| 1 | Excavation for pole above 8.00m length by using JCB/Manual |
| 2 | Erection of RCC, REC, PSC poles above 8.00m length by using Crane / Manual |
| 3 | Excavation and erection of Stay pit of 4.5 ' to 5 ' depth using JCB / Manual |
| 4 | Fixing of Tapping Guarding X arm |
| 5 | Fixing of Tapping Channel X arm |
| 6 | Fixing of LT V cross arm |
| 7 | Fixing of LT single phase cross arm |
| 8 | Fixing of LT 3 phase cross arm |
| 9 | Fixing of 11 KV DISC Insulator |
| 10 | Fixing of LT pin Insulator |
| 11 | Fixing of LT Aluminium Knob |
| 12 | Erection of single pole structure including erection of DT complete structure complete without centre support |
| 13 | Erection of single pole structure including erection of DT complete structure complete with centre support |
| 14 | Erection of LT Shackle |
| 15 | Slotted holes |
| 16 | Pole Concreting |
| 17 | Earthing of poles with GI wire 4 or 6 SWG by coil earthing |
| 18 | Loading or unloading of DT below 250 KVA |
| 19 | Loading or unloading of DT upto 250 KVA |
| 20 | Loading or unloading of line materials |
| 21 | Loading or unloading of above 9 mt pole |
| 22 | Transforting of Distribution Transformer/Line Materials from stores to Office/site |
| 23 | Transforting of 8 mtr poles and other associated materials from road side to pole pit upto 2KM |
| 24 | Paving and stringing of conductor of 7/2.59mm ACSR for HT |
| 25 | Paving and stringing of conductor of 7/3.35mm ACSR for HT |
| 26 | Paving and stringing of conductor of 7/3.35mm ACSR for LT |
| 27 | Paving and stringing of conductor of 7/2.59mm ACSR for LT |
| 28 | Paving and stringing of conductor of 7/4.09mm ACSR for HT |
| 29 | Dismantling of conductor of 7/2.59mm ACSR for HT |
| 30 | Dismantling of conductor of 7/3.35mm ACSR for LT |
| 31 | Dismantling of conductor of 7/3.35mm ACSR for HT |
| 32 | Dismantling of conductor of 7/4.09mm ACSR for HT |
| 33 | Dismantling of pole above 8.00m length by using |
| 34 | Ordinary tree clearence and throne bushes & trees Please Enable Macros to View BoQ information |