|
| 1 | Earth Work in excavation of foundation in dry soil. including lift up to 1.5m and lead up to 30m. and including back filling watering ramming and dressing of excavated earth in to the trenches or in to the space between or in to the plinth with removal and disposal of surplus earth as directed by Engineer in charge etc. complete |
| 2 | Plain Cement Concrete 1:3:6 in cement coarse sand and stone grit foundation including all labour, material T&P etc. |
| 3 | Class - 150 ( Non modular ) brick work in 1:3 cement and coarse sand of FM not less than 1.25 mortar in foundation including supply of all material, labour and T&P etc. required for proper completion of the work. |
| 4 | Reinforced Cement Concrete work for Super structure of M20 (1:1.5:3) mix coarse sand of F.M. not less than 2.25 and 20 mm graded coarse aggregate including cost of all materials, labour charges, curing work, T&P etc but excluding supply of reinforcement and its bending and including its fixing and binding the same with 24 BWGI binding wire and including necessasary centering and shuttering. required for proper completion of the work. |
| 5 | Centring&Shuttering For R.C.C Work I/C All Cost Of Labour T&P etc Complete For Proper Completion Of Work |
| 6 | Supplying and laying TMT Steel bar reinforcement as per approved drawing, including removal of rust, cutting, bending, binding, placement with proper overlapping, providing chairs etc. required.The item includes cost of all material, labour charges, providing & binding with 24 BWG binding wire, T&P, taxes etc. required for proper completion of the work. |
| 7 | Struck Pointing With Cement Mortar Consisting of 1:2 (Cement:Fine Sand of 1.25 Finenes Modulus On Brick Work Including Supply Of all Materials Labour And Completion Of Work. |
| 8 | Supplying & Fixing 100 mm dia PVC Drainage Pipe i/c all cost of material, T&P etc for Proper complition of work. |
| 9 | S/F Tarfelt on Abutment cap i/c all cost of materials, T&P etc for proper completion of work. |
| 10 | Providing of Expansion Joint including cost of all labour, materials, T&P etc. Complete. |
| 11 | Providing & Fixing wheel guard of size 230 x 230 x 900 including cost of all labour and T&P etc. Complete. |
| 12 | Supply and Fixing of M.S. Angle Sign Board 1.200mx0.90m including cost of material,Taxes, labour T&P etc Complete. |
| 13 | Earth work in filling for making Ramp and with compaction in 20.00 cm layers and also including labour T&P etc i/c lead up to 600 mt. and also i/c ramming. Dressing by manual etc comp. |
| 14 | Providing & Laying Of R.B.M. I/C all Cost Of material, Labour T&P etc. Comp . |
| 15 | Providing Brick on edge Soling Including cost of all labour and T&P etc but i/c cost of bricks Complete. |
| 16 | Earth work in Disposal of Earth from the road of Diversion including cost of all labour and T&P etc complete. Please Enable Macros to View BoQ information |