| 1 | Wiring with 2 x1.5 sq.mm. PVC insulated single core unsheathed FRLS copper conductor of 1100 V grade in suitable PVC rigid pipe on wall and ceiling and switch drop portion PVC rigid pipe concealed in wall with PVC accessories with Module GI switch box in flush with wall with 6A one way module switch with module front plate Suitable colour for Concealed PVC Light point / fan point (for electronic regulator) ( 5 points / Coil) Lower End SD No 35 |
| 2 | Wiring with 2 x1.5 sq.mm. PVC insulated single core unsheathed FRLS copper conductor of 1100 V grade in suitable PVC rigid pipe on wall and ceiling and switch drop portion PVC rigid pipe concealed in wall with PVC accessories with Module GI switch box in flush with wall with 6A one way module switch with module front plate Suitable colour for Concealed PVC Plug Point SD No 38 |
| 3 | Supply and fixing of single box type 4'20W LED fitting with LED (Higher End) complete with TW round blocks on wall or ceiling with PVC unsheathed FRLS Copper leads from terminals to the fitting Sd No 446 |
| 4 | Supply and fixing of 25W LED 2x2 square type Recessed fitting with LED (Lower end) on false Ceiling with suitable hanging support from ceiling with PVC unsheathed copper leads from terminals to the fitting. Sd No 455 |
| 5 | supply and fixing of 1200mm (56\\") sweep AC ceiling fan High speed complete with 2 module 100W fan step regulator (Higher end) with 300mm down rod with fan clamp with side plates and cross arm of size 450mm (18\\") SD No 110 |
| 6 | Fabricating supplying and fixing in position of aluminium anodised natural colour matt finish half panelled with 12mm thick bothside prelaminated partile board at bottom and half glazed using 5.50mm thick Plain glass at top double leaves door with 0.3m fixed ventilator at top. The outer frame shall be with aluminium box section 101.60x44.45x3.18m at 2.319kg/m and with the Shutter frame made of section with Vertical & Top rail: [email protected] kg/m Bottom rail:100x44.45x2.50mm@ 1.974 kg/m,Lock rail : 50x44.45x2.5mm @ 1.292 kg/m,Alu.Clips: 17.15x17.27x1.50mm @ 0.176 kg/m,Alu. Handle: 100x30mm @ 0.988 kg/m and Inner Frame of section 63.50x38x3 [email protected] kg/m and necessary accessories such as aluminium clips, rubber beading PVC felt, handle for a length of shutter (both sides), locking arrangements, furniture fittings such as aluminium tower bolts-250x12mm -2Nos, aluminium tower bolt 200x12mm - 1No, aluminium door stopper with rubber bush - 2Nos ., lock-1No.,Hydraulic Door closer as per BIS standards including cost of all materials, labour charges and power consumption charges required for fabrication including chipping dismantling and making holes to the required extent in RCC in column/beam/masonry with power drill wherever neccessary and redoing the demaged portion to the original condition after fixing etc. complete.All Aluminium section shall be used in electrically controlled condition in accordance with ISI specification 1868/1962 for anodic film thickness of not less than 15 microns for glazing portion Aluminium sections and furniture fittings shall be got approved by the Executive Engineer incharge. |
| 7 | Supplying and fixing in position 15mm dia brass CP screw down tap / Pillar tap / Swan neck tap (heavy duty) of approved make conforming to BIS specifications and quality including cost of shellac, thread, etc., complete complying with standard specification and including cutting and threading wherever necessary. (Taps should be got approved by the Executive Engineer before use on the works) |
| 8 | SD Tap |
| 9 | Piller Tap |
| 10 | Supply and fixing of 63 Amp 30 MA Four Pole RCD / RCCB (Higher End) including all labour charges etc., complete as per standard specifications. |
| 11 | Supply, Delivery and fixing of PVC Pipes and specials etc., complete as per standard specifications |
| 12 | 110mm PVC Pipe |
| 13 | 75mm PVC Pipe |
| 14 | 32mm PVC Pipe |
| 15 | 25mm PVC Pipe |
| 16 | 110mm PVC Elbow |
| 17 | 110mm PVC Tee |
| 18 | 110mm PVC Elbow With Door |
| 19 | 110mm PVC Tee With Door |
| 20 | 32mm PVC Elbow |
| 21 | 32mm PVC Tee |
| 22 | 32mm PVC Coupler |
| 23 | 25mm PVC Elbow |
| 24 | 25mm PVC Tee |
| 25 | 25mm PVC Coupler |
| 26 | Painting two coats with ready mixed Plastic Emulsion Paint S.I.358 Plastic emulison paint of'approved quality and colour over a priming coat, including thorough scraping, clean removal of dirt, etc complete and including necessary plaster of paris, putty, wherever required including cost and conveyance of all materials etc.and all lobour charges etc.complete as per Standard specification and as directed by the departmental officers. TNBP No:66-A. |
| 27 | Supply and installation of Acoustical False Ceiling of Mineral Fibre/ GRG Core Ceiling Tiles of size 595 x 595 x 15mm having volume density 270 kgs / m3, weight 4kg / m2 which is suspended by using 0.3mm thick T15 metal grid system. The T15 metal grid system of 600 x 600mm module includes WA15 W30 wall angle with unequal flanges of 15 / 19mm, length 3000mm, fixed along the perimeter of walls with the help of nylon sleeves and suitable fasteners at 300mm centers. Then suspend the MT15 W36 MainT with flange width 15mm, height 32mm and length 3600mm, from the soffit slab with help of soffit cleat and wire rod with leveling spring clip at 1200mm centres. CT15 W12 CrossT with flange width 15mm, height 26mm and length 1200mm is interlocked into the pre-cut slots in the Main T15 at 600mm centers in the perpendicular direction to the Main T15. Finally CT15 W06 CrossT with flange width 15mm, height 26mm and length 600mm are interlocked into the precut slots in the CT15 W12 CrossT in direction parallel to the Main T15 to result in 600 x 600mm module. Mineral Fibre/ GRG Core Ceiling Tiles of size 595 x 595 x 15mm shall be placed into the grid size of 600 x 600mm. The systems to achieve noise reduction coefficient not less than 0.5 NRC, so as to have an neat appearance as directed by the department offices. The cost includes, cost of material, cost of labour, Scaffolding, transportation, conveyance, etc., complying to standard specication. |
| 28 | Supplying and filling in foudation and basement with Crushed Stone Sand (M- Sand) in layers of not more than 15cm thick including well rammed watered and consolidated including cost and conveyance of Stone Dust to work site from approved sources and including labour charges for all lead, Stone Dust lift, filling, laying, levelling, watering and compacting including all other incidental charges etc., complete complying with standard specifications(TNBP No.24&25). |
| 29 | Plain Cement Concrete 1:4:8 mix (One Cement, Four Fine Aggregate and Eight Coarse Aggregate) Using 40mm ISS HBG metal for foundation and basement including dewatering if found necessary and laid in layer of not more than 15cm thick and consolidated including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers (TNBP No.28). |
| 30 | Brick Work in Cement Mortor 1:5 Mix (one cement, five M- Sand) using new best II Class Bricks of size 9 ” x 4 3/8 “x 2 3/4 ” from approved quarry including cost and conveyance of all materials to site. Loading and unloading charges and labour charges for mixing, laying and curing etc. complete. Complying with std. specifications.(For 10 M3) |
| 31 | Plastering in Cement Mortor 1:5 Mix (one cement, five M- Sand) 12mm thick including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. Complying with std. specifications. |
| 32 | Painting Old iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with Two coats of best approved first quality and colour of synthetic enamel paint in all floors etc., complete complying with standard specification and as directed by the departmental officers.(The make, quality and colour of paint should be got approved by the Executive Engineer before use on works.) |
| 33 | Manufacturing, supplying and fixing Precast Reinforced Cement Concrete slabs of following thickness in RCC 1:2:4 (one cement, two crushed stone sand and four aggregates), using following HBGS jelly excluding cost of reinforcement steel in position but including cost of moulding charges, casting of slab, finishing, curing and fixing in position in all floors etc., complete complying with standard specification and as directed by the departmental officers 75 mm Thick |
| 34 | Supplying and fixing Mild Steel grills for windows, ventilators etc.,complete complying with standard specifications and as directed by the departmental officers. |
| 35 | Supplying of haier Steel ice Lined refrigerator capacity 225 litres-Gem portal Please Enable Macros to View BoQ information |