| 1 | Carriage of all the concerning material from store centre to JE's dump store& from dump store to the site work including loading, unloading and proper stacking at the site etc. |
| 2 | 5 MVA T/F |
| 3 | 11 KV 3x300 sq mm XLPE Cable |
| 4 | 11 KV 3x300 sq.mm Cable Jointing Kit I/D |
| 5 | 11 KV 3x300 sq.mm Cable Jointing Kit O/D |
| 6 | 11 KV 3x185 sq mm XLPE Cable |
| 7 | 11 KV 3x185 sq mm XLPE O/D J/Kit |
| 8 | 11 KV 3x185 sq mm XLPE I/D J/Kit |
| 9 | Single core cable 1x400 sq mm |
| 10 | Panther Conductor |
| 11 | 33 KV VCB 800 Amp 750 MVA |
| 12 | Single T/F Control Panel |
| 13 | 11 KV VCB I/C CTR 600/300/5 amp, 350 MVA |
| 14 | 11 KV VCB O/G CTR 200/100/5 amp, 350 MVA |
| 15 | Bus Coupler 350 MVA |
| 16 | 33 KV LINE ISOLATOR 400/800 A |
| 17 | 33 KV Lightening Arrestor |
| 18 | 33 KV BUS ISOLATOR 400/800 A |
| 19 | 33 KV CT 200/100/1 amp |
| 20 | PCC Pole 11 Mtr Long |
| 21 | ST Pole 9 Mtr Long (Galvanised Bottom) |
| 22 | 33 KV Composit Pin Insulator |
| 23 | MS earthing rod 20x2500 mm |
| 24 | MS angle 65x65x6MM 5.8 kg / Mtr. |
| 25 | M.S. Channel 100x50 sq mm 10 kg / Mtr. |
| 26 | Top Channel 125x65 sq mm |
| 27 | LT PVC Cable 1x400 sq mm |
| 28 | Rail 105 Lbs 9 Mtr Long |
| 29 | M.S.Angle 75x75x6, |
| 30 | MS Round of 32 mm dia |
| 31 | Earthing rod |
| 32 | Battery Charger 24 Volt |
| 33 | Battery Set 24 Volt |
| 34 | Earth mate (20x06 Mtr) & Earthing of substation switch yardEarth Laying of earth mat in the switchyard by laying of M.S. Round of 32 mm dia in 750 mm deep trenches with M.S. Round 32mm dia,3 Mtr. Long earth electrodes as per drawing. The work includes welding of the M.S. Round ,connecting all steel structures in the switchyard with the earth mat by means of G.I. strips of size 50x6mm as per item below and proper levelling (All material shall be provided by the contractor except the supplied item) as per RESSPO Norms |
| 35 | Excavation of earth for laying mat |
| 36 | Driving of earth electrode. |
| 37 | Laying of earthmat (M.S.) Bar including cutting, shaping and binding etc) |
| 38 | Preparation of joints, proper making and welding; of main earthmat bar joints and applying bitumen, bitumen impregnated on joints i.e. End Joints. Cross Joints, Lap Joints. |
| 39 | Welding of riser strip with earthmat and structure body. |
| 40 | Plinth of 5/10 MVA.33/11 KV T/Fs Construction of plinth of size 3x4x1.3 Mtr. for 5/10 MVA T/F having 0.4 Mtr. above ground level . The work including excavation of foundation base concreting in CC 1:6:12 ratio (cement ,fine sand & brick ballast)first class brick work in cement mortar of ratio 1:4 foundation CC in 1:4:8 ratio (cement ,fine sand & brick blast) and RCC working ratio 1:2:4 (cement ,coarse sand and stone grit of 20mm gauge using MS Bars of 10mm dia( tor ) in reinforcement including its cutting ,bending &binding in required shape .The work also includes laying of 2 No. 4 Mts. long each rail pieces complete with cutting & proper fitting etc. The plinth will be plastered/ finished on top and sides of the plinth .(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms/Schedule No 44. |
| 41 | FABRICATION ,ERECTION, GROUTING PLINTHING OF S/S STRUCTURE. |
| 42 | (A) ISOLATOR STRUCTURE :- Erection,Plinthing & grouting (1.9 Mtr Below & 2.6 mtr above ground level because of earth filling) of Isolator structure (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms/Schedule No 41. |
| 43 | (B) LIGHTNING ARRESTOR ,C.T. & PT STRUCTURE:- Erection Plinthing & grouting (1.9 Mtr Below & 2.6 mtr above ground level because of earth filling)of L.A. & C.T. structure (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms/Schedule No 42. |
| 44 | PLINTH FOR VCB :-Construction of plinth of size 2.0 mtr x 1.5 mtr x 0.9 mtr suitable for erection of upper structure for 33KV VCB including grouting of anchor bolts in proper alignment and level. Scope of work includes excavation of foundation base concreting in CC 1:6:12(cement, fine sand & brick ballast ),1st class brick work in cement mortar of ratio 1:4 CC in ratio 1:4:8 and RCC work in ratio 1:2:4 (cement coarse sand and stone grit of 20mm gauge )(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 45 | CABLE STAND Fabrication, erection, plinthing & grouting of cable stand made of two nos MS channel 100x50x3.5 mtr(0.9 Mtr Below & 2.6 mtr above ground level because of earth filling) . Long jointed to each other by means of 05 nos MS strip 50x6 mm of size 150 mm Long each by welding at equal distance interval as per norms and completely providing two nos cable clamp also.(All materials will provide by contractor except MS channel) as per RESSPO Norms/Schedule No 49. |
| 46 | INSTALLATION & TESTING OF 33/11KV,5 MVA TRANSFORMERS The work includes shifting of transformer to the site of installation within the substation premises, assembling fixing and fitting of all accessories and filling of transformer oil to the desired level and ensuring that there is no leakage. Providing & fixing Copper.L-piece/Connector 07 no.for transformer. All the jumpering & connection are included in the scope of work. Work shall be done as per RESSPO Norms (All material shall be provided by the contractor except Supplied items) |
| 47 | INSTALLATION OF VCB:- Installation of 33KV VCB- complete work including commissioning.(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 48 | INSTALLATION OF ISOLATORS :-Assembling and installation of line /bus isolator on the isolator structure, In case of line isolator proper operation of earth links shall also be insured. The work includes fabrication for proper flexing if required.(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 49 | INSTALLATION OF LIGHTNING ARRESTOR ,C.T. & PT STRUCTURE |
| 50 | INSTALLATION OF LIGHTENING ARRESTORSAssembling and installation/ Mounting of lightning arrestors on the L.A.Structure (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 51 | INSTALLATION OF CT:- Installation of CTs on the CT structure, along with C.T. Junction box .(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 52 | Jumpering of all equipments in switch yard with ACSR Conductor P.G. clamps & proper size aluminium lugs.(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 53 | Providing & fixing of connector for LA,CT,PT,Isolator etc.(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 54 | NEUTRAL STANDFabrication, Erection,Plinthing & grouting of Neutral Stand (0.9 Mtr Below & 2.6 mtr above ground level because of earth filling) and grouting of M.S Angle 75x75x6 or 65x65x6mm in L shape & in proper size and alignment to provide support for the separate earthing strips for power transformer neutral including supply and fixing of flexible copper bonds for neutral earthing. (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms/Schedule No 52. |
| 55 | INSTALLATION OF SWITCHGEARS IN CONTROL ROOM |
| 56 | Shifting carefully & safely 11KV I/C,O/G&B/C switchgear from outside of the switchgear room in proper position and alignment and checking-complete work with Mounting of P.T on incoming Switch gear.(All material shall be provided by the contractor except 11 KV I/C, O/G & B/C will be provided by the department)as per RESSPO Norms |
| 57 | Fixing and making bus bar connections in between all switchgears after cleaning and taping with H.T. Tape, empire tape and PVC tape properly. Providing and fixing of 6 mm thick Bakelite separators and plugging of all opening & holes with plastic compound-complete work including cost of all material (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms and strictly to the satisfaction of site in- charge. |
| 58 | Shifting carefully & installation of 33KV Single/Double circuit transformer control panel in control room including its grouting. (All material shall be provided by the contractor except 33KV single circuit transformer control panel shall be provided by the department)as per RESSPO Norms |
| 59 | Earthing by way of boring and lowering of \\"B\\" class GI pipe 50mm dia from ground upto the water level (minimum 30 meter deep) as per standard practice (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms/Schedule No 53. |
| 60 | Fabrication & erection of 33 KV cable exposure type double pole with the provision of separate bus bar for each cable with fixing of necessary clamps and other acessories like danger board,number plate,barbed wire, 6 no. pin insulators with pins,2 no. channels 100x50 mm (1600mm each),1 no.MS channel 100x50 mm(3200mm in length) and 2 no.MS angle 65x65x6 mm (each 3200mm in length ) for supporting the hoisting of cable etc.Its jumpering by single core PVC aluminium cable with proper size of lug as per RESSPO norms.(All material to be arranged by contractor except STP, MS Channel, MS Angle, 33 KV Pin Insulator, 33 KV Pin with nut &PVC cable). |
| 61 | EARTHING OF 11KV SWITCHGEARS & 33KV CONTROL PANELSEarthing of indoor equipment by means of M.S strip 50x6mm & connecting to Pipe type earthing as per RESSPO norms. Joints will be welded with high quality arc welding. (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms (minimum 30 mtr deep) |
| 62 | H.T.CABLE LAYING |
| 63 | Cable laying 33KV,11KV,3X300,3X185 and 3X70 above size sq S/C in normal soil by digging of trench including supply of required material as fine sand, bricks. (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms. Spare cable shall be left and buried in the trench in the shape of rings at both ends. Cable laying work includes unrolling, cutting, making rings and sealing both ends of the cable. |
| 64 | Cable laying in existing trench S/C all size cable. |
| 65 | Hoisting of 11 KV cable on 11 switchgear & Cable Stand (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 66 | Hoisting of 33 kv 3x300 sq mm XLPE Cable on D/P with GI Pipe dia 6\\" its jumpring complete with clamps , nuts and bolts .(All the material shall be provided by the contractor except33kv cables & O/D J/K. )as per RESSPO NORMS |
| 67 | High Pressure testing of 11 KV XLPE cable. Testing equipment will be arranged by the contractor. |
| 68 | STATION/SWITCHYARD LIGHTING |
| 69 | Erection of 9 Mt. STP after excavation of earth in any type of soil and grouting of CC in ratio 1:4:8 (cement, coarse sand & brick ballast) With plinthing & Painting of Poles (All material shall be provided by the contractor except Pole)as per RESSPO Drawing/Schedule No 47. |
| 70 | Provided and Fixing of LED flood lamp 120W complete fittings, (standard quality ISI mark with water tight fittings, elbow etc.)on above supports.(All material shall be provided by the contractor )as per RESSPO Norms/Schedule No 47. |
| 71 | Providing and laying of 10 sq. mm. LT PVC cable from S.G. room to street light supports after digging of trench, laying of cable, providing a brick on top of cable , refilling of trench, making connections at poles with street light fittings, complete in all respect. (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 72 | Construction of cable trench of size 300x300 mm including brick work 1:4 in wall of the trench. Brick ballast work in 1:5:10 on foundation, plaster 12 mm thick with coarse sand 1:4 and surface finishing with cement. Providing MS strip at an interval of 0.5 M & MS angle running on both the edges of trench.(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms/Schedule No 54. |
| 73 | Construction of welded frame type control cable trench cover 0.5 M long suitable for trench including cost of MS/Torr Bar.(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms/Schedule No 55. |
| 74 | Providing and Laying of following size Armoured copper control cable through underground/cable trench/trenching SGR interlinking through proper connections to transformer control panel/protection board /Battery and Battery Charger/Relays 33/11 KV Transformer junction box/ 33KV VCB ,CTs etc as per site conditions.(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 75 | a) 2x2.5mm2 |
| 76 | b) 4x2.5mm2 |
| 77 | Providing & fixing of control cable tray.(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 78 | Grouting of STP/PCC in depth of 1/6th the length of pole in ratio 1:4:8 in cement sand and brick ballast and construction of pole plinth 300mm x 45mm above ground level in 1:2:4 in cement, coarse sand and stone gritt as per RESSPO norms. |
| 79 | Construction of Fire wall with the thickness of 300 mm (fire-Resistant RCC/fire-rated brickes), Height 6 Mtr,RCC base foundation 2 Mtr deep for structual stability, with reinforcement bars for strength (All material shall be provided by the contractor) |
| 80 | Painting of all structures, equipments & Old & Used 5 MVA Power Transformer.(All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 81 | Maintaining breather & silica gel in 5 MVA Old & Used transformer (if necessary) |
| 82 | Changing of all damaged packings of power T/F (if Required) & centrifuging the T/F Oil with the proper way that no damage in T/F (if Required). (All material shall be arranged by the contractor) |
| 83 | Installation of 24 Volt, 15 AH sine wave Battery and battery Charger and its cabinate complete and including its commissioning. (All material shall be provided by the contractor except the supplied item)as per RESSPO Norms |
| 84 | All earthing strip shall be painted by green colour (All Material Shall be arranged by the contractor) GST will be paid extra as applicable. Please Enable Macros to View BoQ information |