| 1 | M&L for dismantling end plates of condenser unit shell & tube type of central AC plant carefully and refixing the same after descaling by using descaling solution with descaling pump & replacement of rubber /fiber gasket, rusted nutbolt, etc of both end of condenser all as specified and directed for the condenser of the central type AC plant of following capacity as under. |
| 2 | Central AC Plant Screw type 3x130 TR capacity |
| 3 | Cleaning complete air filter of AHU of central AC Plant screw type 3 x 130 TR capacity by soft brush & using air pressure gun complete all as specified and directed. |
| 4 | Dismaintling carefully blower motor from AHU of central AC plants including un screwing of nut/bolts, washer, belt and replacement of defective bearing set of two (as per sample) etc and complete oiling, greasing, cleaning, servicing and assmebling and refixing at the same position of following capacity all as specified and directed. |
| 5 | 25 HP (3x130 TR Screw type AC Plant) |
| 6 | 10 HP (3x130 TR Screw type AC Plant) |
| 7 | 7.5 HP (3x130 TR Screw type AC Plant) but without replacement of bearing set |
| 8 | M&L for Opening up the section charging valve of central AC Plant 3 x 130 TR and carefully charging refrigernt gas 134 a as per requirement at site in the whole system and making leakage proof for smooth functioning complete all as specified directed. |
| 9 | M&L for repair of chiller water make up tank with insulating material complete all as specified and directed. |
| 10 | De-scaling of complete system of chilled water supply of 130 TR Plant and return line of all including cleaning of strainers , using descaling compound and removing all waste/foreign materials complete all as specified and directed. |
| 11 | Dismantling of compressor side, taking out of all the parts, dismantling of 04 Nos. existing old bearing of compressor side and 04 Nos bearings of Motor Side, refitting of new bearings of compressor, refitting of stator in to body shell and termination of lead connections and testing including rewinding of stator complete all as specified and directed. |
| 12 | S&F in repair for following items/parts as under: |
| 13 | Drier cores |
| 14 | Bearing for motor. |
| 15 | Motor winding sensor. |
| 16 | Oil Pump. |
| 17 | Chiller temprature sensor. |
| 18 | Solenoid Valve |
| 19 | Transducer. |
| 20 | Oil level switch. |
| 21 | Condenser temprature sensor. |
| 22 | Internal oil filter. |
| 23 | External oil Filter |
| 24 | M&L for assembling complete compressor unit including motor hausing oil bearing 01 set 04 nos and supply and fixing new screws male & female 01 set, ORIFICES pressure release valve, loading and unloading valves, assembling rotor into body shell and connecting leads complete all as specified and directed. |
| 25 | M&L for testing of complete compressor unit in the plant after necessary repair including pressure vacuumization, including cooling of complete plant to the entire satisfaction of Engr in charge complete all as specified and directed. |
| 26 | S&F in replacement of 400 A MCCB 4 Pole 415 volts 36 KA 50Hz with thermal and magnetic release with new ones complete all as specified and directed. |
| 27 | Dismantling complete cooling tower from top of building removing unservicable fills, FRP sheets, taking out complete cooling tower including unscrewing nuts/ bolts, washer and cleaning complete area, removing all foreign materials, painting the channels and fixing new PVC fills, FRP sheets (as per sample) making leak proof container of tower completely and testing complete all as specified and directed. |
| 28 | Supply and Filling Compressure Oil for Central AC Plant 3 x 130 TR screw type complete all as specified and directed. |
| 29 | Taking down unserviceble power contactor from SCPM board of central AC Plant screw type 3x130TR and supply and fixing new power contactor and making electrical connection (as per sample) and testing complete all as specified and directed. |
| 30 | Taking proper shutdown unscrewing of strip heater fin type, 3 KW, disconnecting electric connection and replacing by the new one strip heater and making electric connection and screweing nuts/ bolts properly and testing complete all as specified and directed. |
| 31 | S & F in repair 3 pole contactor 440 V ,coil voltage 220, 25 Amp as per sample |
| 32 | S & F in repair 3 pole contactor 440 V ,coil voltage 220, 32 Amp as per sample |
| 33 | S & F in repair 3 pole contactor 440 V ,coil voltage 220, 50 Amp as per sample |
| 34 | S & F in repair Over load relay 16Amp to 24 Amp as per sample |
| 35 | S & F in repair Over load relay 24 Amp to 32 Amp as per sample |
| 36 | S & F in repair timer delay relay 9 Sec to 30 Sec as per sample |
| 37 | S&F in repair M S pipe 200 mm dia medium grade with all necessary fitting includings ( sockets, tee ,elbow etc including welding where required)complete all as specified and directed. |
| 38 | S&F in repair for butterfly valves high quality 200 mm dia , complete all as specified and directed. |
| 39 | Supply and fixing in replacement of Amp meter ,range 0 Amp to 800 Amp capacity with base with new ones complete all as specified and directed. |
| 40 | Supply and fixing in replacement Volt meter ,range 0 volt to 500 volt with base with new ones complete all as specified and directed. |
| 41 | Supply and fixing in replacement of indicator lamp/bush button/element all as per sample complete all as specified and directed. |
| 42 | S&F in repair for M S Y Type strainer high quality 200 mm dia complete all as specified and directed. Please Enable Macros to View BoQ information |