| 1 | Construction of 500 MT Godown No.1 & No.2 at Junagarh Main Market Yard under RMC, JunagarhEarth work in excavation of foundation trenches in hard soil soil including moorum, stony earth and earth mixed with boulders except sheet rock and boulders required depth and depositing the excavated materials away from the work site with all leads and lifts including shoring shuttering & dewatering (if required) with cost of labour hire & running charges of water pumps sundries & T & P required for the work complete as directed by the Engineer in charge. |
| 2 | Supplying and filling plinth with sand well watered and rammed in layers not exceeding 23 cm in depth with all lead and lift including cost, conveyance, loading, unloading, royalities and taxes of all materials cost of all labour sundries T&P required for the work etc complete in all respect as directed by the engineer in charge. (Measurement will be taken on finished compacted section only.) |
| 3 | Filling foundation trenches and plinth with excavated earth including watering ramming and compacting in layers not exceeding 150mm thick including labour sundries T&P etc complete and as per direction of engineer -in- charge. |
| 4 | Providing and laying PCC (1:3:6) in foundation & plinth using 40mm size crusher broken HG metal of approved quality from approved quarry including hoisting, Lowering and laying concrete to the required level ramming, watering & curing etc complete including cost conveyance of all materials with all taxes and royalties all labour with sundries T&P including hire and running charges of machineries required for the work etc complete in all respect and as per the direction of Engineer-in-charge. |
| 5 | C.C (1:2:4)with 12mm size HG chips of approved quality from approved quarry including hoisting. Lowering and laying concrete to the required level ramming, watering & curing etc complete including cost conveyance of all materials with all taxes and royalties all labour with sundries T&P including hire and running charges of machineries required for the work etc complete in all respect and as per the direction of Engineer-in-charge. |
| 6 | Providing Fly Ash brick masonry work in Foundation & Plinth with fly ash bricks 25cm x12 cm x8 cm tolerance of ± 2% size bricks having crushing strength not less than 75 kg/cm2 with cement mortar 1 cement: 6 sands with all necessary projection, splay cutting, circular moulding, corbelling, etc., including cost of all materials, labour, conveyance, loading ,and unloadining, taxes, royalties, scaffolding, watering, curing, sundries, tools and plants, etc., as per the direction of the Engineer-in-charge. |
| 7 | Providing Fly Ash brick masonry work in Super Structure upto 3 meter height with fly ash bricks 25cm x12 cm x8 cm tolerance of ± 2% size bricks having crushing strength not less than 75 kg/cm2 with cement mortar 1 cement: 6 sands with all necessary projection, splay cutting, circular moulding, corbelling, etc., including cost of all materials, labour, conveyance, loading ,and unloadining, taxes, royalties, scaffolding, watering, curing, sundries, tools and plants, etc., as per the direction of the Engineer-in-charge. |
| 8 | Providing Fly Ash brick masonry work in Super Structure above 3 meter height with fly ash bricks 25cm x12 cm x8 cm tolerance of ± 2% size bricks having crushing strength not less than 75 kg/cm2 with cement mortar 1 cement: 6 sands with all necessary projection, splay cutting, circular moulding, corbelling, etc., including cost of all materials, labour, conveyance, loading ,and unloadining, taxes, royalties, scaffolding, watering, curing, sundries, tools and plants, etc., as per the direction of the Engineer-in-charge. |
| 9 | Providing, lifting, hoisting and laying Reinforced Cement Concrete of M-20 grade in Column base, Column Footings, Raft Foundation,Stem of the Columns, beams, chaujja, fin, lintel, stair case, jali , shelves and slab etc as per approved designs and drawings having a minimum compressive strength ( in work test) 20N. / Square mm. in 15 cm. cubes at 28 days after mixing and test conducted in accordance with I.S. 456 and I.S. 516 using screened & washed sharp river sand for mortar and 10 mm. to 20 mm. size black hard crusher broken granite stone chips of approved quality from approved quarry, washed and cleaned to be mixed in concrete mixture with approved quality of cement including hoisting, lowering, laying and compacting concrete by using vibrators, watering and curing for 28 days including, centering and shuttering then after dismantling and removing the debrises away from the work site and finishing the exposed surface smooth providing grooves or beads wherever necessary including cost etc. complete as per direction of Engineer-in-charge. (A) COLUMN AND BEAM (UPTO 3 MTR.) |
| 10 | (B) COLUMN AND BEAM (ABOVE 3 MTR.) |
| 11 | (C) PLINTH BAND |
| 12 | (D) COLUMN BASE |
| 13 | (E) LINTEL & WALL BAND (UPTO 3 MTR.) |
| 14 | (F) LINTEL & WALL BAND (ABOVE 3 MTR.) |
| 15 | Cutting,Straightening coiled or bent up M.S plain HYSD/TMT reinforcement bars welding or jointing if necessary bending,binding,tying the grills as required for R.C.C works,providing fan hooks where necessary and hoisting, lowering and placing in proper position according to approved designs and drawings including cost, conveyance,loading, unloading & taxes of M.S plain/HYSD/TMT reinforcement bars and binding wires of 18 to 20 gaugo required for the work and cost of all labour, sundries, T&P and scaffolding complete in all respect as directed by the Engineer in charge (payment will be made according to the actual weight of M.S plain/HYSD/TMT reinforcement bars consumed in the work only.(A) GROUND FLOOR |
| 16 | Providing 12 mm. thick cement plaster in all floors at all height with cement mortar of mix (1:6) with cement and screened & washed sharp sand for mortar and finished smooth to the rough surface of the brick masonry wall after racking out joints (along with providing grooves wherever necessary) including watering and curing rounding of corner etc. complete with cost, conveyance, loading, unloading, royalties and taxes of all materials, cost all labour, T & P, sundries and scaffolding required for the work etc as directed by the Engineer in charge.(A) UPTO 3 METER HEIGHT |
| 17 | (B) ABOVE 3 METER HEIGHT |
| 18 | Providing 16 mm. thick cement plaster in all floors at all height with cement mortar of mix (1:6) with cement and screened & washed sharp sand for mortar and finished smooth to the rough surface of the brick masonry wall after racking out joints (along with providing grooves wherever necessary) including watering and curing rounding of corner etc. complete with cost, conveyance, loading, unloading, royalties and taxes of all materials, cost all labour, T & P, sundries and scaffolding required for the work etc as directed by the Engineer in charge.(A) UPTO 3 METER HEIGHT |
| 19 | (B) ABOVE 3 METER HEIGHT |
| 20 | Supplying fitting and fixing of precoated Galvanized iron profile sheet semi gloss of 1000mm width and total coated thickness 0.45mm in roof drilling hole in wind ties including fixing of ridges valleys, wind ties including fixing of ridges valleys,wind ties etc. complete including cost of sheet and all fitting,all taxes labour,T&P etc.complete as per direction of Engineer-in-charge. |
| 21 | Supplying, fabricating, fitting, fixing & erection of M.S Anglur/Tubular truss including all cost, convenyance, taxes etc. complete as per direction of Engineer-in-charge. |
| 22 | Supplying, fabricating, fitting, fixing & erection of purlins including all cost, convenyance, taxes etc. complete as per direction of Engineer-in-charge. |
| 23 | Distempering two coats to walls with primer of approved shade on new work to give an even shade including cost of distemper of all labour with T&P etc, complete as per specification & direction of Engineer-in-charge.Note :- Sample of Paint shall be approved before procurement and use.(A) UPTO 3 METER HEIGHT |
| 24 | (B) ABOVE 3 METER HEIGHT |
| 25 | Distempering two coats to walls with one coat of primer of approved shade (weather coat) on new work to give an even shade including cost of distemper of all labour with T&P etc, complete as per specification & direction of Engineer-in-charge.Note :- Sample of Paint & Primer shall be approved before procurement and use.(A) UPTO 3 METER HEIGHT |
| 26 | (B) ABOVE 3 METER HEIGHT |
| 27 | Painting two coats with approved synthetic enamel paints of Asian / Berger/Dulox make and of approved colour, shade to new Iron work over a coat of red-oxide primer of Asian / Berger make including sand papering, polishing the surface, cost, conveyances, taxes of all materials and cost of all labour with T&P etc, complete as per specification & direction of Engineer-in-charge.Note :- Sample of Paint & Primer shall be approved before procurement and use. |
| 28 | Providing cement punning with red oxide mix using 3.5 kg. of red oxide per 50 kg. of cement (1:3) polishing with carborandum stone including all cost of materials, labour, conveyance, T&P etc. complete as per direction of Engineer-in-charge. |
| 29 | Supplying,fitting,fixing of 0.075mm thick plain Glass strips in floor including cost of all materials, labour, T & P etc. complete as per direction of Engineer-in-charge. |
| 30 | Inserting bituminous expansion joints Board 12 mm. thick of depth 0.075 m. including cleaning, all cost, conveyance, labour, taxes etc. complete as per direction of Engineer-in-charge. |
| 31 | Antitermite treatment in foundations trenches, flooring with appropved chemicals including the cost of materials and labour etc. complete as per direction of Engineer-in-charge. |
| 32 | Supplying, fitting, fixing of M.S Steel ventilator glazed composite with M.S Grill out side iron frame welded with wire netting or mesh with glass pairs including supplying & fixing of putty & wire clips,screw & cost of materials including all cost of all materials, labour, T & P etc. complete as per direction of Engineer-in-charge. |
| 33 | Supplying, fitting, fixing of M.S Rolling shutter with frame with M.S angle of (35 x 35 x 6)mm and shutter section of 30 x 30 x 5mm with weldingof 25 x 6mm flat and welding of 16 gauge C R Sheet with arrangement of clamp,fitting of 3 nos 4\\" hinges,1 no of 2\\"hinges and 300mm x 16mm M.S Aldrop with 8\\" tower bolt including cost, conveyance, taxes of all materials, labour T&P etc.required for the work etc. complete as per direction of Engineer-in-charge. |
| 34 | Cost of J hooks, washer & nuts etc.,5/8\\"X21/2'' nut & bolt for trusses & purlins including all cost, convenyance, taxes etc. complete as per direction of Engineer-in-charge. (market rate) |
| 35 | Supplying fitting and fixing of holding down bolts(600mm X 200mm) & base plate of 8mm thickness including all cost, convenyance, taxes etc. complete as per direction of Engineer-in-charge. (market rate) |
| 36 | Supplying fitting and fixing of wind ties with 35mm X 6mm flat iron including drilling release and fixing in position with all cost, convenyance, taxes etc. complete as per direction of Engineer-in-charge. |
| 37 | Cost, conveyance and labour for admixing sand & moorum(40:60) and spreading in sub base not exceeding 22.5cm in thickness and compaction to required density in OMC with PRR including hire and running charges of PRR as per specification and direction of Engineer-in-charge. |
| 38 | Cost, conveyance and labour for spreading stone screened dust and consolidation with PRR including watering, cost and conveyance of screen stone dust including all cost, conveyance, royalities, taxes etc. complete as per direction of Engineer-in-charge. |
| 39 | Cost,supplying & labour for spreading metal 40 mm to 62 mm for IRC Gr.II metalling to an uniform thickness of 100 mm compacted to 75 mm. And packing the voids with small stones and hand packing the same to proper camber including conveying spreading of filler materials and filling the interstices by spreading the same over the surface watering &consolidation with PRR including hire &running charges of PRR complete including all cost of material conveyanve, royalties,taxes etc. complete as per direction of Engineer-in-charge. |
| 40 | Supplying all materials and labour for solling the road surface with solling stone including filling the interstices with earth/moorum watering and compaction with H R R including all cost of materials, coveyance, royalty of solling stone etc complete as per direction of Engineer-in-charge. Please Enable Macros to View BoQ information |