of the damaged thrust roller shall be cleaned properly , at mechanical work shop . , replacement of motor of vibrator screen , a or b stream in n p plant . work involves: the required site arrangements shall be done for the replacement of motor of vibrator screen a or b stream in np plant . the tools and tac
View Original Notice/Document
Result Documents
Tender Documents
Download File Name File Description
Download 04a411ea-4eca-4c11-b61e-44e5a6f89424
Download File Name File Description
Download BOQ_592577 Tender Documents - BOQ
Download TenderDocumentR1 Tender Documents - Tender documents
Download 54117C5D-AFD6-4EB5-A4F5-CE1ECC888ACB Tender Documents - Tender Notice
Download SpecialConditions Tender Documents - Special conditions
Download Tendernotice_1 Tender Documents - NIT
Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount : ₹ 1,00,00,000