|
| 1 | Loading, carriage & unloading of following centralized materials from centre store (ESC Lakhimpur) to work site and its stacking. Distance approx (0-15) kms. Under work area of EDD Lakhimpur |
| 2 | PCC/ST pole 8.5/9/11 Mtr long |
| 3 | 11 kv Polymeric Disc Insulator with fitting |
| 4 | 11 kv Polymeric Pin Insulator with GI pins |
| 5 | Distribution Box 3 Phase |
| 6 | ACSR Rabit/Dog /Racoon/weasel/ conductor |
| 7 | ABC( 3x95+ 1x70 + 1x16) Sqmm. |
| 8 | LT XPLE 1X240 sq.mm |
| 9 | 11 KV Fuse Set |
| 10 | 11 KV Stay Set |
| 11 | Earth rod |
| 12 | Line Material (V-type X-arm, F-Clamp, T-off, Channel, Angles, Top , Dropper, G.I wire, Stay wire etc) |
| 13 | Loading, unloading and installation of 250 kVA Additional New TF with other required line materials (like lugs etc) which are included in estimate from centre store to work site at Mo. Kheri Road near Dr. Pawan Garg, Company Baag, DC road Machi Kothi, Railway Patri, Bus Station infront of Tej Narayan & Tharwarnganj with its stacking. successfully energization Under work area of EDD-Lakhimpur |
| 14 | Loading, carriage, unloading & Errection of 250kVA TF with other material which are included in estimate from centre store to work site near Vilobhi Hall, near Kotwali with its stacking. Dismounting & carriage of old TF of 100kVA from site to DTC centre and Proper connection at HT/LT of New T/F and successfully energization Under work area of EDD-Lakhimpur |
| 15 | Construction new plinth of 250 KVA Distribution transformer of size 5x7x4 Fit with first class bricks, cement and coarse sand as per RESPO Norms alongwith cost of materials. to work site Mo. near Vilobhi Hall, near Kotwali, Kheri Road near Dr. Pawan Garg, Company Baag, DC road Machi Kothi, Railway Patri, Bus Station infront of Tej Narayan & Tharwarnganj work area of under EDD-Lakhimpur |
| 16 | Construction new Fencing of 250kVA distribution Transformers installed at Mo. near Vilobhi Hall, near Kotwali, Kheri Road near Dr. Pawan Garg, Company Baag, DC road Machi Kothi, Railway Patri, Bus Station infront of Tej Narayan & Tharwarnganj work area of under EDD-Lakhimpur by MS Sqaremesh fabricated on MS angles of size 50X50X6mm and MS strip having overall dimension complete with one no gate with provision of hinges roller & lacking arrangement properly grouted and painted with one coat of Red Oxide primer and two coasts of Bus Green Super enamel Paint. |
| 17 | Work for earthing of Distribution Transformer with G.I. Pipe type earthing pipe size 3cm dia from ground up-to the water level (Minimum 20 feet deep) as per standard practice (Al materials shall be provided by the contractor) in work area of Mo. near Vilobhi Hall, near Kotwali, Kheri Road near Dr. Pawan Garg, Company Baag, DC road Machi Kothi, Railway Patri, Bus Station infront of Tej Narayan & Tharwarnganj Under EDD-Lakhimpur. |
| 18 | Fabrication of structure for 2 no.Tailless Units using 65x65x6 mm MS Angle (8 mtr. total length) including grouting of 2 no. angles 900 mm depth, providing and fixing of 8 no. suitable size of lugs and making ends of the LT cable of 250 kva distribution T/F and necessary extension of the fencing will be done by the contractor as per site requirement upto total length of fencing 2 mtr. with providing by the Contractor all material, labour and t&p required for proper completion under EDD Lakhimpur. |
| 19 | Grouting and Nuzzling of stay set complete including fixing of necessary clamps. Accessories required including its grouting by civil material (Sand: brick ballast: cement). Only stay rod and Stay wire shall be supplied by the Department. |
| 20 | Dragging of ST/PCC pole to pit site, digging of pit erection and grouting (As per RESPO norms) of 11KV 9/11/8.5 mtr long ST/PCC pole with fixing of necessary items, such as V-type X-arm, F-bracket, 11KV Pin/Disc insulator, guarding angle(1.8 mm65x65x6) with nut & bolts its ramming as per RESSPO Specification. |
| 21 | Supply & Fixing of Decentralized Material. |
| 22 | Stone Pad |
| 23 | Earthing wire Clamp with Bolt and nuts |
| 24 | Longs Barrel lugs for DT |
| 25 | Eye-Hook |
| 26 | Dead end Clamp |
| 27 | Suspension Clamp |
| 28 | J-hook |
| 29 | Clamp for 3-Ph Distribution box |
| 30 | Holding Clamp with nuts and bolts |
| 31 | Nuts, bolts& washers |
| 32 | Stay Clamp |
| 33 | Stay Insulator Please Enable Macros to View BoQ information |