| 1 | Provision for dismantling of lime concreting very carefully of roof area of Ancestral house of Dr. Rajendra Prasad Jiradei (Roof area) |
| 2 | ProvisionforLimeconcretingwithLimemortar1:1:1:4 (1lime :1Surkhi :1Coarse Sand :1 Brick aggregate) including cost of labour & materials charges etc. all complete. (Roof area) |
| 3 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer – in- charge. (Mandapa House) |
| 4 | Centering and shuttering including strutting, propping etc. and removal of form for Suspended floors, roofs, landings, balconies and access platform (for main dome) |
| 5 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement – All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)derivedfromnaturalsources3graded stone aggregate 20 mm nominal size derived from natural sources) (for main dome) |
| 6 | Provision for cement concrete of specified grade excluding the cost of centering and shuttering – All work uptoplinthlevel:1:2:4(1cement:2coarsesand(zone III) : 4 graded stone aggregate 20 mm nominal size). For pedestal of Mandapa House |
| 7 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placinginpositionand binding all complete up to plinth level. Mild steel and Medium Tensile steel bars (for main dome) |
| 8 | Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete.(for room and verandah area) |
| 9 | Finishing walls with Acrylic Smooth exterior paint of required shade: New work([email protected] ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20kg/ 10sqm) (for room and verandah area) |
| 10 | Provision for 40 cm Diameter Pilling as foundation up to a depth of 2 m including with all completed (For mandapa house) |
| 11 | Earth work in excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge: All kinds of soil. (for main dome pedestal) |
| 12 | Provision for dismantling of old plaster or skiting racking out joint and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 meters lead. |
| 13 | Provision for plaster 20 mm over outer wall of mix : 1:4 ( 1cement : 4 coarse sand) including materials & labour etc complete. |
| 14 | Provision for plaster 12 mm over interior wall of mix : 1:4 ( 1cement : 4 coarse sand) including materials & labour etc complete. |
| 15 | Provision for shifting and reinstallation of Sculpture of Dr. Rajendra Prasad |
| 16 | Provision for painting over steel work with Deluxe Multi Surface Paint to give an even shade. Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @ 0.80 ltr/10 sqm of approved brand and manufacture. (For boundary wall grill) |
| 17 | Providing and fixing double scaffolding system (cup lock type) on the exterior side of building/structure, upto 25 metre height, above ground level, including additional rows of scaffolding in stepped manner as per requirement of site, made with 40 mm dia M.S. tube, placed 1.5 metre centre to centre, horizontal & vertical tubes joint with cup & lock system with M.S. Tubes, M.S. tube challis, M.S. clamps and staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for execution of work of cleaning and/ or pointing and/ or applying chemical and removing it thereafter. The scaffolding system shall be stiffened with bracings, runners, connecting with the building etc, wherever required, if feasible, for inspection of work at required locations with essential safety features for the workmen etc., complete as per directions and approval of Engineer-in-charge. |
| 18 | Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres lead: (For cattle house) |
| 19 | Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in position with hold fast lugs or with dash fasteners of required dia & length (hold fast lugs or dash fastener shall be paid for separately).(For cattle house rafter) |
| 20 | Excavating, supplying, stacking and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift. (for even bed of clay tiles roof flooring) |
| 21 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. (For iron grill mesh for well cover, fordomeperiphery2x3.14x2.5, iron gate with 16 mm square bar with height 2.25) Angle 50 x 50 x 6 mm =180 kg16 mm square bar = 387.48 kg |
| 22 | Dismantling tiled roofing with battens, boarding etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead. Sqm 209.90 (For cattle house) |
| 23 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer – in – charge. (for room flooring) |
| 24 | Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete. (For room flooring) |
| 25 | Provision for repairing/removal of damaged ventilation (transom) and reinstallation of new one in verandah (for damaged ventilation) |
| 26 | Providing & fixing on roof pressed clay tile (Mangalore tile) of 20 mm nominal thickness and of approved size and as per approved pattern on steel frame work complete (steel frame work to be paid separately). (For roofing of cattle house) |
| 27 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. (for cattle house) |
| 28 | Brick work with common burnt clay F.P.S. (non modular) first class bricks in superstructure above plinth level up to floor V level in all shapes and sizes in :Cement mortar 1:4 (1 cement : 4 coarse sand) (for cattle house) Please Enable Macros to View BoQ information |