| 1 | Carriage following material from Centre Stores, Asfabad to site of work (Distance 00-20 Kms.) through the Kacha and Pakka road including the work of its loading and unloading at the respective ends as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier, erection of petty material etc. required for proper completion of work in the area of EUDD Asfabad, Firozabad (Material shall be provieded by Department) | Carriage following material from Centre Stores, Asfabad to site of work (Distance 00-20 Kms.) through the Kacha and Pakka road including the work of its loading and unloading at the respective ends as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier, erection of petty material etc. required for proper completion of work in the area of EUDD Asfabad, Firozabad (Material shall be provieded by Department) |
| 2 | 11/0.4 KV T/F 250 KVA New | 11/0.4 KV T/F 250 KVA New |
| 3 | 11/0.4 KV T/F 100 KVA New | 11/0.4 KV T/F 100 KVA New |
| 4 | 11 KV fuse Set | 11 KV fuse Set |
| 5 | ST Pole 11 MTr (Galvanised) | ST Pole 11 MTr (Galvanised) |
| 6 | ST Pole 9 MTr (Galvanised) | ST Pole 9 MTr (Galvanised) |
| 7 | MS Channel (Dropper) 100x50x2028mm (for fuse set) | MS Channel (Dropper) 100x50x2028mm (for fuse set) |
| 8 | ACSR Dog Conductor | ACSR Dog Conductor |
| 9 | 11kv V-type Steel Cross Arm | 11kv V-type Steel Cross Arm |
| 10 | MS Top channel (125x65x2240mm) | MS Top channel (125x65x2240mm) |
| 11 | 11 KV Disc Insulator T&C type 4500kg. | 11 KV Disc Insulator T&C type 4500kg. |
| 12 | 11 KV Disc fitting | 11 KV Disc fitting |
| 13 | MS Channel 125x65x1300mm (T-off) | MS Channel 125x65x1300mm (T-off) |
| 14 | 11 KV Pin insulator (Polymeric) | 11 KV Pin insulator (Polymeric) |
| 15 | 11 KV TPMO | 11 KV TPMO |
| 16 | LT AB Cable( 3*120+1*70+1*16) sq mm | LT AB Cable( 3*120+1*70+1*16) sq mm |
| 17 | LT XLPE Cable Al 1x400 sq mm | LT XLPE Cable Al 1x400 sq mm |
| 18 | LT XLPE Cable Al 1x120 sq mm | LT XLPE Cable Al 1x120 sq mm |
| 19 | Earthing of pole by MS earthing rod of 20x2500mm | Earthing of pole by MS earthing rod of 20x2500mm |
| 20 | 11 KV 3x70 XLPE Cable | 11 KV 3x70 XLPE Cable |
| 21 | Cable Jointing Kit Out door 11kv 70Sqmm | Cable Jointing Kit Out door 11kv 70Sqmm |
| 22 | Supply of the Following Material. | Supply of the Following Material. |
| 23 | Copper L-piece 62x225x12 mm (LS) | Copper L-piece 62x225x12 mm (LS) |
| 24 | Al Lug long barrel off size (LS) | Al Lug long barrel off size (LS) |
| 25 | Henley/LT Type Tailless Unit Protection Cubical Panel 500A,650v For 250KVA TF | Henley/LT Type Tailless Unit Protection Cubical Panel 500A,650v For 250KVA TF |
| 26 | Nut And Bolt off Size | Nut And Bolt off Size |
| 27 | Stone Pad 300x300x75 mm | Stone Pad 300x300x75 mm |
| 28 | Clamps for LT T-off with bolts & Nuts | Clamps for LT T-off with bolts & Nuts |
| 29 | Cross-Arm Holding Clamps with nut & bolts | Cross-Arm Holding Clamps with nut & bolts |
| 30 | F-Bracket for Fitting top Pin Insulator with nut & bolts | F-Bracket for Fitting top Pin Insulator with nut & bolts |
| 31 | Holding clamps for top channel TPMO & fuse set etc. with bolts & nuts | Holding clamps for top channel TPMO & fuse set etc. with bolts & nuts |
| 32 | LT Protection Box of 100kva T/F 11/.4kv | LT Protection Box of 100kva T/F 11/.4kv |
| 33 | Suspension Clamp | Suspension Clamp |
| 34 | I- Hook | I- Hook |
| 35 | Only Erection of the following Material | Only Erection of the following Material |
| 36 | Copper L-piece 62x225x12 mm (LS) | Copper L-piece 62x225x12 mm (LS) |
| 37 | Al Lug long barrel off size (LS) | Al Lug long barrel off size (LS) |
| 38 | Henley/LT Type Tailless Unit Protection Cubical Panel 500A,650v For 250KVA TF | Henley/LT Type Tailless Unit Protection Cubical Panel 500A,650v For 250KVA TF |
| 39 | Nut And Bolt off Size | Nut And Bolt off Size |
| 40 | Stone Pad 300x300x75 mm | Stone Pad 300x300x75 mm |
| 41 | Clamps for LT T-off with bolts & Nuts | Clamps for LT T-off with bolts & Nuts |
| 42 | Cross-Arm Holding Clamps with nut & bolts | Cross-Arm Holding Clamps with nut & bolts |
| 43 | F-Bracket for Fitting top Pin Insulator with nut & bolts | F-Bracket for Fitting top Pin Insulator with nut & bolts |
| 44 | Holding clamps for top channel TPMO & fuse set etc. with bolts & nuts | Holding clamps for top channel TPMO & fuse set etc. with bolts & nuts |
| 45 | LT Protection Box of 100kva T/F 11/.4kv | LT Protection Box of 100kva T/F 11/.4kv |
| 46 | Suspension Clamp | Suspension Clamp |
| 47 | I- Hook | I- Hook |
| 48 | Erection of Double pole structure 11 Mtrs on ST Pole by digging of pits fitting of all relevant accessories as per RESPO norms. | Erection of Double pole structure 11 Mtrs on ST Pole by digging of pits fitting of all relevant accessories as per RESPO norms. |
| 49 | Erection of single pole structure 11/9 Mtrs on ST Pole by digging of pits fitting of all relevant accessories as per RESPO norms. | Erection of single pole structure 11/9 Mtrs on ST Pole by digging of pits fitting of all relevant accessories as per RESPO norms. |
| 50 | Grouting of STP POLE 11/9 M Lons As per Respo Norms (Cement, Sand, Blast Stone with the ratio 1:4:8) will be provided by conractor | Grouting of STP POLE 11/9 M Lons As per Respo Norms (Cement, Sand, Blast Stone with the ratio 1:4:8) will be provided by conractor |
| 51 | Earthing of pole by M S Earthing Rod 20 x2500 mm and 6 SWG earthing wire etc | Earthing of pole by M S Earthing Rod 20 x2500 mm and 6 SWG earthing wire etc |
| 52 | Chemical Earthing of Distribution T/F by GI stipp patti as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. | Chemical Earthing of Distribution T/F by GI stipp patti as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
| 53 | Constructionof Distribution Transformer plinth of size 5’x6’x5’ at various places under the jurisdiction of EUDC, Firozabad. The size of plinth shall be of 4’ above the ground level. At the bottom there shall be brick ballast pad of size 5x6’x3” thick in ratio 1:3:6 [Cement, sand and brick ballast]. The first class brick wall work shall be 9” thick in ratio 1:4 [Cement and sand]. The hollow portion among the wall shall be filled up with the brick ballast properly hammered and rammered as per direction of supervising engineer. On the top of the wall there shall be mesh of 12 mm thick iron rod at distance of 9’’ and RCC work in ratio 1:3:6 [Cement, Sand and grit stone] There shall be plastering all over the plinth 12 mm thick in ratio 1:4 [Cement and sand] above the ground level. Proper watering and curing of the plinth shall be carried out as per direction of supervising engineer., and also including the cost of arrangement of labourer, T&P etc required for proper completion of work.1A- Job work includes all associated works like shifting and Re-placement of the distribution transformer required during construction of plinth. | Constructionof Distribution Transformer plinth of size 5’x6’x5’ at various places under the jurisdiction of EUDC, Firozabad. The size of plinth shall be of 4’ above the ground level. At the bottom there shall be brick ballast pad of size 5x6’x3” thick in ratio 1:3:6 [Cement, sand and brick ballast]. The first class brick wall work shall be 9” thick in ratio 1:4 [Cement and sand]. The hollow portion among the wall shall be filled up with the brick ballast properly hammered and rammered as per direction of supervising engineer. On the top of the wall there shall be mesh of 12 mm thick iron rod at distance of 9’’ and RCC work in ratio 1:3:6 [Cement, Sand and grit stone] There shall be plastering all over the plinth 12 mm thick in ratio 1:4 [Cement and sand] above the ground level. Proper watering and curing of the plinth shall be carried out as per direction of supervising engineer., and also including the cost of arrangement of labourer, T&P etc required for proper completion of work.1A- Job work includes all associated works like shifting and Re-placement of the distribution transformer required during construction of plinth. |
| 54 | Fencing of 250 KVA Distribution Transformers in proper alignment as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. | Fencing of 250 KVA Distribution Transformers in proper alignment as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
| 55 | Dismentalling and removal of the following transformers from various 11/0.4 KV substation, under the jurisdiction of Electricity Urban Distribution Circle, Firozabad, and their cartage from site to Centre Store Asfabad (Firozabad) through Kaccha Pakka road as per direction of supervising engineer, including the work of safe loading and unloading at the respective ends and also including the cost of arrangement of laborer, T&P, carrier etc required for proper completion of work. (Distance 00-20 Kms.) | Dismentalling and removal of the following transformers from various 11/0.4 KV substation, under the jurisdiction of Electricity Urban Distribution Circle, Firozabad, and their cartage from site to Centre Store Asfabad (Firozabad) through Kaccha Pakka road as per direction of supervising engineer, including the work of safe loading and unloading at the respective ends and also including the cost of arrangement of laborer, T&P, carrier etc required for proper completion of work. (Distance 00-20 Kms.) |
| 56 | 11/0.4 KV T/F 100 KVA | 11/0.4 KV T/F 100 KVA |
| 57 | Installation of the Following new transformers at various 11/0.4 KV substation, under the jurisdiction of Electricity Urban Distribution Circle, Firozabad, in proper alignment and direction and making proper HT/LT connection as per instruction of Supervising Engineer after carriage the same from Centre Stores, Asfabad including the work of safe loading and unloading at the respective ends and also including the cost of arrangement of laborer, T&P, carrier etc required for proper completion of work. | Installation of the Following new transformers at various 11/0.4 KV substation, under the jurisdiction of Electricity Urban Distribution Circle, Firozabad, in proper alignment and direction and making proper HT/LT connection as per instruction of Supervising Engineer after carriage the same from Centre Stores, Asfabad including the work of safe loading and unloading at the respective ends and also including the cost of arrangement of laborer, T&P, carrier etc required for proper completion of work. |
| 58 | 11/0.4 KV T/F 250 KVA | 11/0.4 KV T/F 250 KVA |
| 59 | 11/0.4 KV T/F 100 KVA | 11/0.4 KV T/F 100 KVA |
| 60 | Laying of Following Cable | Laying of Following Cable |
| 61 | LT AB Cable( 3*120+1*70+1*16) sq mm | LT AB Cable( 3*120+1*70+1*16) sq mm |
| 62 | LT XLPE Cable Al 1x400 sq mm | LT XLPE Cable Al 1x400 sq mm |
| 63 | LT XLPE Cable Al 1x120 sq mm | LT XLPE Cable Al 1x120 sq mm |
| 64 | 11 KV 3x70 XLPE Cable | 11 KV 3x70 XLPE Cable |
| 65 | Stay set Complete | Stay set Complete |
| 66 | Water Level T/F Neutral and Body Earthing | Water Level T/F Neutral and Body Earthing |