| 1 | Clearing & grubbing shrub, jungles including uprooting stumps of trees and trees below 1.0 m. girth and thick bushes including bamboo clamps based on pre- measurement including cess etc. complete as per direction of Engineer-in-Charge. |
| 2 | Earth work in excavation of foundation in hard soil within initial lead & lift including rough dressing & leveling the bed and slope and depositing the excavated earth away from work site including all labour, T&P etc. complete as per direction of Engineer. |
| 3 | Filling foundation and plinth with sand with well watered and rammed including cost, carriage, royalty of sand, cess etc. complete as directed by the Engineer-in-charge. |
| 4 | Providing and laying cement concrete M-15 with 20 mm size down graded black hard granite (crusher broken) stone chips free from weathered skin and other deleterious materials including hoisting and laying concrete curing for required days including all labour, cost, conveyance and royalty etc. complete as directed by Engineer-in-charge. |
| 5 | Providing and laying cement concrete M-25 with 20 mm size down graded black hard granite (crusher broken) stone chips free from weathered skin and other deleterious materials including hoisting and laying concrete curing for required days including all labour, cost, conveyance and royalty etc. complete as directed by Engineer-in-charge. |
| 6 | 6mm thick cement plaster (1:4) on RCC surface finished smooth closed deep chipping and slurry treatment etc.including watering and curing with the cost and conveyance of all materials and labour with T&P required for the work with royalties etc. complete as per direction of Engineer-in-Charge. |
| 7 | Providing, laying and fixing in position 900mm dia NP3 Hume pipe with collars jointed with cement mortar (1:3) complete including cost, conveyance, royalty, labour cess including Hume pipes and collars etc. complete including labour cess as per the direction of the Engineer-in-charge. |
| 8 | Providing, laying and fixing in position 300mm dia NP3 Hume pipe with collars jointed with cement mortar (1:3) complete including cost, conveyance, royalty, labour cess including Hume pipes and collars etc. complete including labour cess as per the direction of the Engineer-in-charge. |
| 9 | Providing, laying and fixing in position 200mm dia NP3 Hume pipe with collars jointed with cement mortar (1:3) complete including cost, conveyance, royalty, labour cess including Hume pipes and collars etc. complete including labour cess as per the direction of the Engineer-in-charge. |
| 10 | Rigid and smooth centering and shuttering for R.C.C works including false works and dismantling them after casting including cost of materials, labour css etc. complete as per direction of Engineer-in-charge. |
| 11 | Foundation |
| 12 | Superstructure |
| 13 | Earth work excavation of any approved type of soil from approved borrow area by mechanical means, loading in to and transportation by mechanical means and unloading the soil within a distance of 5 km. on properly prepared and scientifically approved surface, protection works etc. with all labour and cost of transportation , with all leads, lifts and delifts including spreading and breaking the clods to maximum 5cm to 7cm in size including clearance of site, uprooting the stumps and trees, and dressing/cutting the earth to the required profile and slope for all heights of banks and slopes with required quality control test including construction, maintenance, watering , dewatering and lighting of haul road and borrow area and royalties, labour cess, T&P etc. complete, including mobilization and demobilization of men and machineries and all incidental charges and quality control testing charges required for completion of the work as per drawing, specification and direction of the Engineer.(Measurement will be taken on level section). Arrangement of earth is the responsibility of agency. Please Enable Macros to View BoQ information |