Tender For Repairing and Rehabilitation of Forest Rest House Dow-Hill- 1 Dismantling carefully wooden walling, flooring of ceiling and stacking dismantled materials as directed.Bed room(floor) 2/4.45m x 4.45m = 39.61m² Kitchen( ceiling)5.35m x 2.60m= 13.91m²Wall outside (toilet 1&2)2/ 4.08m x 3.0m = 24.48m²Kitchen backside outside 5.625m x 3.0m = 16.88m²Kitchen (left right side) outside2/5.94m x 3.0m = 35.64m²Kitchen inside wall10.85m x 2.40m = 26.04m²external partition6/5.0m x0.60m = 18.0m²bed room( internal partition)2/ 3.5mx 2.5m = 17.50m²skirting75mx 0.25m = 18.75m²210.81m²WB PWD sch2017 page 13/315 item no 17 2 Dismantling carefully woodwork in posts, post plates, rafters, partition etc., sorting and stacking serviceable materials at site and removing rubbish as directed.Bed rooms 2nos( floor hor. Beam) 18/0.15m x 0.1m x 4.6m = 1.242m³Vertical post external wall 35/0.15m x 0.1m x 3.0m = 1.575m³Bottom plate at plinth 65.60m x 0.15m x 0.1m = 0.984m³ 3.801m³WB PWD sch2017 page 13/315 item no 19 3 Dismantling artificial stone flooring up to 50 mm. thick by carefully chiseling without damaging the base and removing rubbish as directed within a lead of 75 m.a) In ground floor including roof.Changing room (room1&2)2/2.35m x 1.25m) =5.87m²Drawing room5.02m x4.30m = 21.586m²Dining room 5.35m x 4.05m = 21.66m²Kitchen5.35m x2.50m = 13.37m²Passage5.35m x 0.9m = 4.815m²67.301m²WB PWD sch2017 page 11/315 item no 6.a 4 Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m.Kitchen brick wall 5.35m x .25m x 2.40m = 3.21m³WB PWD sch2017 page 10/315 item no 1.a 5 Removal of rubbish, earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading intotruck and cleaning the site in all respect as per direction of Engineer in charge3.801m³+3.21m³+(57.935x 0.1) = 12.8045WB PWD sch2017 page 12/315 item no 13. 6 Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m. In ground floor including roof.(a) up to 150 mm. thickKitchen floor slab5.35m x 2.50m x 0.1m = 1.34m³Toilet backside steps 2/ 1.20m x 0.8m x 0.3m = 0.58m³Kitchen backside plum wall 5.35m x 0.75mx 1.0m = 4.01m³ 5.93m³WB PWD sch2017 page 10/315 item no 2.a 7 Plain and finished timber planks in partition, shelves etc. fitted and fixed complete as per design (butt joints) in ground floor.(iii) 25mm thick planks b) Sishu / Champ / Badam / Gamar / Bhola / Mogra / Hallak/panisajInternal wall Kitchen passage1/5.60m x 2.80m = 15.68m²internal partition all rooms3.5.0m x 2.50m = 8.75m²3.7m x 2.60m = 9.62m²skirting75mx 0.25m = 18.75m²window and door jambs 180m x 0.15m = 27.0m²79.80m²WB PWD sch2017 page 179/315 item no 17.iii.b 8 Rough dressed timber planks fitted and fixed with nut bolts excluding framework complete :In ground floor (iv) Above 50mm thick planks (b) Sal LocalFor frame work of internal room partition Bed room2nos 3x4/4.45m = 53.40mKitchen 3x4/5.35m = 64.20mDining room 2x2/(5.35+4.05)m = 37.60mChanging room 2/2.60m = 5.20mPassage 2/5.3m x 4=42.4mKitchen extension 4/4.5m = 18.0m220.80m x 0.05m x 0.075m =0.828m³x WB PWD sch2017 page 137/315 item no 8.iv.b 9 A) Wood work in posts, post plates, rafters, battens, truss members, purlins etc. fitted and fixed complete (excluding the cost of bolts, paints, but including the cost of nails, screws etc.)(The quantum should be corrected up to three decimals)(i) Sal : Siliguri.Vertical post for external partition40/3.0m = 120.00mHorizontal beam for bedrooms floor17/4.50m=76.50mPost plate at plinth all round=70.00m 266.5m x 0.15 x 0.1m = 4.0m³WB PWD sch2017 page 135/315 item no 1(A).i 10 Rough dressed timber planks fitted and fixed with nut bolts excluding framework complete : b) Sal Local(ii) 35mm thick planksIn ground floor external partition60.0m x3.2m = m²192.0m²W.B.PWD schedule 2017, page no 137/315-item no.8.ii. 11 Ceiling with 12mm thick wooden planks fitted and fixed complete (excluding the supporting framework) as per direction of the Engineer-in-charge. In Ground Floor(a) Ordinary Teakfor pelmet box40.0m x 0.17m = 6.80 m²portico4.2m x 4.0m = 16.80m² kitchen 5.30mx 2.60m = 13.78m²extension8.0mx 5.0m = 40.0m²77.38m²W.B.PWD schedule 2017, page no 162/315-item no.7.a. 12 Rough dressed timber planks fitted and fixed with nut bolts excluding framework complete : b) Sal Local(iii) 50mm thick planksIn ground floor Bed roomfloor 2/4.45m x4.45m =39.60m²W.B.PWD schedule 2017, page no 137/315-item no.8.ii. 13 Woodwork in door and window frame fitted and fixed in position complete including a protective coat of painting at the contact surface of the frame excluding cost of concrete, Iron Butt Hinges and M.S clamps. (The quantum should be corrected up to three decimals).(c) Sal : Siliguri.D1=1no(2 x 2.10m ) + 1.20m = 5.40mD2=2nos (4 x 2.00m) + (2 x 0.8m) = 9.60mD3=4nos (10x 2.10m) + (5 x 1.0m) = 26.0mD4=2nos (4 x 2.0m) + (2 x 0.8m) = 9.60mW1= 2nos(6x1.25) + (4 x1.20m) = 12.30mW2=2nos(6 x 1.05) + (4 x 1.75) = 13.30m W4 = 2nos(4 x 0.9m) + (4 x 0.8m) = 6.80mW5= 4nos ( 12 x 1.5) + (8x1.80m) = 32.40mW6= 2nos( 4 x 0.9) + (4 x 1.60) = 9.0mW7= 4nos ( 8 x 0.9) + (8 x 0.6) = 12.0m =136.40mx 0.15m x 0.1m =2.046m³W.B.PWD schedule 2017, page no 114/315-item no.1.c 14 Panel shutters of door and window, as per design (each panel consisting of single plank without joint), including fitting and fixing the same in position but excluding the cost of hinge and other fittings. In ground floor.(In case of non-supply of single plank, penal rate of reduction of 20% will be made)(ii) 40mm thick shutters with 19mm thick panel of size 30 to 45cm b) Sishu, Gamar, Champ,Badam,Bhola, Mogra, Hallak.D1 Main door1.20m x 2.00m = 2.73m²D3 bed room & passage 5/ 0.9m x 2.00m = 9.0m²D2 Toilet 2/0.75m x 1.90m = 2.85m² 14.58m²+ 5% for extra curving0.729m² 15.30m²W.B PWD schedule 2017, page no 117-item noB. 1. ii b 15 Glazed shutters of doors, windows, fan light, clerestory windows etc. as perdesign (with ordinary glass of 7.4kg./sq.m. 3mm. Thick) fitted with putty bed and teak wood bead and nails including fitting and fixing shutter in position but excluding the cost of hinges and other fittings. cost of glass, putty, wooded beadsetc.will be paid separately. In ground floor.(i) 40mm thick shutters. (b) Sishu, Gamar, Champ,Badam,Bhola, Mogra, Hallak. W1(drawing room)= 4 x 0.6m x 1.15= 2.76m²W2(dining room)=4 x 0.87m x 1.05m = 3.654m²W3(toilet)= 2 x 0.85m x 0.40m= 0.68m²W4(changingroom) = 2 x0.76m x 0.9m= 1.368m²W5(bed room)= 8 x 0.745m x 1.3m = 7.75m²W6(toilet)= 2 x 1.60m x 0.9m = 2.880m²W7(kitchen)= 4x0.6m x 0.9m = 2.16m² 21.25m²W.B.PWD schedule 2017, page no 119/315-item no.4.i.b 16 Supplying best Indian sheet glass panes set in putty (as per I.SSpecification) and fitted and fixed with teak wood beads and nails complete. (In all floors for internal wall & up to 6 m height for external wall) (ii) 4 mm thickW.B.PWD schedule 2017, page no 205/315-item no.2.ii 17 Iron butt hinges of approved quality fitted and fixed with steel screws, with ISI mark.(viii) 100mm. X 75mm. X 3.50mm.W.B PWD schedule 2017, page no 140/315-item no 5. 18 Anodised aliminium D-type handle of approved quality manufactured from extruded section conforming to I.S. specification (I.S. 230/72) fitted and fixed complete:W.B.PWD schedule 2017, page no 144/315-item no.27.v 19 Anodised aliminium D-type handle of approved quality manufactured from extruded section conforming to I.S. specification (I.S. 230/72) fitted and fixed complete:W.B.PWD schedule 2017, page no 144/315-item no.27.v 20 Anodised aluminium Aldrop / Sliding bolts of approved quality manufactured from extruded section conforming to I.S. specification (I.S. 2681/66) fitted and fixed complete.(iv) 300mm x 19mm dia. bolt.W.B.PWD schedule 2017, page no 145/315-item no.28.IV 21 Supplying anodized aluminum catch hook with eye fitted and fixed to shutter and chowkat complete of best quality:.ii) 225mm long.W.B.PWD schedule 2017, page no 144/315-item no.25.ii 22 (a) M.S.or W.I. Ornamental grill of approved design jointscontinuously welded with M.S, W.I. Flats and bars of windows,railing etc. fitted and fixed with necessary screws and lugs in ground floor.(i) Grill weighing above 10 Kg./sq.mtr and up to 16 Kg./sq. mtr. 22 nos @ 20kg = 440.00kg 8nos @ 10kg = 80.00kg 520.0kg = 5.2qtlThe weight of grill per sq.m. will be determined by taking thephysical weight of fabricated grill and dividing the same by coveredarea of the same.N.B. No shop priming will be allowed to facilitate inspection ofworkmanship. Weight of grill is to be taken after final grinding andfinishing the weld.(b) Extra for work in grill gate.(I) For hanging and locking arrangements including supply ofmaterials and labour complete.(15% extra over the corresponding item of grill )W.B.PWD schedule 2017, page no 104/315-item no.13 23 Supplying, fitting and fixing 8mm thick Laminated woodenFlooring Work conforming to EN13329:2006 with plank sizenot Iess than 1200 mm X 190 mm (with unilin/tongue-groovelocking arrangement) having 0.2mm thk top abrasive layerover a decorative layer followed by a High-density fiberboard(HDF) having density > 850 kg/m3 substrate core over a resinsaturated backing layer and installing through unilin ortongue- groove system (having locking strength not less than1000 kg/m) over a 2 mm thk under layer polyurethane foam onpolythene sheet 250 micron, over a smooth, flat, hard subfloorfree from moisture (< 8%), grease etc. complete in all respectwith requisite accessories like end profile, transition profile,reducer T profile etc. wherever required and preparation ofbase including all other incidental works as per direction &satisfaction of Engineer in charge. Cost of Laminate FloorAccessories only (Skirting ,End edge, T- moulding,Reducer)shall have to be added separately, wherever required. (Thiswork should not be executed without specific permission ofSuperintending Engineer).Bed room2 x 4.45m x 4.45m =39.61m²Drawing room5.02m x 4.30m = 21.59m²Changing room 2 x 2.35m x 1.23m = 5.76m²66.96m²W.B.PWD schedule 2017, page no 71/315-item no.43 24 Artificial stone in floor, dado, staircase etc with cementconcrete (1:2:4) with stone chips, laid in panels as directedwith topping made with ordinary or white cement (asnecessary) and marble dust in proportion (1:2) includingsmooth finishing and rounding off corners including rakingout joints or roughening of concrete surface and applicationof cement slurry before flooring works using cement @ 1.75kg/sq.m all complete including all materials and labour.In ground floor.3 mm. thick topping (High polishing grinding on this item is not permitted with ordinary cement).Using grey cementDrawing room 5.02m x 4.30m = 21.59m²Changing room 2/2.35m x 1.23m = 5.76m² 27.35m²W.B.PWD schedule 2017, page no 48/315-item no.6.3rd corri. 22/96 item 4.iii 25 Supplying and laying true to line and level vitrified tiles of approved brand (size not less than 600 mm X 600 mm X 10mm thick) in floor, skirting etc. set in 20 mm sand cement mortar (1:4) and 2 mm thick cement slurry back side of tiles using cement @ 2.91Kg./sqM or using polymerized adhesive (6 mm thick layer applied directly over finished artificial stone floor/Mosaic etc without any backing course) laid afterapplication slurry using 1.75 Kg of cement per sqM below mortar only, joints grouted with admixture of white cementand colouring pigment to match with colour of tiles / epoxy grout materials of approved make as directed and removal of wax coating of top surface of tiles with warm water and polishing the tiles using soft and dry cloth upto mirror finish complete including the cost of materials, labour and all other incidental charges complete true to the manufacturers specification and direction of Engineer-in-Charge. (White cement, synthetic adhesive and grout material to be suppliedby the contrr]e)(I) With application slurry @1.75 kg/ Sq.m, 20 mm sandcement mortar (1:4) & 2 mm thick cement slurry at back sideof tiles, 0.2 kg/ Sq.m white cement for joint filling with (A) FloorWith Sand Cement Mortar (1:4) 20 mm thick & 2 mm thick cement slurry at back side of tiles using cement @ 2.91 Kg/Sq.m & joint filling using white cement slurry @ 0.20kg/Sq.m.b) Area of each tile above 0.09 Sq.m(i) Coloured decorativeKitchen 5.35mx 2.50m= 13.375m²Extended area5.35mx 1.50m = 5.00m²Fire proofelec. Room 4.0mx 3.0m = 12.00m²Dinning/passage5.35mx6.70m² = 35.84m²Skirting 10.60m x 0.15 = 1.59m²67.805m²W.B.PWD schedule 2017, page no 64/315-item no.35.A.b.i3rd corri. 34-35/96 item 22.A.b.i 26 Supplying, fitting & fixing 1st quality Ceramic tiles in walls and floors to match with the existing work & 4 nos. of key stones (10mm) fixed with araldite at the back of each tile & finishing the joints with white cement mixed with colouring oxide if required to match the colour of tiles including roughening of concrete surface, if necessary or by synthetic adhesive & grout materials etc.B) WallWith Sand Cement Mortar (1:3) 15 mm thick & 2 mm thick cement slurry at back side of tiles using cement @ 2.91 Kg/Sq.m & joint filling using white cement slurry @ 0.20kg/Sq.m.(a) Area of each tile upto 0.09 Sq.mi) Coloured decorativekitchen 3.30m x1.20m = 3.90m²W.B.PWD schedule 2017, page no 64-/315-item no.35.B.a.i3rd corri. 35-36/96 item22.B.a.i 27 Supplying, fitting & fixing granite slab 15mm to 18mm thick in floor, lobby, stair, landing and treads etc. over 20mm (avg) thick base of cement mortar (1:2) laid with white cement slurry @ 4.40Kg per Square meter before placing of granite and jointed with white cement slurry @ 2.0 Kg per square meter with necessary pigments and complete as per direction of Engineer-in-charge including cost of all materials, labours, curing and roughening of concrete surface complete.In ground floor(a) Area of each Granite slab up to 0.60 Square meters.Kitchen slab2/ 3.30mx 1.4m = 4.60m²W.B.PWD schedule 2017, page no 63/315-item no.34.a 28 Removing loose scales blisters etc. from old painted surface and thoroughly smoothening the surface to make the same suitable for receiving fresh coat of paint.W.B.PWD schedule 2017, page no 203/315-item no.1 29 ) Priming one coat on timber or plastered surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc.portico4.2m x 4.0m = 16.80m² Elec.room Ceiling 3.45m x 4.45m = 15.35m²internalWall elec.room 14mx 2.90m =40.60m²ext. wall elect Room14.6m x 3.10m =45.26m²kitchen internal wall7.85m x 2.40m = 18.84m² external .wall 65.0m x 3.0m = 195.0m²331.85m²W.B.PWD schedule 2017, page no 200/315-item no.1.b 30 Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : a) On timber or plastered surface : (ii) Two coats (withwhite shade)CeilingRooms5/ 5.50 x 4.70 = 105.75m²dressing , w/c4/ 2.50m x 2.50 = 25.00m² Passage5.50m x 1.20m = 6.60m²Wall Dinning/kitchen8/ 5.0m x2.6m= 104.00m² External wall60m x 4.50m = 270.00m²Portico 4.2m x 4.0m =16.80m²Panel door both side 5/0.9m x 2.0m x2.6= 23.40m²Glazed door 5/1.8m x 1.20m =10.80 m²Total562.35m²W.B.PWD schedule 2017, page no 200/315-item no.2.A.a.ii 31 Copal varnish of approved quality including preparing surface :(ii) On old varnish surface including removing old varnish and exposing original surface : pelmet40.0m x 0.17m = 6.80 m² Bed /drawing room12/4.04mx 3.0 =145.44m²W5(bed room)= 8 x 1.0m x 1.5m = 12.00m²164.24m²W.B.PWD schedule 2017, page no 202/315-item no.10.ii.b 32 Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturers specification and as per direction of Engineer-in-Charge to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidentalCharges but excluding the cost of primer. Elec.room Ceiling 3.45m x 4.45m = 15.35m²internalWall elec.room 14mx 2.90m =40.60m²ext. wall elect Room14.6m x 3.10m =45.26m²kitchen internal wall7.85m x 2.40m = 18.84m²Kitchen ext.wall 16.0m x 2.5m = 40m² Gurd roomCeiling3/3.20 x 2.95m = 28.32m²Guard room int. wall16/3.20mx 2.95m = 151.04m²Guard room ext. wall2/5.8m x 3.0m = 34.80m² 2/6.0m x 3.0m = 36.00m²410.21m² W.B.PWD schedule 2017, page no 197/315-item no.17.c 33 Plaster (to wall, floor, ceiling etc.)with sand and cement mortar includingrunding off or chamfering corners as directed and raking out, joints including throating, nosing and drip course, scaffolding/ staging where necessary ( Ground floor). [ Excluding coast of chipping over concerete surface](iii) With 1:3 cement mortar 20mm th.plasterElec.room Ceiling 3.45m x 4.45m = 15.35m²internalWall elec.room 14mx 2.90m =40.60m²ext. wall elect Room14.6m x 3.10m =45.26m²kitchen internal wall7.85m x 2.40m = 18.84m²Kitchen ext.wall 16.0m x 2.5m = 40.00m²Plinth protection 70.00mx 0.8m = 56.0m²saucer drain70.00m x 0.3m= 21.0m² 237.05m²PWD schedule 2017, page no 189/315-item no. 1.iii.a3rd corri. 49-50/96, item 1.iii.a 34 Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materials (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.Fittings c) Bend 87.5 degree ii) 110 mm. Dia. 35 Fittings c) Bend 87.5 degree ii) 110 mm. Dia.a) Plain Tee iii) 160 mm. Dia. 36 iii) 160 mm. Dia.(pipe for gutter )W.B.PWD scheor dule 2017, page no 212/315-item no.21.B.c & A.ii 37 Surface Dressing of the ground in any kind of soil including removing vegetation inequalities not exceeding 15 cm depth and disposal of the rubbish within a lead upto 75 m as directed. 12.0m x 3.5m = 42m²W.B.PWD schedule 2017, page no 1/315-item no.1 38 Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, leveling, dressing and ramming the bottom, bailing out water as required complete.Coln footing : 6nos x 1.0m x 1.0m x 1.30m = 7.80m³ Plum wall(front) 12.0 m x 0.75 m x 0.6m = 5.40m³Plum wall(back)12.0 m x 0.9 m x 0.9m = 9.72m³Slope dressing 1/3 (12.0m x 3.20m x 3.0m)= 38.40m³Approach path 2/40m x 0.3m x0.3m= 7.20m² 68.52m³W.B.PWD schedule 2017, page no 1/315-item no.2.a 39 Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work)895 With earth obtained from excavation of foundation.For foundation 1/5th of excavation=13.70m³Drain filling 12.0m x 0.6mx 0.75m = 5.40m³ 19.10m³W.B.PWD schedule 2017, page no 1/315-item no.3.a 40 Labour for 150mm to 200mm boulder soling including rough dressing hand packing and ramming down small pieces in the interstices including rolling and preparing the bed to proper level and filling up all joints with sandy clay or earth. Footing6 /1.0m x 1.0m = 6.0m²plum wall12.0m x 1.2m =14.40m²floor electric mtr room 3.0mx 4.0m = 12.00m²floor kitchen extension 5.35m x 1.80m = 9.63m²42.03m²Carriage of analysis rate road schedule leads 85kms 0 Km to 5Kms = Rs. 124.00/m³ 5Km to 10Kms= Rs. 75.00/m³10Kms to 20Kms =Rs. 148.00/m³20Km to 50Kms = Rs. 405.00/m³50Km to 85Kms = Rs 456.75/m³Coast of boulder 30/40 kg =Rs. 349/m³ Loading /unloading= Rs. 62.00/m³ Rs.1619.75/m³ x 0.15 = Rs. 242.96/m²Labour rate as per schedule = Rs.18.00/m²Rs. 260.96/m²1% cess Rs.2.60/m² Rs.263.56/m² 41 Cement concrete with 30 mm downgraded shingles excluding shuttering. N.B. Varietyfooting 6 /1.0m x 1.0m x 0.075m = 0.45m³plum wall 12.0m x 1.2m x 0.075 =1.08m³floor electric mtr room 3.0mx 4.0m x 0.075m = 0.9m³floor kitchen extension 5.35m x 1.80m x 0.075m = 0.48m³4.11m³W.B.PWD schedule 2017, page no 34-35/315-item no.22.II. 42 Hire and labour charges for shuttering with centering and necessary staging up to 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out aftercompletion of works (upto roof of ground floor)coln.6nos x 4sides x 0.3m x 3.5m = 25.20m²plinth/tie beam 0.3m x 163.0m = 48.90m²plum wall12.0m x 4.5m = 54.00m²elec. Room slab 4.0m x 5.0m = 20.00m²148.10m²W.B.PWD schedule 2017, page no 42/315-item no.36.a. 43 Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 monomial size) excluding shuttering and reinforcement, if any, in ground floor as per relevant IS codes.Col,1st. footing 6/1.0mmx 1.0m x 0.35m = 2.10m³Col. 2nd footing 6/1.0m x 0.4mx 0.4m = 0.96m³Col.6/3.5mx 0.25 x 0.3 = 1.575m³ Elec.roomTie/plinth beam2/14.2m x 0.25m x 0.35m = 2.485m³Kitchen extension 2/16.7m x 0.25m x0.35m =2.92m³FloorElec.room 3.0m x 4.0m x 0.10m = 1.20m³Floor kitchen extension 5.8m x 1.5m x 0.1m = 0.87m³Plinth FRH60.0m x 0.4mx 0.075 = 1.80m³13.91m³W.B.PWD schedule 2017, page no 24/315-item no.4.bCorrigendum 10/96 item 27.b 44 Plum concrete work with 40 % cement concrete with 30 mm downgraded stone metal and 60 % stone boulder of size 150 mm and above placed in position as directed excluding shuttering if any.Front wall12m x 0.6 m x 1.50m = 10.80m³Back wall12mx 0.9m x 3.4m = 36.72m³Wall foun.12.0mx 1.10mx 0.7m =9.24m³ 56.76m³ W.B.PWD schedule 2017, page no 27/315 item no 11. Corr.sl no 13/96 item no 34 45 Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS Plinth protection70m x 0.75mx 0.05m = 2.62m³Elec.room roof slab4.0m x 5.0m x 0.1m =2.00m³Saucer Drain 70m x 0.25m x 0.2m = 3.50m³ 8.12m³ W.B.PWD schedule 26/315 item no 10.ii Corrigendum12-13/96.sl no 33.ii 46 Neat cement punning about 1.5mm thick in wall, dado, windowPlinth protection 70m x 0.75m = 52.50m²Saucer drain70m x 0.3m = 21m²73.50m²NOTE:Cement 0.152 cu.m per100 sq.m. W.B.PWD schedule 192/315 item no 15 47 Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction.Vol. conc item no 7 = 13.91m³Vol.conc item no 9. Elec room=2.00m³ Total 15.91m³Reinforcement @ 1% of cement concrete [15.91m³ x 1 x 78.5]= 1.25MT 1000W.B.PWD schedule 43/315 40 Corr.sl no 1 48 125 mm. thick brick work with 1st class bricks in cement mortar (1:3) in ground floor.Kitchen extension 15.0m x 2.50m = 37.50m²Elec.room 15.0mx 2.50m = 37.50m²75.00m²Less door 2/0.9m x 2.0m =3.60m²Less window 3/1.20mx 1.10m = 3.96m² 67.44m²W.B.PWD schedule 16/315 item no 17 Corrigendum3/96.sl no 9 49 Part –BSanitary and PlumbingSupplying, fitting and fixing Anglo-Indian W.C. in white glazed vitreous chinaware of approved make complete in position with necessary bolts, nuts etc.b) With S trap (with vent)PWD schedule 2017vol.II, page no79/124/item no 3.b 50 Supplying, fitting and fixing Closet seat of approved make with lid and C.P. hinges, rubber buffer and brass screws complete. (b) Anglo IndianPWD schedule 2017vol.II, page no81/124/item no 10.b.ii 51 Supplying, fitting and fixing 10-liter porcelain low-down cistern of approved make with side or bottom inlet, side overflow, brackets complete with all internal PVC fittings. WhitePWD schedule 2017vol.II, page no36/124/item no 1 52 Supplying, fitting and fixing White Vitreous China Sink in position on C.I. brackets including two coats of painting of brackets. a) Plain edge sink with overflowii) 610 mm X 450 mm X 250 mmPWD schedule 2017vol.II, page no42/124/item no 5.a.ii 53 Supplying,fitting and fixing approved brand P.V.C. CONNECTOR whiteflexible, with both ends coupling with heavy brass C.P. nut, 15 mm dia.v) 900 mm longPWD schedule 2017vol.II, page no43/124/item no 9.v 54 Supplying, fitting and fixing approved brand 32 mm dia.P.V.C. Waste pipe, with PVC coupling at one end fitted with necessary clamps.PWD schedule 2017vol.II, page no43/124/item no 10.iv 55 e) (i) CP Centre hole Basin mixture with regular spout without popupwaste system with 450 mm long braided hoses. (Equivalent to Code No.5167 (B) & Model - FLORENTINE of JAQUAR or similar brand).PWD schedule 2017vol.II, page no45/124/item no 19e.i 56 e) (ii) CP Wall Mixture without spout but with provision for connection to Telephone Shower and exposed pipe for Overhead shower (Equivalent toCode No. 5215 & Model - FLORENTINE of JAQUAR or similar brand).PWD schedule 2017vol.II, page no45/124/item no 19e.ii 57 Supplying, fitting and fixing complete Bottle waste trap (Heavy Quality) (a) Chromium plated Bottle trap 32 mm with 190 mm long connecting pipeand wall flange (Equivalent to Code No. 545 & Model - Tropical /Sumthing Special of ESSCO or similar brand).PWD schedule 2017vol.II, page no44/124/item no 15 58 Supplying, fitting and fixing liquid soap container.(a) Cromium plated.PWD schedule 2017vol.II, page no82/124/item no 17.a 59 Supplying, fitting and fixing soap holder.a) PTMT (Prayag or equivalent)PWD schedule 2017vol.II, page no82/124/item no 18.a 60 Supplying, fitting and fixing best quality Indian make mirror 5.5 mm thick with silvering as per I.S.I. specifications supported on fiber glass frame of any colour, frame size 550 mm X 400 mmPWD schedule 2017vol.II, page no82/124/item no 19 61 Supplying, fitting and fixing Toothbrush and Tumbler holder of approved make of size 140 mm X 65 mm (porcelain).PWD schedule 2017vol.II, page no82/124/item no 20 62 Supplying, fitting and fixing towel rail with two brackets.a) C.P. over brass(iii) 25 mm dia. and 750 mm longPWD schedule 2017vol.II, page no82/124/item no 22.a.iii 63 Supplying, fitting and fixing porcelain toilet paper holder of approved make with wooden spindle as necessary.(iii) Recess roll type size 150 mm X 150 mmPWD schedule 2017vol.II, page no82/124/item no 23.iii 64 Supplying, fitting and fixing bathroom shelf of approved make of size 580 mm X 150 mm (porcelain).PWD schedule 2017vol.II, page no82/124/item no 25 65 Supplying, fitting and fixing pillar cock of approved make.a) (ii) CP Pillar Cock Super Deluxe with Aerator - 15 mm. (Equivalent to Code No. 508 & Model No. Tropical / Sumthing Special of ESSCO or similar brand).WBPWD SCH.VOL-II PAGE 45/124 ITEMNO 19.a.ii 66 Supply of G. I. pipes of TATA make including necessary sockets 15 mmdiaWBPWD SCH.VOL-II PAGE 102/124 ITEMNO 1. a.ii 67 g) CP Sink Cock with Regular Swinging Spout (Table Mounted Model) (Equivalent to Code No. 5357 of JAQUAR or similar brand).WBPWD SCH.VOL-II PAGE 45-46/124 ITEMS NO 9.g 68 Supplying, fitting and fixing bibcock or stopcock.(a) (i) Chromium plated Bib Cock short body (Equivalent to Code No. 511 & Model - Tropical / Sumthing Special of ESSCO or similar brand).PWD schedule Vol II 2017, page no 6/124-item 7 69 Supplying, fitting and fixing stainless steel sink complete with waste fittings and two coats of painting of C.I. bracketsb) Sink with drain board 1050 mm X 450 mm X 180 mmPWD schedule Vol II 2017, page no 42/124-item 6 70 Supplying, fitting and fixing shower of approved brand and make.b.Chromium plated Rose shower with revolving joint and 150 mm long shower arm (Equivalent to Code No. 5489 & Model - Florentine of Jaquar or similar brand).PWD schedule Vol II 2017, page no 3-4/124-item iii.b 71 Chromium plated Hand shower with Flexible Tube &fittings(Equivalent to Code No. Hsh-1937 & (Equivalent to Code No. 5037 & Model - Florentine of Jaquar or similar).).PWD schedule Vol II 2017, page no 3-4/124-item d. 72 Hand Shower(Health Faucet) with 1mtr Fexible Tube with Wall Hook(Equivalent to Code No.573 & Model -ALLIED of Jaquar or similar).PWD schedule Vol II 2017, page no 3-4/124-item f. 73 Chromium plated Bib Cock (angular shape with wall flange)(Equivalent to Code No. 5037 & Model - Florentine of Jaquar or similarbrand).PWD schedule Vol II 2017, page no 6/124-item 7.c 74 Supply of Chlorinated Polyvinyl Chloride (CPVC) pipes& fittings conforming to IS-15778: 2007(B) SocketPWD schedule Vol II 2017, page no 30/124-item 2.B 75 (C) Equal TeePWD schedule Vol II 2017, page no 30/124-item 2.C 76 I) Tank connecting nipple 25 mmPWD schedule Vol II 2017, page no 31/124-item. I 77 (Q) Ball ValvePWD schedule Vol II 2017, page no 33/124-item Q 78 (U) Male threaded adopter 15mmPWD schedule Vol II 2017, page no 34/124-item U 79 (V) Female threaded adopterPWD schedule Vol II 2017, page no 34/124-item V 80 Supplying, fitting and fixing CPVC (ChlorinatedPolyvinyl Chloride) pipes of approved make conformingto IS-15778: 2007 . with all necessary accessories,specials viz. socket, bend, tee, union, cross, elbo, nipple,longscrew, reducing socket, reducing tee, short piece etc.fitted with holder bats clamps, including cutting pipes,fitting, fixing etc. complete in all respect including costof all necessary fittings as required,jointing materials inany position above ground. (Payment will be made onthe centre line measurements of total pipe line includingall specials. No separate payment will be made foraccesories, specials.(a) For Exposed Work15 mm diaPWD schedule Vol II 2017, page no 29/124-item 1. 81 Supplying P.V.C. water storage tank of approved quality with closed top with lid (Black) – MultilayerPWD schedule Vol II 2017, page no 37/124-item 6.b 82 Supply of UPVC pipes (B Type) & fittings conforming to IS-13592-1992ii) Double Socketed 3 Meter Length(b) 110 mmPWD schedule Vol II 2017, page no 69/124-item.ii.b 83 B) Fittingsx) Bend 87.5ºb) 110 mmPWD schedule Vol II 2017, page no 71/124-item x.b. 84 Labour for fitting and fixing U.P.V.C. pipes for above ground work including cost of jointing materials etc. fitting and fixing all necessary specials, cutting pipes, cutting holes in walls or R.C. floor where necessaryand mending good all damages excluding the cost of masonry or concrete work, if necessary, but including the cost and fitting and fixing holder bat clamps (any floor) or for underground work including cutting trenches upto 1.5 metre and refilling the same complete as per direction of the Engineerin- charge. (Payment will be made on centre line measurement of the totalpipeline including specials.(ii) 110 mm dia.PWD schedule Vol II 2017, page no 74/124-item 24.A.ii 85 Add SGST @ 9% 86 Add CGST @ 9% 87 Labour cess @ 1%