| 1 | Transporting LT ABC by hired vehicle to a distance up to 5 km and carring up to 2 drum including loading and un loading using crane |
| 2 | Stringing of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16+1x 50 sqmm with bare/insulated Messenger through existing poles |
| 3 | Dismantling (without damage) one km LT three phase 4 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 4 | Dismantling (without damage) one km LT additional conductor line by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 5 | Providing Strut using LT PSC pole including digging and back filling pit in ordinary soil. |
| 6 | Dismantling (without damage) one km LT single phase 2 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 7 | Redoing single phase WP service connection complete including lowering down the guy wire portion, repairing or changing WP wire, GI wire, Fuse unit etc., changing Energy Meter cutout, neutral link etc., if necessary and reconnecting the same including conveyance of material to site from Section office at various location. |
| 8 | Redoing three phase WP service connection complete including lowering down the guy wire portion, repairing or changing WP wire, GI wire, Fuse unit etc., changing Energy Meter cutout, neutral link etc., if necessary and reconnecting the same including conveyance of material to site from Section office at various location. |
| 9 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 10 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 11 | Erecting one LT PSC Pole in position including digging & back filling pit in ordinary soil. |
| 12 | Labour charges for loading LT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 13 | Installation of Insulation piercing connector for main to service line main:16-95 sqmm, Tap 16-95 sqmm |
| 14 | Erection of Anchor clamp / dead end clamp for LT ABC of any size |
| 15 | Erection of suspension clamp for LT ABC of any size |
| 16 | Installing One No. 4 way Satellite Connector of size Main :16 to 95, Tap:4 to 35 Sq.mm to the LT AB cable of Standard size |
| 17 | Providing Stay for LT poles including digging & back filling pit in ordinary soil. |
| 18 | Providing one Driven Earth using GI earth pipe of size 38.1mm dia, 2.5m length at minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in loose soil. |
| 19 | Renewal of existing damaged/old LT stay with new stay in place including excavation of stay pit, erection of new stay, backfilling pit and refitting of all items and conveyance of all materials. |
| 20 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 21 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 22 | Stringing of 1.1 kV Aerial bunched cable of size 1 x 25 + 1 x 25 sqmm with bare/insulated Messenger through existing poles |
| 23 | Erection of suspension clamp suitable for LT AB cable with SS strap assembly Please Enable Macros to View BoQ information |