| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. |
| 2 | Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6 mm angle iron and 3 mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, including applying a priming coat of approved steel primerUsing flats 30x6mm for diagonal braces and central cross piece. |
| 3 | Providing and fixing factory made uPVC door frame made of uPVC extruded sections having an overall dimension as below (tolerance ±1mm), with wall thickness 2.0 mm (± 0.2 mm), corners of the door frame to be Jointed with galvanized brackets and stainless steel screws, joints mitred and Plastic welded. The hinge side vertical of the frames reinforced by galvanized M.S. tube of size 19 X 19 mm and 1mm (± 0.1 mm) wall thickness and 3 nos. stainless steel hinges fixed to the frame complete as per manufacturer’s specification and direction of Engineer- in-charge9.117.1 Extruded section profile size 48x40 mm |
| 4 | 24 mm thick factory made PVC door shutters made of styles and rails of a uPVC hollow section of size 59x24 mm and wall thickness 2 mm (± 0.2 mm) with inbuilt edging on both sides. The styles and rails mitred and joint at the corners by means of M.S. galvanised/ plastic brackets of size 75x220 mm having wall thickness 1.0 mm and stainless steel screws. The styles of the shutter reinforced by inserting galvanised M.S. tube of size 20x20 mm and 1 mm (± 0.1 mm) wall thickness. The lock rail made up of 'H' section, a uPVC hollow section of size 100x24 mm and 2 mm (± 0.2 mm) wall thickness, fixed to the shutter styles by means of plastic/galvanised M.S. 'U' cleats. The shutter frame filled with a uPVC multi-chambered single panel of size not less than 620 mm, having over all thickness of 20 mm and 1 mm (± 0.1 mm) wall thickness. The panels filled vertically and tie bar at two places by inserting horizontally 6 mm galvanised M.S. rod and fastened with nuts and washers, complete as per manufacturer's specification and direction of Engineer-in-charge. (For W.C. and bathroom door shutter) |
| 5 | P/F WINDOW |
| 6 | Providing and fixing white vitreous china water closet squatting pan (Indian type) : Long pattern W.C. pan of size 580 mm |
| 7 | P/F 25MM P.S . FLOORING 1:2:4 |
| 8 | P/F flyash brick work 1:6 cm , f/p |
| 9 | P/F flyash brick work 1:6 cm , f/p |
| 10 | Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finishedwith a floating coat of neat cement, including cement slurry, but excluding the cost of nosing ofsteps etc. complete. 40 mm thick with 20 mm nominal size stone aggregate |
| 11 | 12 mm cement plaster of mix :1:4 (1 cement: 4 fine sand) |
| 12 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral staircases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement: 1.5 coarse sand (zone-III)derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources).cum |
| 13 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inposition and binding all complete upto plinth level. Cold twisted bars |
| 14 | 12 mm cement plaster of mix :1:6 (1 cement: 6 fine sand) |
| 15 | 6mm cement plaster of mix : 1:3 (1 cement : 3 fine sand) |
| 16 | White washing with lime to give an even shade : Old work (two or more coats) |
| 17 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : One or more coats on old work |
| 18 | Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings, including fixing thepipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. Internal work - Exposed on wall15 mm nominal outer dia Pipes |
| 19 | Providing and fixing PTMT bib cock of approved quality and colour. 15mm nominal bore, 86 mm long, weighing not less than 88 gms |
| 20 | Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes.110 mm diameter |
| 21 | Honey-comb brick work 10 / 11.4 cm thick with common burnt clay bricks of class designation7.5 in super structure above plinth level upto floor V level with cement mortar 1:4 (1 cement : 4coarse sand). |
| 22 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |