| 1 | Excavation in foundation in ordinary soil, loame, clay or sand including lift upto 1.5 m & Iead upto 30m Including filling watering & ramming of excavated earth into the trenches or into the space between the building & the sides of foundation trenches or in to the plinth removal & disposal of surplus earth as directed by the engineer in charge upto a distance of 30m from the foundation trenches. Si No 251 |
| 2 | Concrete with 4cm(1½\\"). Gauge brick ballast, fine sand of 1.25 fineness modulous and cement in proportion of 12:6:1 in foundation and under floor, including supply of all material Iabour and T&P etc.required for proper completion of the work. Si No 273 |
| 3 | M-150 class brick work in 1:4 cement and coarse sand mortar including supply of all mat. Lab. T&P etc. reqd. for prop. Comp. of the work…all comp.. Si No 305 |
| 4 | R.C.C. work with cement approved coarse sand and 2 cm (3/4\\") gauge approved stone ballast in the proportion of 1:1.5:3 in lintels of doors and windows excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.l. binding wire and includuing Necessary centering and shuttering etc.and also including supply of all materials, labour and T&P etc. required for proper completion of the work. Binding wire cost being included in the item. Si No 283(a) |
| 5 | R.C.C. work with cement approved coarse sand and 2 cm (3/4\\") gauge approved stone ballast in the proportion of 1:1.5:3 in lintels of doors and windows excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.l. binding wire and includuing Necessary centering and shuttering etc.and also including supply of all materials, labour and T&P etc. required for proper completion of the work. Binding wire cost being included in the item. Si No 285 |
| 6 | R.C.C. work with cement approved coarse sand and 2 cm (3/4\\") gauge approved stone ballast in the proportion of 1:1.5:3 in lintels of doors and windows excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.l. binding wire and includuing Necessary centering and shuttering etc.and also including supply of all materials, labour and T&P etc. required for proper completion of the work. Binding wire cost being included in the item. Si No 284(a) |
| 7 | M.S. or iron in plain work such as R.cc i\c bending for proper shape and i\c supply of steel & its wastage, bend, hooks, and authorized overlapping shall be measured and i\c cost of binding wire.etc………..all Comp. As per P.W.D.schedule item. Si No 504 |
| 8 | 12 mm thick plaster with Cement mortar over brick work minimum thickness not to be less than 3/8\\" (10 mm) thick including supply of all materials, labour and T&P etc. required for proper completion of the work.with cement and coarse sand of 1.25 F.M. Mortar in 1:5 Si No 584(i) |
| 9 | M.S or iron work in heavy sizes such as trusses, gate, door, frames, record racks, roof work, gates etc. wrought to required from including drilling holes, rivetting or welding where necessary, and also including supply of steel, bolts, nuts etc their fixing required for proper copmletion of work. Si No 502(b) |
| 10 | C.C. work with 1:2:4 cement C-sand and stone grit 20mm concrete in holdfast including all required in complete work. Si No 279(i) |
| 11 | Providing and applying plaster of paris putty of 2 mm thickness over plasteredsurface to prepare the surface even and smooth complete D.S.R No 13.26 |
| 12 | Distemper two coat oil bound distemper of approved brand manufacture and required on decorated wall surface to give an even shade including priming coat with cement primer. Si.No (649+650) |
| 13 | Painting two coats on new iron & wood work as per SI No. 1+2+4iii in new item |
| 14 | Laying of 25mm thick KOTA stone of size 45x45cm and above flooring over previously prepared base with 2cm thick 1:3 cement and sand mortor including filling of joints with cement mixed pigment required for matching the shade of floor as per E/I including cutting polishing with wax polish and supply of all materials labour and T&P require for proper completion of work. Si No. 1 (New items of flooring chapter) |
| 15 | Providing and placing on terrace (at all floor levels) polyethylene water storage tank ISI : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank. as per DSR no. 18.48 Year 2023 Rate 11.00 Bare Rate Factor without cost index 0.781 & UP Disst. wise 106 cost SPN w.e.f 10.10.23 |
| 16 | GSt Please Enable Macros to View BoQ information |