Name of Work:- Making Base Plate and Shed ( 10X15) for 800GPM Pump at water Treatemnet Palnt of ABNS Colliery.
Sl. No.
Item Description
1
Manpower deployment for Dismantling of 10' X 15' Shed at 35 Nos Incline MineHigh Skilled 1 Person x 938 x 4 Shift = Rs. 3752.00Skilled 2 Person x 805 x 4 Shift = Rs. 6440.00Semi Skilled 3 Person x 679 x 4 Shift - Rs. 8148.00( Rs. 3752 + 6440 + 8148 = Rs. 18340.00)
2
Manpower Deployment for manual carrying & transporting of shed size 10' X 15' from 35 No Incline mine to water treatment plant, bhowra south collieryHigh Skilled 1 Person x 938 x 2 Shift = Rs. 1876.00Skilled 2 Person x 805 x 2 Shift = Rs. 3220.00Semi Skilled 2 Person x 679 x 2 Shift - Rs. 2696.00( Rs. 1876 + 3220 + 2696 = Rs. 7792.00)
3
Manpower deployment for Fabrication/Making of Shed size 10' X 15'High Skilled 1 Person x 938 x 7 Shift = Rs. 6566.00Skilled 2 Person x 805 x 7 Shift = Rs. 11270.00Semi Skilled 3 Person x 679 x 6 Shift - Rs. 12132.00( Rs. 6566 + 11270 +12132 = Rs. 29968.00)
4
Manpower deployment for Fabrication/Making Base PlateHigh Skilled 1 Person x 938 x 7 Shift = Rs. 6566.00Skilled 2 Person x 805 x 7 Shift = Rs. 11270.00Semi Skilled 3 Person x 679 x 6 Shift - Rs. 12132.00( Rs. 6566 + 11270 +12132 = Rs. 29968.00)
5
Material required for fabrication of Pantoon1. Cost of Electrodes = 12 x 1200 = Rs. 14400.002. Cost of DA/Oxygen Gas = 4Kg x 1900.00 = Rs. 7600.003. G. I. Hook 64 Nos X Rs.18 = Rs. 1152.004. Cost of Welding Machine = 4 Shift x 500 = RS. 2000.005. Cost of Cutting (Cutter Set) = 4 Shift x 500 = Rs. 2000.00(14400 + 7600 + 1152 + 2000 + 2000 = Rs. 27152)
6
Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.