| 1 | जंगल की सफाई, भारी झाड़ियों तथा 30 से.मी. लपेट तक के पौधों को काटने समेत। |
| 2 | Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m in dry or moist including dressing of excavated area, dewatering wherever required complete in all respect. Hard soil |
| 3 | जे.सी.बी. मशीन/ट्रेक्टर मय स्क्रेपर द्वारा मिटटी खुदाई कार्य, खोदी हुई मिटटी के डगलों को तोडने (Breaking of clods), घास एवं कंकर, पत्थर को अलग करना (Sorting of grass & pebbles) एवं बण्ड (Bund) का सेक्शन (काट क्षेत्रफल में)/प्रोफाइल संधारित करना मय चढाना एवं उतारना प्रारंभिक लीड 250 मी. एवं लिफ्ट 3 मी. तक। Draft based on chapter 5th of irrigation page number 32 to 34 (दिनाँक 01/02/2017 से मान्य) ईकाई 1 घन मी. मशीनरी कार्य सख्त मिट्टी (in Hard Soil) |
| 4 | Compaction of earth by or plain roller Excluding water ( Density 90 % of Proctor) |
| 5 | Watering of earth including cost of carriage of water when source of water lead upto 5 km |
| 6 | Seed sowing of trees species on mounds of ditch / dola/fencing,trenches, V ditches etc at the spacing of 30 cm |
| 7 | Cost of seed / Dhaman/ Stylohamata |
| 8 | सीमेंट कंक्रीट 1 सीमेंट, 4 बजरी तथा 8 गिट्टी पत्थर की 20 मिमी नामीय माप की नींव में डालना,कूटना तथा तराई आदि सहित एनीकट के लिए। |
| 9 | सीमेंट कंक्रीट 1 सीमेंट, 3 बजरी तथा6 गिट्टी पत्थर की 20 मिमी नामीय माप की नींव में डालना,कूटना तथा तराई आदि सहित एनीकट के लिए। |
| 10 | सीमेंट कंक्रीट 1:2:4 मिश्रण की प्रवलित सीमेंट कंक्रीट में डालना तथा आपूर्ति करना, छत की स्लैब, छज्जे, बीम, लिंटल आदि में दबाना, तराई करना तथा सतह को 1:3 सीमेंट मसाले से समतल करना आदि समेत पाडबन्दी सहित परन्तु स्टील तथा शटरिंग की कीमत अलग से।Superstructure |
| 11 | सेन्टरिंग'शटरिंग (तख्ता एवम ढुलाबंदी) का आर.सी.सी. छत, स्लेब, छज्जे, लिन्टल आदि डालने के लिए लगाना 4.5 मीटर ऊचाई तक के लिए तथा हटाना आदि विशेष विवरण के अनुसार। |
| 12 | आर.सी.सी. काम के लिए लोहे को काटना, मोड़ना तथा स्थान पर लगाना तथा बांधने का कार्य मय आपूर्ति के । |
| 13 | Construction of TUBE-WELL upto 100m depth and above in all type of rocks by DTH system and over burden to accomodate casing pipe of following size in all type of soils and over burden including lowering of casing pipe but excludind cost of casing pipe as per IS 2800 (part I & II ) 1979 spwcifications . The work should be completed after obtaining sand free water . The tube well should have a throughout bore as per nominal dia of casing pipe. 250 mm dia Nominal size (minimum bore size of 250 mm ) |
| 14 | Cement concerete (1:2:4) well mixed laid in posit- ion complete including all leads of all construc- tion materials including curing and finishing having well graded broken stone aggreate of maximum size upto 20 mm |
| 15 | Supplying and laying aggregate in layers and profile as specified including all leads & lifts. |
| 16 | River gravel 40 to 80 mm size |
| 17 | River gravel 20 to 40 mm size |
| 18 | River gravel upto 20 mm size |
| 19 | Supplying and laying sand in required profile including all lead & lifts |
| 20 | Supply & fixing Pre cast RCC ring at mouth of recharge shaft of M20 mix with 40 mm thickness 900mm dia |
| 21 | Providing &Fixing rigid PVC pipe dia. 75 mm |
| 22 | S/F of strainer pipes made of ERW MS black pipe ISI mark of 150 mm dia nominal bore size at the site of work including required size of slottings as per IS : 81110- 1985 |
| 23 | Bricks masonary in cement mortar 1:6 for Foundation and Superstructure. |
| 24 | Cement plaster in cement sand mortar 1:4, 20mm thick. |