| 1 | Cutting & clearance of jungle, bushes, shrubs Ankra/Ipomoea, Julicflora typna etc. on canal and bunds in dry/moist/slushy conditions including disposal as per instructions of the Engineer-in-charge. Cost of wood has been deducted from rates and thus will be property of contractor after cutting. (a) Ordinary |
| 2 | Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m in dry or moist including dressing of excavated area, dewatering wherever required complete in all respect.For Soft/Loose soil |
| 3 | Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m in dry or moist including dressing of excavated area, dewatering wherever required complete in all respect.For Hard/dense soil |
| 4 | Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m in dry or moist including dressing of excavated area, dewatering wherever required complete in all respect.For Hard soil mixed with Kankar / boulders, Morrum |
| 5 | Providing and Laying in position of Cement concrete Nominal mix (1:3:6) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto40mm |
| 6 | Side shuttering including propping etc. complete (to achieve finish F 2 for Curved edges or sides of special shapes like baffle or chute blocks, end sills, Basin Block, projected copings, extended sills, curved surfaces arches, circular ducts etc. |
| 7 | Supplying of M.S. reinforcement including labour charges for bending binding and placing in position all reinforcement as per drawing including cost of binding wire and all leads and lifts using. Tor or ribbed bars (IS :1786) |
| 8 | Providing and Laying in position of Cement concrete Design mix M- 15 including leads of all construction materials, plasticizers (if required), curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto; (For mix design Cement content considered 320 kg/ cum of concrete) (d) 20 mm |
| 9 | Extra labour charges for RCC due to obstruction in laying and placing the reinforced cement concrete due to reinforcement (a) In foundation rafts, beams, columns bases stilling basins, buckets, aprons etc. (non suspended horizontally laid mass concrete) |
| 10 | Earth work in rough (borrow area) excavation for embankments in hard soil, morrum or highly weathered strata dry or moist, including laying in 20 cm layers (before compaction) and breaking of clods, sorting of grass, pebbles etc. and dressing when compacted by vibro compactor, vibro sheep foot roller, sheep foot roller/pneumatic tyred roller to obtain dry density of at least 98% of Standard Proctor's density with initial lift of 1.5m (Excluding charges for compaction and watering) including loading and un-loading wherever required complete in all respect. (c) With lead beyond 750 m and up to 1250 m (for average lead 1 Km) Deduct in item no 16 (a) to (d) above if Standard Proctor's density to be achived is at least 90% |
| 11 | Compaction of earth or highly weathered strata (a) By manually or plain roller. (density 90% of Proctor) |
| 12 | Watering of earth including cost of carriage of water when source of water (a) up to 1 km |
| 13 | Supplying, Laying & consolidation of quarry rubbish / Murrum / Murda to required grade & camber in layers not exceeding 15 cm. thickness (loose) by road roller as per specifications including dressing etc. complete Please Enable Macros to View BoQ information |