| 1 | Providing and laying in positioncement concreteofspecifiedgrade excluding the cost of centering and shuttering :All work upto plinth level : |
| 2 | 1 : 2 : 4(1 cement : 2 coarse sand :4 graded stone aggregate 20 mm nominal size). |
| 3 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). |
| 4 | Centring and shuttering including strutting, propping etc.and removal of form for :- |
| 5 | Lintels, beams, plinth beams, girders, bressumers and cantilevers . |
| 6 | Columns, pillars, piers, Abutments, posts and struts. |
| 7 | Smooth finishing of the exposed surface of R.C.C. work with 6 mm thick cement mortar 1:3 (1 Cement : 3 fine sand). |
| 8 | 12 mm cement plaster of mix : |
| 9 | 1:6 (1 cement: 6 coarse sand) |
| 10 | 15 mm cement plaster on rough side of single or half brick wall of mix : |
| 11 | 1:6 (1 cement: 6 coarse sand) |
| 12 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. |
| 13 | Dismantling and dismembering of 18 Mtr Roof Toptower at \"Bagicha\" Non BSNL site Distt. Jashpur including unscrewing nuts & bolts washer, angle/struts, cable tray and all accessories & fixtures of tower runway (Horizontal and vertical) and stacking safely at ground by ropes in Countable position serial wise, complete in all respects i/c insurance charges of labour as per direction & satisfaction of Engineer-in-Charge. |
| 14 | Carriage of roof top tower materials (Approximately weight 2000.00 Kg)from old non BSNL site Bagicha to BSNL Store at Beladula Road Raigarh (upto 250 km.) i/c loading, unloading the materials as per direction of Engineer- in- Charge |
| 15 | Disposal of the dismantled rubish material from terrace i/c loading, unloadingby manually head load and disposal the same beyond municipal limit by mechanical transport etc. all complete as per direction & satisfaction of Engineer-in-Charge. |
| 16 | Credit for reinforcement bar obtained from dismantling of R.C.C. |