| 1 | INCREASING CAPACITY OF TFs FROM 25 KVA-1 PHASE T/F TO 63 KVA-3 PHSE T/F, AT VILLAGE , BARWATALI, ACHAKAPUR, PURE DHAUKAL, AHAMADPUR CHAHETA, RAM NAGAR, RANMAU, BASANT KHEDA, DEPARMAU, MAHARANIGANJ, PURE BAHAI, CHAKAWAPUR, BAJPAIKHEDA, GODHANI KHEDA, PURE BADHAIN, DEVNAGAR, DEVNAGAR-2, PURE CHAIN, MAHA KHEDA, SURJA SINGH KA PURAWA, NARSINGH PUR, REWARI PASIYA KHEDA, KALUVA KHEDA, MARDAN PUR, TIWARI KA PURAWA , BAIRIYA THOK BHEETARGAON, BALBHADRA KHEDA, HARDI, HARIPUR, HARIPUR NIHASTHA, KAMALPUR, HIMANCHAL KHEDA, KUSANDI, KUTKURI, LALPUR , LALPUR BHEETARGAON, MAHIPALPUR, MEDAULI, MEDAULI-2, NAYA PURAWA, PAHO, PURE SAMBHAR SINGH, RAGHUNAT KHEDA, (42 Nos) UNDER BUSINESS PLAN 2026-27, IN JURISDUCTION OF EE EDD LALGANJ, RAEBARELI. (Total 42 Nos.) |
| 2 | Safe loading & carriage including Loading-unloading & proper stacking at a Place of work site of following store materials from ESC Tripula to site of work:- |
| 3 | 63 KVA T/F |
| 4 | PCC Pole 805 Mtr Long. |
| 5 | Top Channel |
| 6 | Dropper Channel |
| 7 | Pin Insulator with Pin |
| 8 | S/S Base Angle |
| 9 | Disc Insulators with Fittings |
| 10 | Earthing Complete |
| 11 | Stay Set Complet |
| 12 | Cable LT ABC (3x50+1x70+1x16) Sq.mm |
| 13 | Three Phase Distribution Box |
| 14 | Cable Alluminium 3.50x70 Sq.mm |
| 15 | ACSR Weasal Conductor |
| 16 | 11 KV Fuse Set |
| 17 | Recd. back Old 25 KVA T/F and other Related Materials etc. from work site to ESC Tripula, Raebareli alongwith loading unloading. |
| 18 | Labour Ereection Charges:- |
| 19 | Making/Prapairing/Erection of .PCC Pole including fitting of all required accessories as per RESPO Norms. |
| 20 | Grouting of PCC Pole alongwith Grouting Materials, as per RESPO Norms. |
| 21 | Earthing of Pole as per RESPO norms. |
| 22 | Making/Prapairing of Double Pole Structure for mounting of 63 KVA T/F by.PCC Pole then grouting of Pole with grouting materials, including fitting of all required accessories, as per RESPO Norms. |
| 23 | Dismantling of old existing 25 KVA 1 PH T/F from D/Pole/SINGLE Pole Structure/Plinth then stacking of dump site with loading unloading, |
| 24 | Mounting of 63 KVA T/F on New Constructed D/Pole Structure, alongwith fitting of all related accessories, Earthing of T/F body & neutral & FUSE SET etc, As per RESPO norms. |
| 25 | Digging of Pits, fixing nozzling & grouting of Stay Rod inclucing fitting of all accessories with grouting materials as per RESSPO Norms |
| 26 | Laying , stringing & sagging of HT Line by DOG/ACSR weasal / RABBITconductor including all associated work & making clearance of Road with Joint/jumpers & binding on insulators as required. |
| 27 | Fixing & Jouinting of Alluminum Conductor 3.5X70 sq.mm for connectiing from TF to Jumpers. |
| 28 | Laying , stringing & sagging of LT Line by LT ABC ( 3X50+1X70+1X16) including all associated work & making clearance of Road with Joint/jumpers & binding on insulators as required. |
| 29 | Making/Fixing/Tightening of 11 KV Fuse Set with Tightening of Nuts & Bolt. |
| 30 | Making/Fixing /Installation of TOP CHANNEL with tightening by Nuts & Bolts. |
| 31 | Making/Fixing /Installation of DROPPER CHANNEL with tightening by Nuts & Bolts. |
| 32 | Making/Fixing /Installation of Three Phase Distribution Box, with tightening by Nuts & Bolts. |
| 33 | Making/Fixing/Installation of Holding Clamp, Material Provided by Contractor |
| 34 | Making/Fixing/Tightening of LT SHACEL INSULATOR, Material Provided by Contractor |
| 35 | Making/Fixing/Tightening of \\" I \\" HOOK, for LT ABC with Nuts & Bolt, Material Provided by Contractor |
| 36 | Making/Fixing/Tightening of Nuts & Bolt, Material Provided by Contractor |
| 37 | Making/Fixing/Tightening of LT CLAMP for PCC Pole alongwith Nuts & Bolt, Material Provided by Contractor |
| 38 | Making/Fixing/Tightening of LT FUSE (SMC BOX) & 11 KV Fuse Set, fixing arrangements with Nuts & Bolt, Material Provided by Contractor |
| 39 | Making/Fixing/Tightening of DANGER BOARD, barbed wire WITH JUMPER Material Provided by Contractor |
| 40 | Making/Fixing/Tightening of \\"F\\" CLAMP & fixing arrangements with Nuts & Bolt, Material Provided by Contractor Please Enable Macros to View BoQ information |