| 1 | 11.5.3:- 12 mm cement plaster of mix : 3. 1:4 (1 cement: 4 fine sand) [Through Rate] |
| 2 | 13.29.1:- Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 1. In stringers, treads, landings etc. of stair cases, including use of chequered plate wherever required, all complete [Through Rate] |
| 3 | 11.58:- Providing and applying two coats white cement based putty of approved brand and manufacturer, over plastered surface and grinding the surface smooth with sand paper to get en even and smooth finish including cost and carriage of all material , labour charges, scaffolding, sundries etc. complete [Through Rate] |
| 4 | 23.5.1.3:- COPPER WIRING IN EXISTING PVC/MS CONDUIT PIPE SURFACE/RECESSED FOR ELECTRICAL POINTS 1.3. Wiring only in 1.5 sqmm PVC insulated copper conductor cable for LIGHT/FAN/ all bell point in existing conduit pipe and MS boxes including cost of Bakelite cover for MS box, switch, wall socket, ceiling rose/connector etc. Group C [Through Rate] |
| 5 | 23.5.6.2:- COPPER WIRING IN EXISTING PVC/MS CONDUIT PIPE SURFACE/RECESSED FOR ELECTRICAL POINTS 6.2. Wiring main and sub mains in two single core for phase and neutral wire and one single core for earth wire PVC insulated Copper conductor cable 1100 Volts grade in existing MS/PVC Conduit etc as required. 1 run of Size 2.50 Sqmm(1.1.80mm) [Through Rate] |
| 6 | 7.22.1:- Brick work with common burnt clay non-modular bricks of class designation 10.5 in superstructure above plinth level up to floor IV level in all shapes and sizes in : 1. Cement mortar 1:4 (1 cement : 4 coarse sand) [Through Rate] |
| 7 | 23.22.1.1:- MCCB ,DISTRIBUTION BOARDS, MCB`s, RCCB`s, CHANGE OVER etc. 1.1. Supply and erection of Modular case circuit breaker single pole/4 pole on existing wall/pedestal/Panel including bounding to earth and making necessary connections required to complete the job in all respect up t the entire satisfaction of the Engineer- in-charge of the work. Double pole MCCB 16 to 63 Amp, 25 Ka [Through Rate] |
| 8 | 30.28.1:- Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : 1. One or more coats on old work [Through Rate] |
| 9 | 30.37.1:- Finishing walls with Acrylic Smooth exterior paint of required shade : 1. Old work (Two or more coat applied @ 1.67 litre/ 10 sqm) on existing cement paint surface [Through Rate] |
| 10 | 6.25.2:- Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centerin , shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge. 2. All works above plinth level up to floor IV level [Through Rate] Please Enable Macros to View BoQ information |