| 1 | All these below items/materials from S.N. 1.01 to 1.21 will be given and errected by the contractor at his own cost as per estimate/Resspo Norms. |
| 2 | Aluminium Lug of different size |
| 3 | Aluminium Lug barrel off size (L.S.) |
| 4 | PG clamp suitable for weasal conductor |
| 5 | Clamp with nut and bolt |
| 6 | MS nut and bolt off size with washers |
| 7 | Suspension clamp |
| 8 | Dead End clamp |
| 9 | LT clamp with nuts and bolt of PCC/STP |
| 10 | Eye-Hook |
| 11 | Three phase distribution box with clamp |
| 12 | Holding clamp for Top, T-off, dropper etc. |
| 13 | 11 KV fuse set |
| 14 | Danger board barbed wire including jumper |
| 15 | Copper L-piece of different size (L.S.) |
| 16 | Loop Insulator |
| 17 | F-bracket |
| 18 | X-bracing angle |
| 19 | Shackle Insulator |
| 20 | Guarding angle with clamp |
| 21 | 6/10 G.I. Wire |
| 22 | Extra for stay at angle location |
| 23 | Loading, Unloading and safe cartage of the following materials (S.N. 2.01 to 2.16) from Electricity Store Centre, Gonda to the work site/dump site. |
| 24 | PCC Pole |
| 25 | 100 KVA T/F |
| 26 | 250 KVA T/F |
| 27 | DROPPER CHANNEL |
| 28 | ABC of different size |
| 29 | ACSR weasal conductor |
| 30 | LT PVC Cable of different size |
| 31 | Top channel |
| 32 | T-off channel |
| 33 | S/S Base |
| 34 | Stay set complete |
| 35 | Disk Insulator with fitting |
| 36 | Polymer Pin insulator |
| 37 | Earthing set complete |
| 38 | X-arm |
| 39 | Other material |
| 40 | Erection of single PCC Poles alongwith fitting of all accessories on pole including dragging of pole from Dump Site to pit site (All decentralize material shall be given by the contractor on his own cost.) |
| 41 | Erection of sectional double pole sectional PCC Poles alongwith fitting of all accessories on pole including dragging of pole from Dump Site to pit site. (All decentralize material shall be given by the contractor on his own cost.) |
| 42 | Grouting of Poles with 1:4:8 CC ratio of cement, sand & brick ballast, backfilling of pits with mud completely.All required materials provided by the contractor at his own cost. |
| 43 | Erection and Grouting of stay sets alongwith complete fittings. Cement, Sand & Brick ballast provided by the contractor at his own cost. |
| 44 | Earthing of Pole |
| 45 | Installation of Tailless unit 500 Amp. 3 Ckt. Fabricatin & Installation of M.S. Frame grouting and fixing of tailless unit suitable for LT side of transformer. Material used:-MS angle (35X35mm), height 8 feet, Aluminium strip (100X50X6mm), Red oxide and yellow paint, copper L-Piece, Fuse wire 240 Amp. AL.Lug, Nut and bolt etc. (All the required material shall be supplied and erected by the contractor at his own cost.) |
| 46 | Bore type Earthing and lowering \\"B\\" class G.I. Pipe (Gindal) of 50mm dia from ground upto water level not less than 40 feet, with G.I. strip of proper size as per standard /Estimate/Resspo Norms. (All the required material shall be given by contractor at his own cost.) |
| 47 | Fencing of Transformers (size 10X8X6 feet height including civil work) with MS strip (50X6 mm) as well as proper paint including single door as per estimate's requirement/as per RESSPO norms. (All the required material shall be given by contractor at his own cost.) |
| 48 | Construction of T/F plinth of size 2x2x1.5 mtr on a padding 0.25M deep in ground 1:5:10 cement sand and brick ballast on the top of padding brick work Ist class brick of 0.95 mtr. Height and 0.35 mtr wall will be constructed. Rest wall should be 0.23 mtr thick. brick work in ratio 1:4 cement and cores sand in the hollow portion the sand should be filled from the ground level up to 15 centimeter below from the top of wall, cement, sand and brick ballasts should be filled up to 15 centimeer. Two no. of channel 100x50 in length 1500mm will be grouted. 0.35 cm RCC will be done with cores sand, cement and stone ballast in the ratio of 1:2:4. The T/F's plinth should be plastered on all sides 12mm thick in ration 1:6 by cement and cores sand. (All the required material shall be given the contractor on his own cost.) |
| 49 | Construction of 11/0.4 KV S/S for following capacity of T/F with mounting and fitting of T/F on plinth/double pole with proper fitting of all acessories and connecting with all circuit including earthing of T/F fitting with all accessories. |
| 50 | 100 KVA T/F |
| 51 | 250 KVA T/F |
| 52 | Laying, stringing, sagging & binding of conductors of 11 KV in 3 phase, 3 wire line with jumpering (where as required) |
| 53 | Laying, Stringing & Sagging of ABC Cable of upto proper sag for the different size cable as per estimate/resspo norms |
| 54 | LT PVC Cable of different size |
| 55 | Cutting of tree branches for cleaning route of 11 KV/LT line at the work site (25 mtr.= 1 Job) Please Enable Macros to View BoQ information |