BRR : 4768390
Click Here To View Tendering Authority. Aoc City/State :  bareilly, Uttar Pradesh
Tender Brief : Work Of Replacement Of Damage Cable Lug, Tail Less Unit Etc For Preventive Maintenance Of Distribution T / F & For The Work Of New Proposed T / F ( 02 No ) & Increasing Capacity Of T / F ( 03 No. ) In Different Areas Of Eudd-I, Bareilly For System Strengthening For Providing Uninterrupted 24*7 Power Supply Under The Head Of ( B.P. 2023-2024 ) =-2 Lt Cable Size 1X240 Mm2 3 Lt Cable Size 1X400 Mm2 4 Lt Cable Size 1X630 Mm2 5 Lt Cable Size 1X1000 Mm2 6 Lt Cable Size 3.5X150 Mm2 7 Lt Cable Size 3.5X240 Mm2 8 Lt Cable Size 3.5X400 Mm2 9 Ms Channel 100X50 For... Read More
Tender Value
53,63,000
Contract Value
₹ 43,83,010
Saving / Difference
₹ 9,79,990 ▲
Submission Date
06-10-2023
Contract Date
15-03-2024
Completion Date
365 days
Participated Bidder List
4 No of Bidder(s)
Sr No. Bidder Name Bid Analytics Technical Bid Financial Bid AOC Bid Value Rank
1 cnet-technologies Bid Analytics 52,87,465 L3
2 cnet-technologies Bid Analytics 43,83,010 L1
3 cnet-technologies Bid Analytics 48,26,700 L2
4 cnet-technologies Bid Analytics
Work Detail
work of replacement of damage cable lug, tail less unit etc for preventive maintenance of distribution t / f & for the work of new proposed t / f ( 02 no ) & increasing capacity of t / f ( 03 no. ) in different areas of eudd-i, bareilly for system strengthening for providing uninterrupted 24*7 power supply under the head of ( b.p. 2023-2024 ) =-2 lt cable size 1x240 mm2 3 lt cable size 1x400 mm2 4 lt cable size 1x630 mm2 5 lt cable size 1x1000 mm2 6 lt cable size 3.5x150 mm2 7 lt cable size 3.5x240 mm2 8 lt cable size 3.5x400 mm2 9 ms channel 100x50 for mounting of tail less unit 10 erection work 11 fabrication and erection ofms channel 100x50 ( total 3700 kgs. ) for mounting of tail less unitfor distribution t / f . 12 dismantling and removing ofold and damaged lt cable from transformerandfixing of new ltcable size ( 1x240mm2 ) 13 dismantling and removing ofold and damaged lt cable from transformerandfixing of new ltcable size ( 1x400mm2 ) 14 dismantling and removing ofold and damaged lt cable from transformerandfixing of new ltcable size ( 1x630mm2 ) 15 dismantling and removing ofold and damaged lt cable from transformerandfixing of new ltcable size ( 1x1000mm2 ) 16 dismantling and removing ofold and damaged lt cable from transformerandfixing of new ltcable size ( 3.5x150 mm2 ) 17 dismantling and removing ofold and damaged lt cable from transformerandfixing of new ltcable size ( 3.5x240mm2 ) 18 dismantling and removing ofold and damaged lt cable from transformerandfixing of new ltcable size ( 3.5x400mm2 ) 19 replacementof old damaged tail less unit & fixing new tail less unit ( 300 amp ) with material at m.s channel frame along with providing and fixing fuse wire ( 10 swg / 12 sgw / 14 sgw ) . ( all the material will be arranged by the contractor at his own cost ) . 20 replacementof old damaged tail less unit & fixing new tail less unit ( 500 amp ) with material at m.s channel frame along with providing and fixing fuse wire ( 10 swg / 12 sgw / 14 sgw ) . ( all the material will be arranged by the contractor at his own cost ) . 21 replacement of old damaged tail less unit ( 800 amp ) with material. at m.s channel frame along with providing and fixing fuse wire ( 10 swg / 12 sgw / 14 sgw ) . ( all the material will be arranged by the contractor at his own cost ) 22 replacement of old damaged copper l-piece & fixing of newcopper l-piece ( 50x225x10mm ) with material. ( all the material will be arranged by the contractor at his own cost ) 23 replacement of old damaged copper l-piece & fixing of newcopper l-piece ( 62x225x12mm ) with material. ( all the material will be arranged by the contractor at his own cost ) 24 replacement of old and damaged al lugs and fixing new al lugs suitable for 150 mm2 with material. ( all the material will be arranged by the contractor at his own cost ) . 25 replacement of old and damaged al lugs and fixing new al lugs suitable for 240 mm2 with material. ( all the material will be arranged by the contractor at his own cost ) . 26 replacement of old damaged al lugs suitable for 400 mm2 with material. ( all the material will be arranged by the contractor at his own cost ) . 27 replacement of old damaged al lugs suitable for 630mm2 with material. ( all the material will be arranged by the contractor at his own cost ) . 28 replacement of old damaged al lugs suitable for 1000 mm2 with material. ( all the material will be arranged by the contractor at his own cost ) . 29 for the work of one side of complete fencing of damaged side fencing of existing distribution t / f . ( all the material will be arranged by the contractor at his own cost ) .. 30 repair of damaged plinth complete, by providing first class bricks work as per respo norms. ( material will be supplied by contractor ) . 31 chemical earthing of t / f neutral including all materials ( chemical, gi pipe, gi strip, nut bolt, etc ) 32 supply & fixingofm.s clamps with nut & bolts. 33 workofincreasingcapacity of distribution t / f of different capacity in the different area of under eudd-i bareilly. 34 carriage of following materials from e.s.cs store c.b ganj to work site including loading & unloading 35 new 250 kva t / f 36 new 400 kva t / f 37 dismantling ofold 100 kva t / f from site and back carriage from site to e.s.cs store c.b ganj including loading & unloading 38 dismantling ofold 250 kva t / f from site and back carriage from site to e.s.cs store c.b ganj including loading & unloading 39 construction of plinth complete ( 2.0x2.0x1.5 ) meter, by providing firstclass bricks work as per respo norms. ( material will be supplied by contractor ) . 40 the work of fabrication / construction and grouting of wire mesh fencing of 16 meter running length / as per site requirement in rectangular shape height 2 meter with angle size of 45x45x05 m.m including gate at one side as per respo norms. ( material will be supplied by contractor ) . 41 erection ofnew 250 kva t / f on plinth by laying of cable , jumpering & commissioning of t / f . 42 erection ofnew 400 kva t / f on plinth by laying of cable , jumpering & commissioning of t / f. 43 earthing of distribution t / ffor body & neutral upto water level with gi pipe of 1.5 dia. including mild steel strip size 35x6 mm. ( material will be supplied by contractor ) . 44 providing and fixing of tell-less unit ( 500 amp. ) 45 providing and fixing al. lugs ( for 400 sqmm. ) cable 46 providing and fixing al. lugs ( for 630 sqmm. ) cable 47 workofincreasingcapacity of distribution t / f of different capacity in the different area of under eudd-i bareilly. 48 carriage of following materials from e.s.cs store c.b ganj to work site including loading & unloading 49 new s.t. pole 11 meter long. 50 acsr weasel conductor. 51 a.b cable ( 3x120 sqmm. ) 52 new 250 kva t / f 53 3-phase distribution box 54 other associatedmaterials 55 erection of s.t. transformer d / pole including digging of pit & grouting work complete and fitting of all accessories complete. 56 concreting of st poles. 57 earthingofpoles . 58 construction of plinth complete ( 2.0x2.0x1.5 ) meter, by providing firstclass bricks work as per respo norms. ( material will be supplied by contractor ) . 59 earthing of distribution t / ffor body & neutral upto water level with gi pipe of 1.5 dia. including mild steel strip size 35x6 mm. ( material will be supplied by contractor ) . 60 erection of 250 kva t / f on plinth by laying of cable , jumpering & commissioning of t / f . 61 the work of fabrication / construction and grouting of wire mesh fencing of 16 meter running length / as per site requirement in rectangular shape height 2 meter with angle size of 45x45x05 m.m including gate at one side as per respo norms. ( material will be supplied by contractor ) . 62 stringing and sagging acsr weasel conductor 63 stringing & sagging of a.b cable ( 3x120 sqmm ) 64 providing and fixing of tell-less unit ( 600 amp. ) 65 providing and fixing al. lugs ( for 400 sqmm. ) cable 66 erection and fixing 3-phase distribution box and making all connections 67 erection of stay set complete. 68 fixing of associated items i.e. dropper channel-02 no., pin insulator- 06 no. disc insulator- 06 no., top channel- 02 no., 11 kv tpmo- 02 no., 11 kv fuse set- 02 no. etc.
View Original Notice/Document
Result Documents
Tender Documents
Download File Name File Description
Download fefbcc03-4917-4800-a0d8-8f94c7f7ab54
Download File Name File Description
Download d3317089-c2c1-4e63-abc1-1f40d6fcd7a7 Tender Documents
Download BOQ_1400790 Tender Documents
Download Tendernotice_1 Tender Documents
Download Tender_form Tender Documents
Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount : ₹ 1,00,00,000