| 1 | Earth work in excavation of foundation trenches in all kinds of soil including moorum stoney earth and earth mixed with boulders except sheet rock and boulders not requiring blasting including dressing of sides and leveling the bed upto the required depth and depositing the excavated materials away from the work site with all lead and lift including shoring, shuttering & dewatering (if required) with cost of all Labour, Hire & Running charges of the water pumps, Sundries, T & P required for the work complete in all respect excluding GST as directed by the Engineer- in- charge. |
| 2 | Filling in foundation and plinth with excavated materials etc including watering and ramming as directed by the Engineer-in-charge of earth work etc. |
| 3 | Filling in foundation and plinth with with clean coarse river sand including watering and ramming including cost & conveyance of all materials, labours, & T & P all taxes royalty etc complete in all respect as per direction of engineer in charge. |
| 4 | Providing Plain Cement Concrete (1:4:8) in foundation/floor bed concrete using 40 mm & below size b.h.c.b granite stone metal of approved quality from approved quarry including lowering laying concrete watering ramming &curing etc compacting to required level laid in layers not exceeding 4’’ thick including cost conveyance all taxes royalty &cost of all material & labours T&P required for the works etc complete in all respects as per the direction of Engineer in Charge |
| 5 | RCC work M/25 Grade having crushing strength of 250 kg/cm2 after 28 days curing as per using 12mm to 20 mm size b.h.c.b granite chips 20mm size not exceeding 25% including hoisting lowering laying concrete and compacting by using vibrators watering & curing for 28 days including centering, shuttering ,dismemdering to form work &finishing the exposed surface smooth providing grooves beads when ever necessary including cost, conveyance, taxes & royalty of all materials & cost of all labour T&P hire charges of concrete mixture machine & vibrator machine required for the work etc. complete in all respect but excluding the cost of M S rod or tor steel & binding wires & labour charges for cutting bending, binding & tying the grills. As per the direction of Engineer in charge. |
| 6 | GROUND FLOORColumn footing |
| 7 | Column Super Str. |
| 8 | (PLINTH BEAM)Frame BEAM for Ratproof slab Lev Beam (oo+/-)-1.20 Lev. |
| 9 | Wall Beam at 3.850m Lev. |
| 10 | Lintel at 2.10m Lev. |
| 11 | Roof slab/ Canopy slab/ Chajja |
| 12 | FIRST FLOORColumn Super Str. |
| 13 | Wall Beam |
| 14 | SECOND FLOORColumn Super Str. |
| 15 | Wall Beam |
| 16 | RCC Gutter slab |
| 17 | THIRD FLOORColumn Super Str. |
| 18 | Wall Beam |
| 19 | Cutting ,straightening of steel HYSD (Fe- 500D) conforming to (IS- 1786) with bending, binding, cranking, hooking, welding or jointing if necessary & tying the grills and placing in position as required for the Rod work in all floors and & for1 providing fan hooks hosting lowering ,& laying steels including cost conveyance ,taxes & royalties of all materials and binding wires of 18 to 20 gauge & cost of all labour T&P required for the work etc. Complete in all respect as per the direction of Engineer in charges ( payment will be made on weight of MS rod or tersteel only basing on the co- efficient of MS rod or tor steel bars approved by SAIL/ TATA/ competent authority and (No separate payment will be made towards the cost of binding wires over lapping, wastage, coupling, welded, joints , spacer bars, ,chairs stays, hangers and annealed steel wires or other methods for binding and placing etc.) |
| 20 | Ground Floor |
| 21 | 1St Floor @1.80 Qtl/Cum |
| 22 | 2nd Floor @1.80 Qtl/Cum |
| 23 | 3rd Floor @1.80 Qtl/Cum |
| 24 | Providing 25cm thk.Brick work with Fly ash bricks 25cm x 12cm x 8cm size having crushing strength not less than 75 kg/cm2 with dimensional tolerance +/ - 2 percent in cement mortar ( 1 cement: 6 sand), with all necessary projections, splays cutting, circular moulding, corbelling, chamfering, watering and curing etc in F&P superstructure . including cost, coveyance,stacking, loading, unloading, royalties of all materials ,cost of all labour,scaffolding, sundries and T&P required for the works complete in all respect as per specification excluding GST as directed by the Engineer-in-charge. |
| 25 | Foundation and Plinth |
| 26 | Ground Floor |
| 27 | First Floor |
| 28 | 2ND Floor |
| 29 | 3 RD Floor |
| 30 | 16m.m thick cement plaster in cement mortar of mix (1:6) in all floors at all height using screened & washed sharp river sand for mortar with approved quality of cement, finished smooth to the rough surface of the brick masonry walls after racking out the joints properly ,providing grooves wherever necessary including cost, conveyance, loading, unloading,stacking, royalties of all Materials, cost of all Labour, T&P, Sundries , Scaffolding, Watering, Curing,Rounding of corners etc. required for the work complete in all respect as per specification excluding GST as directed by the Engineer- in -charge.(in side wall) |
| 31 | Inside PlasterGround Floor |
| 32 | First Floor |
| 33 | 2ND Floor |
| 34 | 3 Rd Floor |
| 35 | 12 m.m thick cement plaster in cement mortar of mix (1:6) in all floors at all height using screened & washed sharp river sand for mortar with approved quality of cement, finished smooth to the even surface of the brick masonry walls after racking out the joints properly ,providing grooves wherever necessary including cost, conveyance, loading, unloading,stacking, royalties of all Materials, cost of all Labour, T&P, Sundries , Scaffolding, Watering, Curing,Rounding of corners etc. required for the work complete in all respectas per specification excluding GST as directed by the Engineer- in- charge.. |
| 36 | OUT SIDE Ground Floor |
| 37 | First Floor |
| 38 | 2ND Floor |
| 39 | 3 Rd Floor |
| 40 | 6 m.m thick cement plaster in cement mortar of mix (1:4) in all floors to R.C.C surface at all height using screened & washed sharp river sand for mortar with approved quality of cement to the ceiling of the Roof Slab, Staircase, Beams, Columns,Landings, Railings,Chajja ,Fins ,Walls ,Jally and Shelves etc. including roughening, scraping, chiseling, cleaning, closed deep chipping with slurry treatment and finished smooth to all R.C.C. Surface including cost, conveyance, loading, unloading, royalties ,stacking of all Materials, cost of all Labour,Sundries, T&P, Scaffolding,Watering, Curing etc. complete in all respectas per specification excluding GST as directed by the Engineer- in- charge |
| 41 | OUT SIDE Ground Floor |
| 42 | First Floor |
| 43 | 2nd. Floor |
| 44 | 3 Rd Floor |
| 45 | Providing 25mm thick grading concrete in C.C. (1:2:2) laid in proper slope over terrace roof slab by using two part of sand, one part of cement and two parts of 6mm size black hard crusher broken granite chips with addition of water proofing compound of approved quality to be mixed with specified ratio including watering, curing, cost, conveyance, royalties, taxes of all materials, cost of all labour, T&P etc. complete in all respect excluding GST as per specification as directed by the Engineer-in-Charge. |
| 46 | Providing,laying fixing of 16 mm thick KOTA Tiles of area above 0.10 Sqm in flooring of approved quality, ccolour and size in floors, treads on steps and landings in all floors at all height on 25mm thick bed of cement mortar of mix (1:1) laid in proper slope and gradient with screened and washed sharp sand for mortar and grouted with neat white cement slurry jointing the tile with neat white cement slurry mixed with required quantities of pigments of approved marks to match the shades of the KOTA tiles(if required) watering and curing up to 21 days, including cost, conveyance, loading, unloading, royalties of all materials, cost of all labour, sundries, T&P required for the work including rubbing mechanically and wax polishing etc. complete in all respect excluding GSTas per specification as directed by Engineer-in-charge(Note- Sample of tiles shall be approved before procurement and use.) |
| 47 | Providing, fitting and fixing of 16 mm thick KOTA Tiles of area upto 0.10 Sqm for dados of approved quality, colour and size in dado/skirting , riser of steps in all floors at all height on 12mm thick bed of cement mortar of mix (1:3) laid in proper slope and gradient with screened and washed sharp sand for mortar and grouted with neat white cement slurry jointing the tile with neat white cement slurry mixed with required quantities of pigments of approved marks to match the shades of the Kota tile( if required ) watering and curing up to 21 days, including cost, conveyance, loading, unloading, royalties of all materials, cost of all labour, sundries, T&P required for the work including rubbing mechanically and wax polishing etc. complete in all respect as per specification as per specification as directed by Engineer-in-charge.(Note- Sample of tiles shall be approved before procurement and use.) |
| 48 | Providing and fixing in position of galvanised Rolling Shutter made of required SiZE (3.80x3.80)m double skined galvanised steel lath each lath is retained by interlovcking together including cost,conveyance,loading,unloading, of all materials, cost of all labour required for the work complete in all respect excluding GST as per specification as directed by Engineer-in-charge |
| 49 | TRUSSLESS ROOFING SYSTEM (I) Designing, Fabricating, installing and fixing Self supported mechanically seamed roofing system by American Hydraulic operated profile machine for fabricating, seaming, bolting, etc. made of high quality steel of any approved brand having 350MPA yield strength(pre coated galvalume sheet) as per specification noted below.(II)Product Description : “Supplying and Installation of Self Supported Arch Shaped Galvalume Roofing made up of Superior Quality Structural Grade Steel, having Base Metal Thicknesses ranging from 1.00 MM, Thickness Tolerance (+/- 0.05MM), Coil Width of 912MM (+/- 2 MM), and, Profile width of 625 MM (+/- 10MM). Color Coated Galvalume Sheets complied to ASTM A792 Standards with Coating mass AZ 150, Yield Strength 350 mPA minimum to be used. Fabrication and Installation of Self Supported Roofing to be carried out using American Hydraulic Profile Machines and joined by mechanical seamers only. |
| 50 | (III) Execution of Works Contract for Self Supporting Roof on your following buildings of dimensions as mentioned below : : Span/5 – Full Arch (a) Span : 12.50 mtrs ( Column In to In) (b) Arch Rise : 2.50 mtr. (c) Length :-20.20m (with projection) (d) Arch Length : 15.00 mtrs (e) No of Bays : 1 No. (f) Area Per Bay : 1400 SQM (g) Column Height : 11.55 mtrs Material Specification : Grey White RAL 9002 Color Coated Galvalume Sheet -ASTM A792 Std. (IV) The agency shall have to produce the Quality assured certificate obtained from the concern Company/ Manufacture's Engineering head along with detail shop drawings and design with wind load calculation sheet etc. before final parment.(FOR TRUSSLESS ROOFING SYSTEM AN AMOUNT OF 5% OF THE EXECUTED WORK AMOUNT WILL BE RETAINED AS SECURITY DEPOSIT FOR 3 YEARS ON AND ABOVE THE REGULAR SECURITY DEDUCTION) |
| 51 | Roofing area |
| 52 | Painting to external surface of building with two coats of weather coat Paint of approved shade and quality over a coat of Primer after cleaning the surface to be painted in all floor & at all heights including cost, coveyance, loading , unloading ,stacking of all Materials, cost of all Labour,Sundries, Scaffolding, T&P required for the work etc. complete in all respect excluding GST as per specification as directed by Engineer-in-charge. |
| 53 | Out side Area Ground Floor |
| 54 | First Floor |
| 55 | 2ND Floor |
| 56 | 3 Rd Floor |
| 57 | Finishing walls with water proofing cement paint of approved shade on new work TWO coats to give an even shade overa coat of grey cement wash to out side area including cost of brushes including cost of paint.including cost and conveyance of all materials &Labour at all floor & at all heights including cost, coveyance, loading , unloading ,stacking of all Materials, cost of all Labour,Sundries, Scaffolding, T&P required for the work etc. complete in all respect excluding GST as per specification as directed by Engineer-in-charge. |
| 58 | Inside AreaGround Floor |
| 59 | First Floor |
| 60 | 2ND Floor |
| 61 | 3 Rd Floor |
| 62 | Providing and painting two coats with synthetic enamel paint of approved quality and approved shade on steel work in all floors at all height of approved quality and shade including sand papering and making the surface smooth with cost, coveyance, loading and unloading of all materials, cost of all labour, sundries, T&P, scaffolding etc. required for the work and complete in all respect excluding GST as per specification as directed by Engineer-in-charge. |
| 63 | Providing and fixing of UPVC sliding windows 2 track sliding-60 series/Top hung ventilator of any approved make ,duly manufactured using upvc reinforced profiles of 62mmx60mmxx2.25mm for outer frame,66mmx38mmx2.25mm for sliding shutter frames capable of mounting single glazing system,structurally reinforced with hot dip galvanised upto 50 microns of minimum thickness of 1.2 mm prefabricated and welded through fusion welding & the window sash shall be fitted with 6 mm thick clear float glass of reputed make duly fixed with EPDM weathering seal including the cost of all materials,necessary locking arrangements ,fittings,cost of labour,T&P ,etc. complete in all respect excluding GST as perspecification as directed by the Engineer- in- charge. |
| 64 | Supply ,fitting and Fixing of M.S. Weld mesh Jali of vent size(25mmx25mm )& 11 gauge in floor bed concrete by nails, before casting RCC mat slab at floor as rat proof item.including cost and conveyance of all materials labours T&P etc all complete as per the direction of Engineer in Charge. |
| 65 | Supplying, fitting and fixing of M.S grills, grill gates with top and bottom rails, steel windows, steel doors, steel frames for doors and windows, staircase and parapet railing ( as per I.S. specification and as per approved drawings ) in proper position in all floors and at all height including making holes to brick walls/ R.C.C structure/wood work etc. and making good to the damaged walls/ structures with cement concrete (1:2:4) with black hard crusher broken granite stone chips of 12mm to 20mm size ( 20mm size not to exceeds 25% ) including watering and curing etc. complete in all respect excluding GST as per specification as directed by Engineer-in-charge. ( W.I. / M.S. windows grills, grill gates, collapsible gates with top and bottom rails, steel windows, steel doors, steel frames for doors and windows, staircase and parapet railings square bar along with required nos. of nails and screws and other required materials of approved quality and approved size shall be supplied by the contractor at his own cost.) |
| 66 | Supply and installation of Turbo Ventilators of 600mm dia made up 306 grade &1mm thk. S.S. sheet for turbine blade with heavy duty PVC base including M.S frame &Clamps fitted to roof ing sheet as per approved drawings , design and site requirement, cost and conveyance of all materials labours T&P etc all complete as per the direction of Engineer in Charge. Please Enable Macros to View BoQ information |