| 1 | Supply, Installation & Commissioning of Portable Cable Swage Machine with 12 moths warranty as per Technical Specification | Supply, Installation & Commissioning of Portable Cable Swage Machine with 12 moths warranty as per Technical Specification |
| 2 | The equipment shall be able to crimp Ball End terminals and Sleeve Type Terminals on Steel Wires using pneumatic power. The Equipment shall be supplied along with multiple and suitable die sets to carry out crimping.Vendor shall prove out the equipment performance for swaging of items mentioned in Sl No. 4 and 5 and satisfy load test as per Sl No. 6. | The equipment shall be able to crimp Ball End terminals and Sleeve Type Terminals on Steel Wires using pneumatic power. The Equipment shall be supplied along with multiple and suitable die sets to carry out crimping.Vendor shall prove out the equipment performance for swaging of items mentioned in Sl No. 4 and 5 and satisfy load test as per Sl No. 6. |
| 3 | Pneumatic (Compressed Air Supply). Equipment shall have a provision to connect with Pneumatic supply .Effective Swaging shall happen with 90 psi input air pressure to satisfy load test as per Sl No. 6. Vendor shall visit LCA TD, HAL to confirmpneumatic connection adaptability. | Pneumatic (Compressed Air Supply). Equipment shall have a provision to connect with Pneumatic supply .Effective Swaging shall happen with 90 psi input air pressure to satisfy load test as per Sl No. 6. Vendor shall visit LCA TD, HAL to confirmpneumatic connection adaptability. |
| 4 | Standard Crimping | Standard Crimping |
| 5 | As per Sl No. 4.1 and 4.2 | As per Sl No. 4.1 and 4.2 |
| 6 | MIL-DTL-83420M, 1.58 MM (0.062')DIA | MIL-DTL-83420M, 1.58 MM (0.062')DIA |
| 7 | MIL-DTL-83420 , 2.4 mm (3/32'' ) DIA,7X7 GAC STEEL CABLE | MIL-DTL-83420 , 2.4 mm (3/32'' ) DIA,7X7 GAC STEEL CABLE |
| 8 | To suit and carry out swaging of 1. Ball end AN664-3 Standard on SL No. 4.1 2. Sleeve Terminal OD 6 mm of material MIL-S-6758 Cond D4 on SL No. 4.2 | To suit and carry out swaging of 1. Ball end AN664-3 Standard on SL No. 4.1 2. Sleeve Terminal OD 6 mm of material MIL-S-6758 Cond D4 on SL No. 4.2 |
| 9 | Crimping force shall be sufficient to crimp terminals/Ball ends mentioned in Sl No. 5 to withstand load test of 1. 250 kg after crimping for SL No. 4.12. 150 kg after crimping for SL NO. 4.2 | Crimping force shall be sufficient to crimp terminals/Ball ends mentioned in Sl No. 5 to withstand load test of 1. 250 kg after crimping for SL No. 4.12. 150 kg after crimping for SL NO. 4.2 |
| 10 | Sufficient to crimp terminals/Ball Ends mentioned in Sl No. 5 to satisfy Load Test as per SL No. 6. | Sufficient to crimp terminals/Ball Ends mentioned in Sl No. 5 to satisfy Load Test as per SL No. 6. |
| 11 | Bidder has to submit during bid, the catalog mentioning the make and model of the equipment indented for the purpose of this specification along with OEM authorisation.Make & Model: ATI Tools - ATI520JK or similar | Bidder has to submit during bid, the catalog mentioning the make and model of the equipment indented for the purpose of this specification along with OEM authorisation.Make & Model: ATI Tools - ATI520JK or similar |
| 12 | Shall be able to be operate by a single person. Vendor shall demonstrate the proper crimping procedure by a single operator. | Shall be able to be operate by a single person. Vendor shall demonstrate the proper crimping procedure by a single operator. |
| 13 | Vendor shall visit LCA Tejas Division , HAL before the bid end date to understand the requirement and application before finalizing the Equipment and Dies. | Vendor shall visit LCA Tejas Division , HAL before the bid end date to understand the requirement and application before finalizing the Equipment and Dies. |
| 14 | The safety precutions that need to be taken while operating the machine shall be clearly mentioned in the Documentations supplied along with the equipment. | The safety precutions that need to be taken while operating the machine shall be clearly mentioned in the Documentations supplied along with the equipment. |
| 15 | The Manufacturer shall have an experience of Min. 5 Years in manufacturing similar equipmentsFor non MSME vendors:Supplier should have delivered atleast minimum two nos (02) of such equipment or with better features. Documents such as PO Copies and Installation Report of the same shall be submitted by the supplier along with technical bid.For MSME vendors:Supplier should have supplied atleast minimum one no (01) of such equipment or with better features. Documents such as PO Copies and Installation Report of the same shall be submitted by the supplier along with technical bid. | The Manufacturer shall have an experience of Min. 5 Years in manufacturing similar equipmentsFor non MSME vendors:Supplier should have delivered atleast minimum two nos (02) of such equipment or with better features. Documents such as PO Copies and Installation Report of the same shall be submitted by the supplier along with technical bid.For MSME vendors:Supplier should have supplied atleast minimum one no (01) of such equipment or with better features. Documents such as PO Copies and Installation Report of the same shall be submitted by the supplier along with technical bid. |
| 16 | i) The Item shall be covered under warranty for all the design,material and manufacturing defects for a period of 24 months from the date of installation and commissioning at HAL site and accepted by HAL.ii) During warranty period, Bidder shall make atleast one free visit to HAL as a part of Customer Support Program.iii) There must not be any software lock which can lock the equipment.iv) Uptime of the equipment shall be 95%v) Warranty claims shall be attended within 48Hrs and resolved, any delay in resolution of grievance extends the warranty correspondingly. | i) The Item shall be covered under warranty for all the design,material and manufacturing defects for a period of 24 months from the date of installation and commissioning at HAL site and accepted by HAL.ii) During warranty period, Bidder shall make atleast one free visit to HAL as a part of Customer Support Program.iii) There must not be any software lock which can lock the equipment.iv) Uptime of the equipment shall be 95%v) Warranty claims shall be attended within 48Hrs and resolved, any delay in resolution of grievance extends the warranty correspondingly. |
| 17 | Following documents in English are to be supplied with the machine in 3 sets of hardcopies and one soft copy in pendrive.a) Equipment Manualb) Maintenance and spare parts manual c) Preventive maintenance check list, trouble shooting charts and guides. | Following documents in English are to be supplied with the machine in 3 sets of hardcopies and one soft copy in pendrive.a) Equipment Manualb) Maintenance and spare parts manual c) Preventive maintenance check list, trouble shooting charts and guides. |
| 18 | Installation, Commissioning and all the tests required for confirming the function and accuracies shall be demonstrated to HAL personnel for acceptance at HAL site. | Installation, Commissioning and all the tests required for confirming the function and accuracies shall be demonstrated to HAL personnel for acceptance at HAL site. |
| 19 | Supplier shall provide required training to Min. 2 operators at LCA TD ,HAL site regarding operation, safety precautions and mechanical maintenance of the equipment. | Supplier shall provide required training to Min. 2 operators at LCA TD ,HAL site regarding operation, safety precautions and mechanical maintenance of the equipment. |
| 20 | The equipment should be offered for pre-dispatch inspection before final supply of the equipment. Intimation for PDI must be given one month prior to the scheduled date of dispatch of equipment from supplier site. Performance test for the Entire System shall be carried out in presence of HAL representatives during PDI. Note: HAL reserves the right to waive off Pre-Dispatch Inspection.Supplier need to obtain clearance from HAL, before making the shipment. | The equipment should be offered for pre-dispatch inspection before final supply of the equipment. Intimation for PDI must be given one month prior to the scheduled date of dispatch of equipment from supplier site. Performance test for the Entire System shall be carried out in presence of HAL representatives during PDI. Note: HAL reserves the right to waive off Pre-Dispatch Inspection.Supplier need to obtain clearance from HAL, before making the shipment. |
| 21 | After sales service by trained Engineers with in 48 hours of communication shall be provided free of cost during warranty period. Manufacturer shall clearly establish their organization capability for the above requirement. Manufacturer shall be able to provide spare and service support for the quoted machine for at least 10 years. | After sales service by trained Engineers with in 48 hours of communication shall be provided free of cost during warranty period. Manufacturer shall clearly establish their organization capability for the above requirement. Manufacturer shall be able to provide spare and service support for the quoted machine for at least 10 years. |