| 1 | Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within All lead & Lift to MC Muck Disposal sitef:G.S. Sheet |
| 2 | Dismantling of wooden roof upto floor two level including stacking of serviceable material & Disposal of Un servicable material All lead & Lift to MC Muck Disposal site (Joists to be measured & paid for Separately |
| 3 | Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within All lead & Lift to MC Muck Disposal site :Of area beyond 3 sq. metres |
| 4 | Dismantling Wooden Celling & celotax/hard board in ceiling or partition wall including stacking of serviceable materials and disposal of un-serviceable materials within 2 All lead & Lift to MC Muck Disposal site (Frame work such as joists, beams to be measured and paid for separately) |
| 5 | Demolition above G.L.upto floor two level including disposal of Unserviceable materials within All lead & Lift to MC Muck Disposal site.un-reinforced cement concrete upto 15cm. Thickness. |
| 6 | Dismantling tiled floors laid in mortar upto floor two level including stacking of serviceable materials and disposal of un-serviceable materials within All lead & Lift to MC Muck Disposal site (wooden/concrete joists to be measured and paid for separately) |
| 7 | Dismantling of wooden floors upto floor two level including stacking of serviceable materials and disposal of un-serviceable materials within All lead & Lift to MC Muck Disposal site(joists to be measured and paid for separately) |
| 8 | Dismantling wood work. Wrought framed and fixed in frames other frames and trusses of span upto 10 metres and height between ridge and floor level stacking the serviceable materials and disposal of un-serviceable materials with in All lead & Lift to MC Muck Disposal site: Sectional area average 40 sq.cm. Or over. |
| 9 | Demolition above G.L. upto floor two level including disposal of unserviceable materials within All lead & Lift to MC Muck Disposal site and including cutting the necessary reinforcement and separating out from R.C.C. work. |
| 10 | Demolition of stone masonry above G.L. upto floor two level including stacking of serviceable materials and disposal of un-serviceable materials within All lead & Lift to MC Muck Disposal site. Dressed stone in cement mortar. |
| 11 | Demolition of brick work above G.L. upto floor two level including stacking of serviceable materials and disposal of un-serviceable materials within All lead & Lift to MC Muck Disposal site. lead.in cement mortar |
| 12 | Dismantling steel work upto span of 10 metres and a height of 5 metres in bullt up sectional in angles, tees, flats and channels including all gusset plates, bolts, nuts, beading etc and stacking the materials within All lead & Lift to MC Muck Disposal site |
| 13 | Taking out doors, windows and clerestory windows shutters (steel or wood) including stacking within All lead & Lift to MC Muck Disposal site. Exceeding 3 sqm in area. |
| 14 | Dismantling doors, windows and clerestory windows, ventilators etc. (wood or steel) shutters including mchowkhats, architraves, hold fasts and other attachements etc. complete and stacking them within All lead & Lift to MC Muck Disposal site. Not exceeding 3 sq.m in area Please Enable Macros to View BoQ information |