| 1 | Earth work excavation foundation in hard soil trenches within 50 meter initial leadand 1.5mt. Intial lift including rough dressing and levelling the bedincluding all labour, T&P etc. complete as directed by the Engineer in Charge. |
| 2 | Supplying & Filling foundation and plinth with sand well watered and rammed including cost, conveyance, Royalities, Taxes of all materials,all labours & T&P required for the work complete ( measurement will be takenon finished compacted section only)as perthe direction of Engineer-in-Charge. |
| 3 | Cement concrete (1:3:6) using approved quality from approved quarry including lowering laying concrete watering and curing etc. as required levels laid in layers not exceeding(0'-6'') 15 cm thick including cost, conveyance,royalities of all materials and cost of all labour ,T&P required for the work etc. complete in all respect as directed by the Engineer-in-charge . |
| 4 | Providing Single under-reamed Piles foundation of 300 mm dia. 4.0m long with R.C.C M-20 using 12 mm size black hard granite (Crusher Broken) stone chips including cost of boring , but excluding cost of M.S rods /Tor steels and labour charges for cutting bending and binding of steel and T&P required for the work etc. complete as directed by the Engineer-in-Charge. |
| 5 | 300 mm dia. 6.0m |
| 6 | R.C.C. work M-20 in grade having a minimum compressive strength (in work test) 200 kg/cm2 in 15cm cubes at 28 days using 12mm. & down grade hard granite C.B. chips of approved quality and from approved quarry including watering, lowering laying concrete, compacting with vibrators, curing for 28 days with smooth centering and shuttering and finishing the exposed surface including cost conveyance, royalties of all materials, cost of labour & T&P rand other machinsries required for the work complete but excluding cost and carriage of HYSD bars and cost of bending, binding tying the grills and etc. as per specification & direction of the Engineer-in-charge |
| 7 | Column |
| 8 | Plinth Band |
| 9 | Roof Slab |
| 10 | Supplying Cutting,bending un- coated HYSD bars,for reinforcement tying the grills and placing in position as required for the RCC works and for providing fan hooks hoisting and lowering,laying including cost,conveyance of HSYSD bars and binding wires of 18 to 20 gauge required for the work and bending binding and tying the grills ( Payment will be made on weight of HYSD bars only and no separate payment will be made towords the weight of binding wires) as per direction of the Engineer-In-Charge. |
| 11 | Cement concrete (1:2:4) using 12 mm size hard crusher broken granite chips of approved quality from approved quarry including lowering lying concrete watering and curing etc. complete with cost, conveyance, royalities and taxes of all materials and cost of all labour ,T&P etc. complete. as directed by the Engineer-in-charge. |
| 12 | 16 mm (5/8\\") thick cement plaster (1:6) finished smooth to inside rough surface or 10'' thick brick walls after raking out joints including watering and curing with cost , conveyance , royality of all materials , cost of all labour and T&P required for the work etc complete as per direction of the Engineer-in-charge. |
| 13 | 6mm thick cement Plaster (1:4) to RCC surface after chipping the RCC surface and slurry trement including watering & curing etc. complete with cost, conveyance,royality of all materials & all labour royalty T&P directed for the work etc. complete as per directed by the Engineer-in-charge. |
| 14 | Removing Old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50 mtr. lead. as per direction of the Engineer-in-charge. |
| 15 | 12mm(1/2'') thick cement Plaster in cement mortar (1:6) finished smooth to outside surface of brick walls after racking out the joints scapping and cleaning the surface including watering & curing for specified period etc. complete with cost, conveyance,royality and taxes of all materials & cost of all labour, T&P scaffolding required for the work complete in all respect. The materials used for the work and items of work shall confirm to relevant I.S specification and test as per specification and as directed by the Engineer-in-Charge. |
| 16 | Finishing wall surface with a coat of primer on new work to give an even shade including cost of brushes & putty including cost of paints , cost of all labour,T&P etc complete as directed by the Engineer-in-charge . G. floor |
| 17 | First Floor |
| 18 | Wall Painting one coats Plastic Emulsion Paint any approved shade of including cost conveyance, taxes of all materials and T & P required for the work including cost of paint etc all complete as directed by the Engineer-in-charge. |
| 19 | First Floor |
| 20 | Finishing wall with Weather coat paint two coats over a coat of primer including cost of brushes and putty with cost of paints and taxes of all materials and all labour etc complete as per direction of the Engineer-in-charge. G. floor |
| 21 | First Floor |
| 22 | Painting two coats any approved shade to wood / Iron works over a coat of priming including sand papering polishing the surface cost, conveyance of all materials & T&P required for the work including cost of paints etc complete as per the direction of the Engineer-in-charge. G. floor |
| 23 | First Floor Please Enable Macros to View BoQ information |