| 1 | Construction of sand pit for 220KV Sub-Station, Kanduni (Sitapur):- |
| 2 | Exacavation of dry soil including lift upto 0.30 Mtr., watering and ramming in the pit and backfilling after completion of work (Exacavation and backfilling both)2x(2x1.5x0.3)m3 |
| 3 | Base cement concreeting 1:4:8 with 40mm brick balast coarse sand and cement under the floor including cost of all material, Labour, T&P etc to complete the job 2x (2x1.5x0.3)m3 |
| 4 | First class brick work in 1:4 cement and coarse sand mortar in pit foundation & walls including cost of all material, labour, T&P etc to complete the job. 2[(1.06x1x0.22)+(2x1x0.22)]+2[(1/2x(1.28x.22x.22)]+(0.22x2x.22)m3 |
| 5 | 12mm thick plaster with cement mortar with 1:4 cement and coarse sand mortar on walls of pit including cost of all material, Labour,T&P etc to complete the job. 2x[{(1.5x1)+(2x1)}+{(1.06x1)+(1.56x1)}]+4x{1/2x(1.28x.22)}+2x(1.29x0.22)+(2x0.22)+1.56x.22)m2 |
| 6 | Sand filling including cost of sand, labour T&P required for filling |
| 7 | Constrcution of Shed for sand pit for 220KV Sub-Station, Kanduni:- |
| 8 | Cement concrete with 20 mm stone ballast coarse sand and cement in ratio of 1:2:4 for grooting of angle (04 Nos leg). (0.3x0.3x0.3)m3 |
| 9 | Grouting of 04 Nos 65x65x6 mm G.I./m.s. Angle post of size 3000 mm after due fabrication with CC mixture in the ratio of 1:2:4 fixing and welding of open hut type G.I./M.S. Angle frame structure of size 3000x2400x2400 mm by due fabrication with 65x65x6 mm size and 50x50 mm size G.I./M.S. angle on above GI/MS angle post by due cutting, drilling, welding etc of GI/MS angle to provided by department of each fire hut. |
| 10 | Fixing and fitting of asbestos corrugated (A.C.) roofing of size 3x4 inch to cover the roof of open hut type GI/MS angle frame structure of size 3000x2400x2400 mm with j hook bolt, nut and washer etc for each fire hut. |
| 11 | Spray painting of galvanized angle and AC sheets with two coats of standard make red synthetic enamel paint of first quality after cleaning of rest, dust and oily surface including cost of all material labour T&P as per technical specifications. |
| 12 | Carriage of 4 MT Galvanized Iron angle from 220KV Sub-Station, Sitapur to 220 KV Sub-Station, Kanduni (Distance approx. 42 km.) including cost of loading/unloading/shorting by labour. |
| 13 | Construction of Shed for DG Set:- |
| 14 | Cement concrete with 20 mm stone ballast coarse sand and cement in ratio of 1:2:4 for grooting of angle (04 Nos leg). (0.3x0.3x0.3)m3 |
| 15 | Grouting of 04 Nos 65x65x6 mm G.I./m.s. Angle post of size 3000 mm after due fabrication with CC mixture in the ratio of 1:2:4 fixing and welding of open hut type G.I./M.S. Angle frame structure of size 3000x2400x2400 mm by due fabrication with 65x65x6 mm size and 50x50 mm size G.I./M.S. angle on above GI/MS angle post by due cutting, drilling, welding etc of GI/MS angle to provided by department of each fire hut. |
| 16 | Fixing and fitting of asbestos corrugated (A.C.) roofing of size 3x4 inch to cover the roof of open hut type GI/MS angle frame structure of size 3000x2400x2400 mm with j hook bolt,nut and washer etc for each fire hut. |
| 17 | spray painting of galvanized angle and AC sheets with two coats of standard make red synthetic enamel paint of first quality after cleaning of rest, dust and oily surface including cost of all material labour T&P as per technical specifications |
| 18 | Making of sand drum at 220 KV S/S Kanduni:- |
| 19 | Making of sand storage drum by cutting of 04 no old & used T/F Oil drum in two pieces, properly bending on edge of drum, welding of 04 no iron angle legs of approximate length 30 cm at bottom each piece of drum with 02 nos handle for making sand storage drum. (Angle pieces and empty oil drum provided by the department) |
| 20 | provinding drum cover made of 18 SWG MS sheet for protection it from rain for above 08 nos sand storage drum with 04 nos standing supprt leg. Including cost of M.S. Sheet. |
| 21 | Painting of above sand storage drum after denting, rubbing by emery paper applying red oxide paint & then 02 coat of synthetic enameled red paint (Berger/Asian make) as per instruction and shifting it proper place at 132 KV or 33KV switchyard at 220 KV Sub-Station, Kanduni. |
| 22 | Filling of sand in to above sand storage drum. Please Enable Macros to View BoQ information |