| 1 | Annual Maintenance of HVAC System (80 TR Air Cooled Chiller), Including:- Inspection of plant/system and carry out preventive maintenance as per the standard practice four times a year.,Checking the refrigeration system, motor and starters for performance and ensuring healthy condition of the plant., Checking the system for any leaks and rectification of leaks., Taking set of readings and evaluating to ensure satisfactory performance of the plant., Checking the refrigeration control system for operation and adjusting the settings., De scaling the condensers., Cleaning the evaporator / condenser coils once a year ., Lubricating the bearings of motor, pumps, fans ., Quarterly inspection of belts adjusting the tension and replacing the worn out belts., Repairing / replacing the components of the equipment at site or in service station., Overhauling the components of the equipment at site or in service station., Replacing the refrigerant as a result of leak in the system arising out of fair wear and tear Attending to complaint/break down calls when called upon., Repair/replacement of microprocessor control if installed., Reporting the healthiness of the plant and suggesting improvements., Annual checking of compressor oil and replacement of the same., Checking of electrical controls and components (switches, timer, relays and starters) in the starter panel and replacement of the same.,Excluding:-Replacement of equipment such as compressor, condenser, chiller, compressor body, motor, cooling coil, cooling tower fills, body of cooling tower and body of AHU unit etc. However repairing of the same is covered under scope of CAMC., Replacement of Ducting and its accessories like dampers of all types, Thermal and Acoustic insulation, all types of piping, valves and Non Return Valves, , Incoming electrical panel, cabling, control wiring Bulbs and fuses., All kinds of civil and structural works, false ceiling. Replacement of any type of filters. AOR Pg-24 |
| 2 | Providing 2 Nos.(34241/- x 2 = 68482.00) Electrician & 01 Nos. (25270.00/- x 1= 25270.00) Helper (Total Cost Rs. 93752.00) for Operation of Chiller plant. ( NOIDA LABOUR RATE) AOR Pg-5 |
| 3 | Annual Maintenance charges for 250 KVA Silent Diesel Genrators Set with monthly visit of service Engineer routing & Preventive maintenance & Breakdown service Complete in all respects as per direction. Pg- |
| 4 | Providing 2 Nos.(25270/- x 2 = 50540.00) Helper for Operation of DG set. ( NOIDA LABOUR RATE)AOR Pg-5 |
| 5 | Annual repair & maintenance work of . HT Panels, main LT panels, Complete in all respect as perdirection of E/I. AOR Pg-8 |
| 6 | S/L of Al. armoured cable PVC insulated Ar. served & sheathed cable 1100 V grade at a depth of 750 mm below ground level over a cushion of 75 mm. thick sand all around and protected with burnt bricks on sides and on top. on surface the cable run shall be fixed on M.S. clamps etc of suitable size or as directed by the E/I.Complete in all respects . The armouring of the cable shall be properly connected with the earth conductor by clamps etc. Make -Grandlay/Plaza/Kalinga/ Havells. (PS No. 501) UPSR -2018 |
| 7 | a)- 300 sq. mm 3.5 core |
| 8 | b)- 185 sq. mm 3.5 core |
| 9 | S/F of Plain or Pin type copper tin plated cable socket (Lug) to the cable lead, insulating with tape and making connector etc. Complete in all respects as per Direction of E/I (PS No. 504) UPSR-2018a)-300sq. Mm |
| 10 | b)-185sq. Mm |
| 11 | Rewinding & Repairing of 1000 KVA Transformer. Complete in all respect as per direction of E/I. AOR Pg-10 |
| 12 | 1. HV Coial of Super Enamelled copper wire as required gauge with insulation peper complete all Respects. |
| 13 | 2. LV Coial of Super Enamelled copper wire as required gauge with insulation peper complete all Respects. |
| 14 | 3. Insulation |
| 15 | 4. H.V Metel Part |
| 16 | 5. LT Metel Part |
| 17 | 6. HV Bushing |
| 18 | 7. HV Bushing |
| 19 | 8. Set Gasket |
| 20 | 9. Breather |
| 21 | 10. Fresh Tranformer Makeup Oil |
| 22 | 11. Dehydration charges of Oil |
| 23 | 12. Cleaning and Painting Charges |
| 24 | 13. Overing Charges |
| 25 | 14. Loading and Unloading charges |
| 26 | 15. Labour Charges |
| 27 | Supply and Fixing of 2.5 sq.mm x 3 core copper cable.Complete in all respect as per direction of E/I. AOR Pg-9 Please Enable Macros to View BoQ information |