| 1 | 0 | Part-A (Supply) | | | |
|---|
| 2 | 1 | Fabrication, Galvanizing, Inspection & Supply of 220 KV KPTL DC Towers including stubs and template | | | |
|---|
| 3 | 1.01 | KPTL DC Tower (02 Nos. B type towers) | | 22.6 | MT |
|---|
| 4 | 1.02 | Cost of nuts and bolts | | 1 | MT |
|---|
| 5 | 2 | Tower Accessories | | | |
|---|
| 6 | 2.01 | Number Plate | | 2 | No. |
|---|
| 7 | 2.02 | Danger Plate | | 2 | No. |
|---|
| 8 | 2.03 | Phase Plate in set of Red, Blue and Yellow | | 2 | Set |
|---|
| 9 | 2.04 | Pipe Type Earthing Material | | 2 | No. |
|---|
| 10 | 3 | Hardware suitable for ACSR Zebra Conductor | | | |
|---|
| 11 | 3.01 | Single Tension Fitting | | 18 | No. |
|---|
| 12 | 3.02 | 160 KN Polyner Insulator String | | 18 | No. |
|---|
| 13 | 3.03 | Repair Sleeve | | 4 | No. |
|---|
| 14 | 3.04 | Vibration Damper | | 18 | No. |
|---|
| 15 | 3.05 | Mid Span Compression Joint | | 2 | No. |
|---|
| 16 | 4 | Earth Wire Accessories suitable for 7/10 SWG Earth Wire | | | |
|---|
| 17 | 4.01 | Tension Clamp | | 4 | No. |
|---|
| 18 | 4.02 | Mid Span Compression Joint | | 2 | No. |
|---|
| 19 | 4.03 | Vibration Damper | | 4 | No. |
|---|
| 20 | 4.04 | Copper Bond | | 2 | No. |
|---|
| 21 | 5 | Part-B (Work) | | | |
|---|
| 22 | 5.011 | Survey including preparation of final tower schedule of material, marking of locations etc. | | 1 | Job |
|---|
| 23 | 5.012 | Check survey and final peg marking (Route Length) | | 1 | Job |
|---|
| 24 | 5.02 | Cost of excavation of 220 KV D/C KPTL tower foundation pits including all earth work, back filling and leveling | | 475 | CuM |
|---|
| 25 | 5.03 | Cost of concreting for B type 220 KV D/C tower founadation including cost of cement, dewatering, shuttering & curing but excluding cost of reinforcement bars. | | 125 | CuM |
|---|
| 26 | 5.04 | Installation of steel reinforcement bars in RCC foundation including cost of steel reinforcement bars with cutting, bending, placing, binding etc. | | 0.4 | MT |
|---|
| 27 | 5.05 | Cost of setting of Stubs including all foundation work but excluding cost of concreting and excavation (Rate per location) for 220 KV KPTL DC Towers | | 2 | No. |
|---|
| 28 | 5.06 | Erection of 220 kV KPTL D/C super structure of all type of towers and their extensions where ever required including all woks above ground level excluding hoisting of insulators and hardware. | | 22.6 | MT |
|---|
| 29 | 5.07 | Tack welding of all the bolts upto firs section of DC towers | | 2 | Job |
|---|
| 30 | 5.08 | Installation of Back stay | | 6 | Job |
|---|
| 31 | 5.09 | Dismantling of old 220 KV S/C towers | | 2 | Job |
|---|
| 32 | 5.1 | Destringing of 220 kV S/C ACSR Zebra conductor | | 4 | Span |
|---|
| 33 | 5.11 | Destringing of earthwire | | 4 | Span |
|---|
| 34 | 5.12 | Laying, tensioning, stringing,clamping, jointing etc complete with ACSR Zebra conductor DC/SC including hoisting of insulators, fitting of all necessary hardware & accessories etc. | | 4 | Span |
|---|
| 35 | 5.13 | Laying, tensioning, stringing,clamping, jointing etc complete with ground wire including hoisting of all necessary hardware & accessories for 1 no. 7/3.25 mm G.S earthwire. | | 4 | Span |
|---|
| 36 | 5.14 | Grounding Work including earth work for pipe type earthing | | 2 | No. |
|---|
| 37 | 5.15 | Excavation of earth 1.0 to 1.5 mtr deep around old tower stub in 2 mtr dia and breaking of old foundation & chimney up to 1.5 mtr to 2.0 mtr, cuting old stub by gas cutted collection of broken concrete in gunny begs and its disposal outside of field and back filling and leveling of earth to resstore both the embankment of canal and for ensuring alignment with exiting A type tower no. 26 | | 2 | Job |
|---|
| 38 | 5.16 | Transportation of condutor, earthwire from UPPTCL Store to Site including MCD toll and other applicable taxes in Delhi. | | 1 | Job |
|---|
| 39 | 5.17 | Transportation of cold dismantalled tower parts, conductor, earthwire and all accessories from Site to UPPTCL Store including MCD toll and other applicable taxes in Delhi. | | 1 | Job |
|---|