| 1 | Fitting and erecting one HT PSC Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through Vcross arm to the ground for earthing (excluding provision of earthing). |
| 2 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Laterite. |
| 3 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 4 | Renewal of existing damaged/broken old 11kV Stay to the existing stay rod. |
| 5 | Renewal of existing damaged/old 11kV Stay with new stay in place including excavation & backfilling of pit, dismantling, refitting of all items and conveyance of all materials. |
| 6 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 7 | Fitting one set AB switch on existing DP, giving connection and drawing sufficient length of GI earthing leads to the ground for earthing, excluding provision of earthing. |
| 8 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 9 | Fitting one Additional2.4/3m Channel cross arm (75x40x6mm), in existing 11kV DP including conveyance of materials. |
| 10 | Additional rate for refitting/redoing one Disc set while renewing any type of 11kV cut pole. |
| 11 | Fitting and providing one HT Fly stay for 11kV pole using HT PSC pole including digging and back filling pits in ordinary soil, drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing). |
| 12 | Stringing of one km 3 PH 11kV line with XLPE Insulated ACSR Raccoon or equivalant (3 conductors) after fitting insulators, binding conductors to pin insulators using suitable tie and anchoring with wedge type anchoring clamps including cutting and removing tree branches wherever necessary excluding cut point works. |
| 13 | Doing one cable end termination on HT ABC of sizes Up to 3x150+1x120 sqmm and connecting to existing MVT or other terminals,using the cable end termination kit supplied departmentally including charges for cable jointer etc. complete as per the direction of the departmental officers. |
| 14 | Fitting and providing one Strut using HT PSC pole including digging and back filling pit in ordinary soil. |
| 15 | Providing one Coil Earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 16 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling. |
| 17 | Additional rate for excavation of one Earth Pit (2.5m depth) in Laterite. |
| 18 | Erection of Anchor clamp / dead end clamp for 11kV ABC of any size |
| 19 | Dismantling one suspension clamp from 11 KV ABC |
| 20 | Erection of suspension clamp for 11KV ABC of any size |
| 21 | Providing Cable Tie |
| 22 | Fiting One No MVT on existing cross arm excluding termination work (for One phase) of any rating for 11 kV AB Cable |
| 23 | Half rate of Key 2046 Errection and commissioningof street light metering with timer Set |
| 24 | Fitting one set (3No.) 11kV LA and giving connections excluding earthing. |
| 25 | Dismantling One no MVT on existing cross arm (for One phase) of any rating for 11 kV AB Cable (Half rate of Key no. 27.1) |
| 26 | Providing bridging at Cut points for 3 PH 11kV line with XLPE Insulated ACSR Raccoon or equivalent (1 conductors) using IPC and respective conductors |
| 27 | Installation of Insulation piercing connector for main to service line main :16-95 sqmm, Tap 16-95 sqmm |
| 28 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 29 | Fitting Knee bracing or suitable support on existing HT or LT post. |
| 30 | Providing WP support with PSC pole including digging & back filling pit in ordinary soil. excluding transportation of poles. |
| 31 | Dismantling (without damage) one km 11kV line (three conductors) including dismantling cross arm, disc insulators, disconnecting jumper connection, rolling the conductor and stacking the materials. |
| 32 | Errection and commissining of street light metering with timer |
| 33 | Redoing single phase WP service connection complete including lowering down the guy wire portion, repairing or changing WP wire, GI wire, Fuse unit etc., changing Energy Meter cutout, neutral link etc., if necessary and reconnecting the same including conveyance of material to site from Section office at various location. |
| 34 | Redoing three phase WP service connection complete including lowering down the guy wire portion, repairing or changing WP wire, GI wire, Fuse unit etc., changing Energy Meter cutout, neutral link etc., if necessary and reconnecting the same including conveyance of material to site from Section office at various location. |
| 35 | Fitting and erecting one HT A type Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 36 | Dismantling (without damage) one V cross arm/Channel cross arm from existing Pole and bringing back to section store. |
| 37 | Dismantling one HT pin insulator with pin and bring back to section store. |
| 38 | Additional rate for excavation of Pit for A type pole in Laterite. |
| 39 | Additional rate for excavation of Pit for A type pole in Hard Laterite. |
| 40 | Additional rate for providing one disc set, PG clamp etc. complete, on any type of HT pole for making cut point. |
| 41 | Providing concrete muffing of size 0.45x0. 45x1.5m (0.5m above GL and 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm)0.45x0.45x1.5m, Plastering (1:3) 12mm0.45x0.45mx5sides. |
| 42 | Dismantling (without damage) one 11kV PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 43 | Dismantling one damaged 11kV PSC/RCC pole after disconnecting stays, strut etc.attached thereon and stacking the same. |
| 44 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 45 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 46 | Fitting one Additional 75x40mm, 1.8m Channel cross arm in existing single pole including conveyance of materials. |
| 47 | Fitting one Additional V cross arm in existing single pole including conveyance of materials. |
| 48 | Additional rate for providing one HT Pin with insulator, complete on any type of HT pole. |
| 49 | Additional rate for providing one F top bracket complete, on any type of HT pole. |
| 50 | Dismantling (without damage) one Channel cross arm from existing DP structure and bringing back to section store. |
| 51 | Transferring LT three phase 4/5 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 52 | Additional rate for refitting/redoing one Shackle Set, including reshacling one span, while renewing any type of LT pole. |
| 53 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires. |
| 54 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 55 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 56 | Dismantling one section fuse from structure and bringing back to section store. |
| 57 | Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with bolt & nut etc. |
| 58 | Dismantling (without damage) one LT PSC/RCC Strut pole including removal of clamps and stacking. |
| 59 | Dismantling one damaged LT TW/RSJ/Rail Strut pole including removal of clamps and stacking. |
| 60 | Dismantling of 11 kV Aerial bunched cable XLPE insulated of size 3 x 120+ 1 x 95 sqmm with bare insulated Messenger |
| 61 | Stringing of 11 kV Aerial bunched cable of size 3 x 120+ 1 x 95 sqmm with bare/insulated Messenger through existing poles |
| 62 | Dismantling one Anchor clamp /dead end clamp from 11 KV ABC |
| 63 | Fitting and erecting one HT Double Pole Structure using A type pole in position including fitting 2 No. channel cross arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 64 | Fitting one Additional2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP including conveyance of materials. |
| 65 | Transferring LT single phase 2/3 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and Please Enable Macros to View BoQ information |