| 1 | Supply Component:- |
| 2 | Nuts & Bolts including washers (Hot dip galvanized hexagonal round hexagonal head transmission towers as per BOM). |
| 3 | Single Suspension Fitting for pilot suspension in complete set alongwith suspension hook. |
| 4 | Number plate as per sample provided |
| 5 | Danger Plate as per sample provided |
| 6 | Phase plate in set of Red, Blue & yellow for tension tower as per sample provided |
| 7 | Pipe Type Earthing material per tower |
| 8 | Midspan Compression Joint |
| 9 | Preformed Armour Rod |
| 10 | Work Component:- |
| 11 | Dismantalling of all 3 phases of existing ACSR Panther conductor, all hardware fittings and conductor accessories e.g armour rod, vibration dampers, insulator strings etc of existing line and re-rolling of dismantalled conductors on empty drums for re-use, safely transportation of all removed material to UPPTCL stores. |
| 12 | Dismantalling of existing OPGW alongwith necessary hardware, rerolling of OPGW Fibre on empty drums & safe transportation of all removed materials to UPPTCL stores, or its proper safe storage in drums at working site for its re-use. The work also includes safe dismantaling of the joint box for its reuse. |
| 13 | Dismantaling of tower, stacking of tower parts and all associated works. The work includes removing old tack weldings without causing any damage to dismantaled tower(DA+0). |
| 14 | Carriage of dismantaled material from site to store and stacking at store |
| 15 | Dismantalling of earlier foundation which includes excavation, breaking of foundation upto 2 mtrs depth and removing of concrete, cutting, removing of stub and steel reinforcement, backfilling, levelling and making field suitable for agriculture. |
| 16 | Survey including preparation of schedule of materials, marking of locations( Route Length), GPS survey of line with co-ordinates of each tower followed by submission of survey report in 3 copies( The length of tower shall be auhtnticated by GPS survey). |
| 17 | Check Survey and peg marking |
| 18 | Soil Investigation( All kind of soil) |
| 19 | Carriage of various materials from different substation to working site. Materials to be transported includes : (a)OPGW cable from 132 KV S/S Jhusi, it also includes fibre untangling, its straightening amd its carraiage even if its cable drum is damaged (b)OPGW vibration damper and its tension fitting from 132 KV S/S Soraon,(c) Stub and Cleat from EFU Naini,(d) Tension Fitting, Conductor, Joint Box from Cantt/Kareli store to working site, Insulator disc and other remaining materials from 220 KV S/S Rewa Road, (e) 02 No DC+0 type tower, 01 No DC+5 extension, 01 No DC+10 extension from any designated storage location to working site, 02 job included for this work (f) carriage of any miscellaneous materials for satisfactory completion of the work (g) carriage of any remaining/unused materials from working site to UPPTCL stores, 02 job included for this work. The carriage of any amount of materials from stores falling under same route will be considered as one job, or, one vehicle/truck used for transportation of materials will be considered as one job. |
| 20 | Cost of Excavation of 132 KV Tower foundation pits including all earth work, backfilling, levelling etc. |
| 21 | Setting of stubs including all foundation work but excluding the cost of concreting and excavation (Rate per location) for following towers(The stub has to be set with the help of template, with template being arranged by the contractor at his own cost) : |
| 22 | 132 KV DC/DE Panther (DC+5, DC+10) |
| 23 | Installation of Reinforcement bars in RCC Foundation including cost of steel reinforcement bars with cutting, bending, placing, binding etc. |
| 24 | Cost of concreting of all type of tower foundation including cost of cement of Ultratech/ACC/Birla make, dewatering, shoring and shuttering, forming, curing but excluding cost of reinforcement bars (cement:sand:aggregate ratio). |
| 25 | 1:2:4 Concreting |
| 26 | Anchoring by providing stay on cross arms of towers at any appropriate location before removal of conductors by making CC foundation for anchoring of stay wire, fixing os suitable stay wire/rod etc and finally removal thereof after stringing of new conductors with all men and materials to be arranged by the contractor at his own cost. |
| 27 | Erection of super structure of 132 KV Towers and Anchor Tower and their extensions wherever required including all work above ground level excluding hoisting of insulators, hardware & accessories, but including fitting of danger, number, phase plates, bird guard and fixing and punching for 132 KV SC/DC lines alongwith nuts and bolts. The work also includes any fabrication of pieces, if needed,for satisfactory completion of the work giving the tower its required strength. The pieces needed for fabrication will be provided by the department. (DC+5, DC+10). |
| 28 | Laying, stringing, tensioning, clamping, jointing, etc of ACSR Panther conductor including hoisting of insulators, fitting of all necessary hardware and accessories i.e fittings, armour rods, vibration dampers etc on all six phases of 132 KV DC/MC Lines. The die pressing machine if needed for jointing conductor, if required, to be arranged by the contractor at his own cost. |
| 29 | Laying, stringing, tensioning, clamping, jointing including fittings of all necessary hardwares and accessories of OPGW & OFAC, commissioning of links, termination at S/S, end to end connectivity & testing etc on 132 KV & 220 KV Lines. |
| 30 | Splicing & Installation of Joint Box (48 Fibre). The splicing machine if needed for jointing OPGW, if required, to be arranged by the contractor at his own cost. |
| 31 | Tack welding of all the bolts up to the height of one section of the tower or 5 meter from ground level whichever is higher with three tacks at 1200 separation of minimum 10 mm thickness with 10mm/12mm electrode & application of Zinc rich Aluminium paint on the affected area including cost of all material including tack welding of River Crossing Towers/Anchor Towers/ Any kind of Tower. |
| 32 | Grounding work, including earthwork etc for pipe type grounding including cost of coke & salt. |
| 33 | Round the clock watch & ward of Line/Line materials during work to avoid theft of Tower Parts, Conductors, Hardware fittings, Accessories etc even after completion of work till all the materials are safely shifted to UPPTCL stores. [ Please Enable Macros to View BoQ information |