| 1 | Dismantling of existing damaged concretes of slab, longitudinal beams, cross beams, hand rails, electric posts, low landings, screen walls, midtide beams etc and transporting the materials to the department stack yard as instructed by EIC leaving no brocken concrete pieces on the sea bed including hire charge of tractors, cost hire charge of required heavy machineries like concrete cutter, demolition hammer, breaker etc, cost of labours etc complete. |
| 2 | Providing and laying RCC (M30) with 1:0.9:1.8 mix (1cement,0.9 M sand,1.8 20mm stone chips) for short colums, beams, slabs of old approach/jetty as instructed by EIC including cost of all materials (Cement, M Sand, 20mm Chips), form work, all labour charges, transportation charge of materials to the site, hire charge of mixer machine, vibrator and minor tools etc complete. |
| 3 | Providing and laying RCC (M25) with 1:11/2:3 mix (1cement 11/2 Msand,3 20mm stone chips) for Hand railposts, handrails and lightpost etc as instructed by EIC including cost of all materials (Cement, M Sand, 20mm Stone Chips), transportation charge of materials to the site, hire charge of mixer machine, vibrator and minor tools etc. complete |
| 4 | Centering and shuttering for Hand railposts, handrails and lightpost etc including cost of all materials for the form work, transportation charge of materials to the site, hire charge of woodcutting tools and minor tools as per the direction of EIC etc complete. |
| 5 | Fabrication and fixing of reinforcement (Fe 500D make SAIL/TATA/RINL/JINDAL or its equivalant) as per the direction of Nodal Officer, including cost of material, fabrication, fixing dowels, shear ties, cutting, bending, tying, lapping and welding in position wherever necessary with black 18 SWG annealed binding wire, all labour charges, transportation charges of all materials to work site, all T&P required for the work etc. complete. |
| 6 | Providing and laying PCC (M20) with 1:2:4 mix (1cement 2 Msand,4 20mmchips) for wearing coat as instructed by EIC including cost of all materials (Cement, M Sand, 20mm Chips), form work, transportation charge of materials to the site, hire charge of mixer machine, vibrator and minor tools etc. complete |
| 7 | Applying two coat of ready mixed acrylic plastic emulsion paint (Exterior emulsion) antifunges over the primer coat on the hand rail posts, hand rails, light posts and on the right sides of the newly concreted jetty superstructure (longitudinal beam, deck slab side) as per the direction of EIC including cost of all the required materials, minor tools and labour charges etc complete. |
| 8 | Fixing 10T and 20T bollards on the both side of the jetty for arresting the vessels, boat with ropes for embarkation/ disembarkation of passenger and cargoes excluding the cost of bollard with its fittings, including transportation charges, minor tools, labour charges etc complete. |
| 9 | 20T Please Enable Macros to View BoQ information |