| 1 | Cleaning and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs jungles, saplings and trees girth upto 300 mm removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable materials to be used or auction upto a lead of 1000 mtrs. including remoival and disposal of top organic soil not exceeding 150mm thickness with all leads, lifts and delifts including cost of all labours, T&P etc. complete and as per direction of Engineer-in-charge. |
| 2 | Earth work in excavation of foundation in hard soil or gravelly with all leads, lifts and delifts including rough dressing and breaking clods to maximum 5cm. to 7cm. and laying in layers not exceeding 0.30 M in depth and depositing the excavated earth away from work site with cost of all labours and T&P etc .complete as per direction of Engineer-in-charge. |
| 3 | Filling in foundation and plinth with sand well watered and rammed including cost, conveyance, royalty of all materials and cost of all labours and T&P etc. complete as per direction of Engineer-in-charge. |
| 4 | Cement concrete (1: 3 : 6) using hard granite crusher broken stone metal of 40mm.& down graded size of approved quality free from weathered skin and flakes including hoisting, laying and compacting the concrete to required thickness including proper watering, curing to required period with cost, conveyance, royality and taxes of all materials and cost of all labours, T&P etc. complete as per direction of Engineer-in-charge. |
| 5 | Brick work with Fly Ash brick in masonary (1:6) in foundation& Plinth using brick of size 23 x 11 x 8cm having crushing strength not less than 75 kg/cm2 with dimensional tolerance ± 8% including watering, curing to required period with cost, conveyance, royalty and taxes of all materials and cost of labours, T&P etc. complete as per direction of Engineer-in-charge. |
| 6 | Providing straightening, cutting, bending, binding, fitting and placing uncoated HYSD bar reinforcement and laying in position including cost of binding wire 18mm to 20mm gauge and fixing of reinforcement including lapping (as per steel code) where necessary spot with cost of all materials, conveyance, and cost of all labours, T&P etc. complete as per direction of Engineer-in-charge. |
| 7 | Rigid smooth centering and shuttering for R.C.C. works including false work and dismenteling the same after casting including cost of all materials, conveyance and cost of all labours, T&P etc. complete as per direction of Engineer-in-charge. (For RCC foundation, Plinth band and footing bases of column, Mass concrete, Precast slab etc.) |
| 8 | Rigid smooth centering and shuttering for R.C.C. works including false work and dismenteling the same after casting including cost of all materials, conveyance and cost of all labours, T&P etc. complete as per direction of Engineer-in-charge. (For RCC beams, Columns, grider and bressmer etc.) |
| 9 | Rigid smooth centering and shuttering for R.C.C. works including false work and dismenteling the same after casting including cost of all materials, conveyance and cost of all labours, T&P etc. complete as per direction of Engineer-in-charge. (For RCC floor and roof slabs, landing, balconies, projection sub-shades and chajja upto 4.30m height) |
| 10 | Brick work with Fly Ash brick in masonary (1:6) in superstructure using brick of size 23 x 11 x 8cm having crushing strength not less than 75 kg/cm2 with dimensional tolerance ± 8% including watering, curing to required period with cost of all materials, conveyance, royalty and cost of labours, T&P etc. complete as per direction of Engineer-in-charge. |
| 11 | Reinforcement cement concrete with 20mm down graded hard granite crusher broken chips of approved quality free from weathered skin materials mixing by concrete mixer including hoisting,lowering and laying the concrete in position to proper slope , level and compacting by vibrator in layers not exceeding 0.15m in depth and finished the exposed surface smooth including proper watering, curing to required period with cost of all materials, conveyance, hire and running charges of all machineries, royality and cost of all labours, T&P etc.complete as per direction of Engineer-in-charge. |
| 12 | Provoding & Fixing of granite tiles in floors treads or steps above 0.10sqm & upto 0.4sqm (10mm thick) confirming to IS:13755 landing on 25mm thick bed cement plaster (1:1) and filling jointed with neat cement slurry mixed with pigment to match the shade of tiles including rubbing and polishing with cost of all material, conveyance, royalty and cost of all labours, T&P etc. complete as per direction of Engineer-in-charge. |
| 13 | 12mm. thick cement plaster in C.M. (1 : 6 ) over brick masonary work including racking out joints and watering, curing to required period with cost of all materials, conveyance, royality and cost of all labours, T&P etc. complete as per direction of Engineer-in-charge. |
| 14 | 16mm. thick cement plaster in C.M. (1 : 6 ) over stone masonary work including racking out joints and watering, curing to required period with cost of all materials, conveyance, royality and cost of all labours, T&P etc. complete as per direction of Engineer-in-charge. |
| 15 | 6mm. thick cement plaster in C.M. (1 : 4 ) over RCC surface finished smooth including closed deep chipping and slury treatment with cost of all materials, conveyance, royality and cost of all labours, T&P etc. complete as per direction of Engineer-in-charge. |
| 16 | Supply at work site M.S. Panelled window double leave shutter with M.S.Frame & Grill over all size lincluding frame-1220mm height x 910mm width made out of the following materials conforming to relevant ISS frame-35x35x6mm M.S.Angle shutter style-top and bottom rail 25x25x3mm M.S. Angle window panel-1.0mm C.R. Sheet panel stiffener covering width of each leaf-19x5mm M.S.Flat 2 nos. lon each leaf. Hinges-size 100mm 4 nos (2 nos.on each side) bought out as per ISS hold fast-35x35x6mm M.S.Angle 100mm length bifurcated tip 2 nos. one each side, Handle-19x5mm M.S.Flat 2 nos. Fabricated (inside). Tower bolt-4 nos. bought out as per ISS Horizontal grills-12mm M.S.Round at 100mm spacing. Approximate weight-39 kg.inclding cost of all materials, cost of all labours, fabrication, transportation charges etc. complete as per direction of Engineer-in-charge.(Actual weight to be measured in kg weight.) |
| 17 | Supply at work site M.S Paneled door double leaved with M.S. framed over all size including frame 1980mm (H) x 1070mm.(W) made out of the following materials confirming to relevant ISS frame 35 x 35 x 6mm. M.S. angle shutter with style top and bottom rail 25 x 25 x 3mm. M.S. angle door panel 1.00mm C.R. sheet, panel stiffener covering width of each leaf with 19 x 5mm. M.S. flat 2 nos. on each leaf. Hinges size 100mm. - 6 nos. ( 3 nos. in each side) brought out as per ISS hold fast 35 x 35 x 6mm. M.S. Angle 175mm. length bifurcated at the tip – 3 nos. on each side handle 19 x 5mm. M.S. flat fabricated 4 nos. aldrop – 2 nos., tower bolt-2 Nos., including cost of all materials, and cost of all labours, fabrication and transportation charges etc. complete as per direction of Engineer-in-charge. (Actual weight of M.S. door to be taken before fixing in position). |
| 18 | Labour for fitting and fixing of M.S. door & windows and M.S. gate, M.S. grills etc. as per approved design including cost of all fitting materials, conveyance and cost of all labours etc. complete as per direction of the Engineer-in-Charge. |
| 19 | Priming one coat with any approved water bound primer in plaster surface work including cost of all materials, conveyance, and cost of all labours and T&P required for the work etc. complete as per direction of Engineer-in-charge. |
| 20 | Priming one coat with any approved primer in Iron work including cost of all materials, conveyance, and cost of all labours and T&P required for the work etc. complete as per direction of Engineer-in-charge. |
| 21 | Wall Painting two coats with Plastic emulsion paint of approved shade on new or old work to give an even shade including cost of all materials, conveyance and cost of all labours, T&P etc. complete as per direction of Engineer-in-charge. |
| 22 | Finishing wall painting two coats with water proofing weather coat of approved shade on new or old work including cost of all materials, conveyance and cost of all labours, T&P required for the work etc. complete as per direction of Engineer-in-charge. |
| 23 | Filling in foundation & plinth with excavated earth and well watered and rammed with cost of all materials, conveyance, royalty and cost of all labour, etc. complete as per direction of Engineer-in-charge Please Enable Macros to View BoQ information |