| 1 | Earth work in digging foundation in all type of soil with all lead & lift and disposal of earth including refilling the trench As per direction of Engineer in charge with in 30.00 m. |
| 2 | Laying P.C.C. M-15 in foundation with cement, Coarse sand & stone ballast 20 mm to 40 mm size including cost of all material & labour T&P etc. As per direction of Engineer in charge. |
| 3 | Ist class B.W in 1:4 CM with C-sand including cost of all material labour and T&P etc. As per direction of Engineer in charge. |
| 4 | 12 mm thick Cement plaster work with 1:4 cement, coarse sand Mortar including all cost of material , labour T&P etc complete. As per direction of Engineer in charge. |
| 5 | Cement pointing Deep struck 1:2 cement Mortar including all cost of material , labour T&P etc complete. As per direction of Engineer in charge. |
| 6 | Providing and laying and replacing of R.C.C. pipe 150 mm dia, including all cost. As per direction of Engineer in charge. |
| 7 | Laying Dry Brick on edge soling with Brick 150 laid dry joint sand filled including preparation of base to proper slope and its ramming, including all cost of material, labour T&P etc. complete. Required for proper completion of work. As per direction of Engineer in charge. |
| 8 | Earth work in Corecting Internal Section for restoration of Mariyahu Branch from km. 50.200 to km. 85.700 by poclain machine with Bucket capacity 0.90 Cum. Including T&P etc . Complete. As per direction of Engineer in charge. |
| 9 | Dressing of Executed earth in canal bank and its outer side of slope of Mariyahu Branch from km. 50.200 to km. 85.700 including all cost of labour T&P etc. Complete. As per direction of Engineer in charge. |
| 10 | Earth work in digging foundation in all type of soil with all lead & lift and disposal of earth including refilling the trench As per direction of Engineer in charge with in 30.00 m. |
| 11 | Laying P.C.C. M-15 in foundation with cement, Coarse sand & stone ballast 20 mm to 40 mm size including cost of all material & labour T&P etc. As per direction of Engineer in charge. |
| 12 | Ist class B.W in 1:4 CM with C-sand including cost of all material labour and T&P etc. As per direction of Engineer in charge. |
| 13 | 12 mm thick Cement plaster work with 1:4 cement, coarse sand Mortar including all cost of material , labour T&P etc complet. As per direction of Engineer in charge. |
| 14 | Cement pointing Deep struck 1:2 cement Mortar including all cost of material , labour T&P etc complet. As per direction of Engineer in charge. |
| 15 | Providing and laying and replacing of R.C.C. pipe 150 mm dia, including all cost. As per direction of Engineer in charge. |
| 16 | Laying Dry Brick on edge soling with Brick 150 laid dry joint sand filled including preparation of base to proper slope and its ramming excluding supply of all material, but including cost of sand, labour and T&P etc. Required for proper completion of work. As per direction of Engineer in charge. |
| 17 | Earth work in Corecting Internal Section for restoration of Mariyahu Branch from km. 50.200 to km. 85.700 by poclain machine with Bucket capacity 0.90 Cum. Including T&P etc . Complete. As per direction of Engineer in charge. |
| 18 | Dressing of Executed earth in canal bank and its outer side of slope of Mariyahu Branch from km. 50.200 to km. 85.700 including all cost of labour T&P etc. Complete. As per direction of Engineer in charge. Please Enable Macros to View BoQ information |