| 1 | (Part-A) Supply & Erection Providing & Fixing of Stone pad | (Part-A) Supply & Erection Providing & Fixing of Stone pad |
| 2 | Providing & Fixing of Alluminium Lug 240/400 | Providing & Fixing of Alluminium Lug 240/400 |
| 3 | Providing & Fixing of Suspension Clamp with I Hook | Providing & Fixing of Suspension Clamp with I Hook |
| 4 | Providing & Fixing of LT Clamp | Providing & Fixing of LT Clamp |
| 5 | Providing & Fixing of Dead End Clamp | Providing & Fixing of Dead End Clamp |
| 6 | Providing & Fixing of I Hook | Providing & Fixing of I Hook |
| 7 | Providing & Fixing of T-off Channel with clamp | Providing & Fixing of T-off Channel with clamp |
| 8 | Providing & Fixing of Danger Board | Providing & Fixing of Danger Board |
| 9 | Providing & Fixing of DP Clamp | Providing & Fixing of DP Clamp |
| 10 | Cooper L-Piece 50x225x10mm (36 Nos.)/Cooper L- Piece 62x225x12mm (36 Nos.) | Cooper L-Piece 50x225x10mm (36 Nos.)/Cooper L- Piece 62x225x12mm (36 Nos.) |
| 11 | Providing & Fixing of DB Clamp | Providing & Fixing of DB Clamp |
| 12 | Providing & Fixing Tailless unit set and making connection as per diretion of superevising engineer | Providing & Fixing Tailless unit set and making connection as per diretion of superevising engineer |
| 13 | (Part-B) Carriage & Erection Carriage of PCC Pole 8.5 Mtr. Long. from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.) | (Part-B) Carriage & Erection Carriage of PCC Pole 8.5 Mtr. Long. from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.) |
| 14 | Carriage of ST Pole 11 Mtr. Long. from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.) | Carriage of ST Pole 11 Mtr. Long. from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.) |
| 15 | Carriage of following from Electricity Store CentreTajganj Agra to dump site through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70Kms.) I) LT XLPE CABLE AL 3.5X70/150/35/240/400 SQMM ( 618mtr), LT PVC Cable (mtr), ABC 3X120/95 SQMM(1610 mtr) | Carriage of following from Electricity Store CentreTajganj Agra to dump site through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70Kms.) I) LT XLPE CABLE AL 3.5X70/150/35/240/400 SQMM ( 618mtr), LT PVC Cable (mtr), ABC 3X120/95 SQMM(1610 mtr) |
| 16 | Carriage of following material from Electricity Store CentreTajganj Agra to dump site through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70Kms.) J) Line material viz. Weasal conductor , stay set Complete, 11 kv Fuse set, cross arm, angle, Pin insulators (nos), Disk insulators with fitting, and other line material, if required, x Arm v type ( nos), Distribution Box (53nos), G.I PIN 11 Kv with Nut. | Carriage of following material from Electricity Store CentreTajganj Agra to dump site through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70Kms.) J) Line material viz. Weasal conductor , stay set Complete, 11 kv Fuse set, cross arm, angle, Pin insulators (nos), Disk insulators with fitting, and other line material, if required, x Arm v type ( nos), Distribution Box (53nos), G.I PIN 11 Kv with Nut. |
| 17 | Carriage of 250 KVA T/F from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.) | Carriage of 250 KVA T/F from Electricity Store CentreTajganj Agra to work of site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-50Kms.) |
| 18 | Construction of plinth for 250 KVA Transformer of size 5’x5’x4’ above the ground lable and 1 feet below the ground. At the bottom there shall be CC pad of brick ballast of size 5x5’x3” thick in ratio 1:3:6 [Cement, sand and brick ballast]. The first class brick wall work shall be 9” thick in ratio 1:4 [Cement and sand]. The hollow portion among the wall shall be filled up with the brick ballast. On the top of the wall of plint there shall be RCC work in ratio 1:3:6 [Cement, Sand and grit stone] by using 12 mm dai MS bar at distance of 9’’. There shall be plastering all over the plinth 12 mm thick in ratio 1:4 [Cement and sand] above the ground level. Proper watering and curing of the plinth shall be carried out as per direction of supervising engineer. | Construction of plinth for 250 KVA Transformer of size 5’x5’x4’ above the ground lable and 1 feet below the ground. At the bottom there shall be CC pad of brick ballast of size 5x5’x3” thick in ratio 1:3:6 [Cement, sand and brick ballast]. The first class brick wall work shall be 9” thick in ratio 1:4 [Cement and sand]. The hollow portion among the wall shall be filled up with the brick ballast. On the top of the wall of plint there shall be RCC work in ratio 1:3:6 [Cement, Sand and grit stone] by using 12 mm dai MS bar at distance of 9’’. There shall be plastering all over the plinth 12 mm thick in ratio 1:4 [Cement and sand] above the ground level. Proper watering and curing of the plinth shall be carried out as per direction of supervising engineer. |
| 19 | Fencing of 250 KVA T/Fs as per following specification -Fabrication of 50x50x6 mm size MS Angle frame of size 3000x2400mm with 450 mm long angle for grouting the frame and fixing of 2\\"x1.5\\", 10 SWG welded wire mesh with MS strip of 24x5mm size all round the frame and drilling 9 mm holes insides of frames at as distance of 300mm for jointing of frame with the help of boslts and nuts including cost of material. The width of panal may vary as per site conditions, Grouting and fixing of angle iron frames in ratio 1:2:4 (cement, coarse sand and stone ballast ) in the pocket of 150x150x150mm all round the plinth and bolting of frames with 25x8 mm size bolts and nuts, Making main gate in front of the plinth of size 3000x2400 mm by making two leaves of size 3000x1200mm size and grouting the same in ratio and method mentioned at item (b) above fixing with hinges with dandlas for locking system & Painting of entire wire mesh angle iron etc. with Bus Green super enamelled pain in two coats on the primer two coats of Red oxide. | Fencing of 250 KVA T/Fs as per following specification -Fabrication of 50x50x6 mm size MS Angle frame of size 3000x2400mm with 450 mm long angle for grouting the frame and fixing of 2\\"x1.5\\", 10 SWG welded wire mesh with MS strip of 24x5mm size all round the frame and drilling 9 mm holes insides of frames at as distance of 300mm for jointing of frame with the help of boslts and nuts including cost of material. The width of panal may vary as per site conditions, Grouting and fixing of angle iron frames in ratio 1:2:4 (cement, coarse sand and stone ballast ) in the pocket of 150x150x150mm all round the plinth and bolting of frames with 25x8 mm size bolts and nuts, Making main gate in front of the plinth of size 3000x2400 mm by making two leaves of size 3000x1200mm size and grouting the same in ratio and method mentioned at item (b) above fixing with hinges with dandlas for locking system & Painting of entire wire mesh angle iron etc. with Bus Green super enamelled pain in two coats on the primer two coats of Red oxide. |
| 20 | Earthing of 250 KVA distribution transformer by maintenance free Earthing Electrods (Chemical) by digging pits 6\\" dia 3mtr. deep including inserting pipe in pipe technology concept involve two mild steel pipes one inserted inside the other of size ;- 1. Inner pip dia meter 50 Mm. 2. outer pipe dia meter 100 mm. length of the both pipe shall be 3000 mm. The M.S.pipe shall be ISI mark of class B as per IS 1239. Thickness of the pipe shall be 12 swg. The empty space in the pipe shall be filled with the specially developed crystalline material conductiv mixture such as copper and aluminimum powder.conductive carbon and bonding material etc. mixed in diffrent proportions. Conductive mixture contents shall be 70 % carbon powder & 30% metal powder preferably pure copper or aluminum material along with the required quantity of bonding materials. Granule size of the carbon & metal powder shall be 100 mesh. The mixture if forced (pressurized) inside the earth electrode in empty space of inner pipe & in empty space between the inner & outer pipe of the earth electrode, in paste form and after soldification of the same the bottom end cap as well as top end cap is provided. The mixture shall be pressed by machine in the pipe. Precaution shall be taken has to have no air gap inside the pipe while pressing. The back fill compound (earth enhancment material ) shall be superior conductive material that improves earthing effectiveness especially in areas of poor conductivity such as rocky ground, sandy soil & areas of moisture varation. It may contain conductive cement (20%) graphite carbon powder(50%), hydrous aluminum siliacate (10%), Sodium montmorillonite (20%) etc. it shall be placed around earth electrode in the earth pit to improve the conductive of earth electrode & ground contact area. Mild steel electro galavanized Flat 50x6 mm shall welded to earth electrode pips & connected with Trasnformer neutral and body as below with the hlep of steel nut & bolt or through welding as per requirment of site, to GI pipe and filling of chemical mixutre around the GI pipe upto 3 mtr. including making of chamber & connecting the top of the inserted pipe with transformer body & neutral through M.S.flat 50x6mm with the help of nut & bolt or through welding and making a main hole of size 2'×2' and covering the same by a stone pad for the purpose of poring water for moisture. | Earthing of 250 KVA distribution transformer by maintenance free Earthing Electrods (Chemical) by digging pits 6\\" dia 3mtr. deep including inserting pipe in pipe technology concept involve two mild steel pipes one inserted inside the other of size ;- 1. Inner pip dia meter 50 Mm. 2. outer pipe dia meter 100 mm. length of the both pipe shall be 3000 mm. The M.S.pipe shall be ISI mark of class B as per IS 1239. Thickness of the pipe shall be 12 swg. The empty space in the pipe shall be filled with the specially developed crystalline material conductiv mixture such as copper and aluminimum powder.conductive carbon and bonding material etc. mixed in diffrent proportions. Conductive mixture contents shall be 70 % carbon powder & 30% metal powder preferably pure copper or aluminum material along with the required quantity of bonding materials. Granule size of the carbon & metal powder shall be 100 mesh. The mixture if forced (pressurized) inside the earth electrode in empty space of inner pipe & in empty space between the inner & outer pipe of the earth electrode, in paste form and after soldification of the same the bottom end cap as well as top end cap is provided. The mixture shall be pressed by machine in the pipe. Precaution shall be taken has to have no air gap inside the pipe while pressing. The back fill compound (earth enhancment material ) shall be superior conductive material that improves earthing effectiveness especially in areas of poor conductivity such as rocky ground, sandy soil & areas of moisture varation. It may contain conductive cement (20%) graphite carbon powder(50%), hydrous aluminum siliacate (10%), Sodium montmorillonite (20%) etc. it shall be placed around earth electrode in the earth pit to improve the conductive of earth electrode & ground contact area. Mild steel electro galavanized Flat 50x6 mm shall welded to earth electrode pips & connected with Trasnformer neutral and body as below with the hlep of steel nut & bolt or through welding as per requirment of site, to GI pipe and filling of chemical mixutre around the GI pipe upto 3 mtr. including making of chamber & connecting the top of the inserted pipe with transformer body & neutral through M.S.flat 50x6mm with the help of nut & bolt or through welding and making a main hole of size 2'×2' and covering the same by a stone pad for the purpose of poring water for moisture. |
| 21 | Installation for 250 KVA T/F on Plinth in proper alignment direction & making HT/LT connection all Cost of labour and T&P which required for completion of work. | Installation for 250 KVA T/F on Plinth in proper alignment direction & making HT/LT connection all Cost of labour and T&P which required for completion of work. |
| 22 | Erection and grouting of Single Pole 8.5 Mtr. long PCC poles in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. | Erection and grouting of Single Pole 8.5 Mtr. long PCC poles in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. |
| 23 | Erection and grouting of Double Pole 8.5 Mtr. long PCC Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. | Erection and grouting of Double Pole 8.5 Mtr. long PCC Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. |
| 24 | Erection and grouting of ST Pole 11 Mtr. long Single in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms.Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. | Erection and grouting of ST Pole 11 Mtr. long Single in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories alongwith stone pad as per RESPO norms.Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. |
| 25 | Fixing of Distribution Box with Clamp on Errected pole for giving supply to consumer by connecting consumer cables. | Fixing of Distribution Box with Clamp on Errected pole for giving supply to consumer by connecting consumer cables. |
| 26 | Installation of Stay set complate as direction by supervising Engineer. | Installation of Stay set complate as direction by supervising Engineer. |
| 27 | Laying of LT XLPE CABLE AL 3.5X70/150/35/240/400 SQMM ( 618mtr), LT PVC Cable (mtr), ABC 3X120/95 SQMM(1610 mtr), overhead with making loop as per RESPO Norms and direction by superivising Engineer. | Laying of LT XLPE CABLE AL 3.5X70/150/35/240/400 SQMM ( 618mtr), LT PVC Cable (mtr), ABC 3X120/95 SQMM(1610 mtr), overhead with making loop as per RESPO Norms and direction by superivising Engineer. |
| 28 | Dismentling & Removal of 100 KVA T/F and Recived back to ele. Store Center Taj Agra | Dismentling & Removal of 100 KVA T/F and Recived back to ele. Store Center Taj Agra |