| 1 | TOTAL AMOUNT |
| 2 | SUPPLY, DELIVERY, INSTALLATION, TESTING ANDCOMMISSIONING OF 700 MM DIA MS DISMANTLING JOINTS. |
| 3 | LowerIng M.S pipes & specials in trench up to a depth of 3.00 metre below G.L, laying and jointing the same inside the trench /over ground by means of electric arc welding using standard electrodes as per l.S. specification, all complete as per direction of the Engineer-in-Charge. [The Engineer-in-Charge shall approve the electrodes for arc welding before use. (For laying over ground. the rates shall be reduced by 10% and that is inclusive of holding arrangements) ] 750mm |
| 4 | Flange joint to C.l./D.l/MS. pipes and specials including supply of rubber gasket. nuts. bolts. washers etc. of best quality to make the joint watertight at required hydraulic pressure all complete as per specification & direction of the Engineer-in-Charge. Diameter in mm 750mm dia. |
| 5 | SEQUENTIAL DISMANTLING OF ACTUATOR INCLUDING DISCONNECTIONS OF ALL THE ELECTRICAL LINES, GEAR BOX,WHEEL ETC. OF 750MM DIA ACTUATOR-OPERATEDNON-RISING TYPE SLUICE VALVE. PN1.6 CWPS-II GRWW ANDKEEPING THEM AT A SUITABLE PLACE INCLUDING ALL SORTSOF ALLIED WORKS, ALL COMPLETE, ADOPTING ALL SORTS OF REQUIRED PRECAUTIONS, SAFETY ETC AND USING ALLSORTS OF MACHINES, INSTRUMENTS, TOOLS AND TACKLES,ARRANGEMENTS, SUPPORTS ETC AS PERSITE-REQUIREMENT AND DIRECTION OF THE EIC |
| 6 | DISMANTLING, LIFTING ETC OF THE ENTIRE EXISTING 750MMDIA ACTUATOR-OPERATED NON-RISING TYPE SLUICE VALVE,PN1.6 CWPS-II, GRWW FROM THE EXISTING PIPE-BAY,SEQUENTIALLY BY OPENING, DISMANTLING AND REMOVINGOF THE EXISTING SCRAP HOLDING, OPENING ANDDISMANTLING OF ALL THE NUTS, BOLTS ETC OF BOTH SUCTION AND DELIVERY SITE AND KEEPING IT AT A SUITABLEPLACE, ADOPTING ALL SORTS OF REQUIRED PECAUTIONS,SAFETY ETC AND USING ALL SORTS OF MACHINES,INSTRUMENTS, TOOLS AND TICKLES, ARRANGEMENTS,SUPPORTS ETC AS PER SITE-REQUIREMENT AND DIRECTIONOF THE EIC. |
| 7 | TRANSPORTATION OF THE 750MM DIA ACTUATOR-OPERATED NON-RISING TYPE SLUICE VALVE. PN1.6 FROM CWPS-II, GRWW FROM MACHINE SHOP TO GRWW, KEEPING IT AT A SUITABLE PLACE WITH FULL SAFETY AND PRECAUTIONSINCLUDING LOADING & UNLOADING WITH THE ARRANGEMENTOF CRANE AND/OR TEPOY ALONG WITH ALL REQUIRED TOOLS AND TACKLES AS PER SITE-REQUIREMENT AND DIRECTION OF THE EIC. |
| 8 | LIFTING, PUTTING AND INSTALLATION OF THE 750 MM DIAACTUATOR-OPERATED NON-RISING TYPE SLUICE VALVEPN1.6 OF CWPS-II, GRWW IN EXISTING PIPE-BAYSEQUENTIALLY BY PROVING, INSERTING TIGHTENING ETC OFTHE REQUIRED SSNUTS, BOLTS, WASHERS ETC OF BOTHSUCTION AND DELIVERY SIDES AND REASSEMBLING OF THESCRAP HOLDING PART BY PART INSERTING AND TIGHTENINGOF ALL THE NUTS, BOLTS ETC OF THE SCRAP HOLDINGADOPTING ALL SORTS OF REQUIRED PRECAUTIONS, SAFETYETC AND USING ALL SORTS OF MACHINES, INSTRUMENT,TOOLS AND TACKLES ARRANGEMENTS, SUPPORTS ETC ASPER SITE-REQUIREMENT AND DIRECTION OF THE EIC |
| 9 | INSTALLATION OF THE ACTUATOR INCLUDING CONNECTIONSOF ALL THE ELECTRICAL LINES, GEAR BOX, WHEEL ETC OFTHE 750MM DIA ACTUATOR-OPERATED NON-RISING TYPESLUICE VALVE, PN1.6 OFCWPS-II GRWW AND INCLUDINGREQUIRED GREASING AND ALL OTHER ALLIED WORKS ALLCOMPLETE, ADOPTING ALL SORTS OF REQUIRED PRECAUTIONS, SAFETY ETC AND USING ALL SORTS OFMACHINES, INSTRUMENTS, TOOLS AND TACKLES,ARRANGEMENTS, SUPPORT ETC AS PER SITE-REQUIREMENTAND DIRECTION OF THE ELC |
| 10 | TRIAL OPERATION OF THE 750MM DIA ACTUATOR- OPERATEDNON-RISING TYPE SLUICE VALVE,PN1.6 OF CWPS-II,GRWWAND OBSERVATION FOR 8 HOURS, INCLUDINGRECTIFYING AND ADJUSTING THE REQUIRED PARTS,INCLUDING ALL SORTS OF ALLIED WORKS, ALL COMPLETE,ADOPTING ALL SORTS OF REQUIRED PRECAUTIONS, SAFETYETC AND USING ALL SORTS OF MACHINES INSTRUMENTS,TOOLS AND TACKLES, ARRANGEMENTS, SUPPORTS ETC ASPER SITE REQUIREMENT AND DIRECTION OF THE EIC. Please Enable Macros to View BoQ information |