| 1 | Jungle clearance with cutting heavy under growth and Bushes up to 7.5 cm dia including all T&P etc all complete. |
| 2 | Earth work in Excavation of foundation for all type of soil with disposal within 30 m lead and 1.50 m lift etc. required proper completion of work. |
| 3 | Earthwork in Mar, Rankar and Kankar mixed soils in embankment for filling including lead and lift with dressing, making profile with proper compaction. all labour charges T&P etc. as per direction of Engineer -in-charge. |
| 4 | Supply and laying sand in foundation, including cost of all material, labour T&P etc all complete. |
| 5 | Supplying and laying of 11.20 to 19 mm size stone ballast under dry stone pitching including cost of all material, labour T&P etc. all complete. |
| 6 | Supplying and laying of 45 to 63 mm size stone ballast under dry stone pitching including cost of all material, labour T&P etc. all complete. |
| 7 | Laying Cement concrete 1:3:6 with cement, coarse sand and Stone grit including Mixing , laying ,ramming , curing and cost of all Material, Labour T&P etc all complete. |
| 8 | R.C.R. Stone Masonary in 1:4 Cement & Coarse Sand including cost of all Material, labour, T&P, Curing etc all complete. |
| 9 | Raised Struck cement pointing in 1:2 CM with cement and coarse sand including cost of all material, labor T&P etc. all complete. |
| 10 | Laying CC 1:1.5:3 with cement , coarse sand and Stone grit including Mixing with machine , laying , curing and cost of all Material, Labour T&P etc all complete . |
| 11 | Cement plaster 20 mm thick in 1:4 with cement and coarse sand including cost of all material, labor T&P etc. all complete. |
| 12 | Dismantling and Relaying stone pitching including cost of all material, labour, T&P etc all complete. |
| 13 | Supply and laying dry stone Boulder pitching including cost of all material, labour T&P etc all complete. |
| 14 | Grouting on stone boulder pitching Including cost of all material, labour and T&P etc all complete |
| 15 | Ist class - 150 Brick masonary in (1:4) cement, sand mortor including cost of all material, labour T&P etc. all complete. |
| 16 | Finishing wall with white coloured two coat approved make of or Birla, JK wall putty including cost of all material, labour T&P required for proper completion of work. |
| 17 | Distempering (Oil Bound Distemper) two coat of premium quality over one priming coat of cement primer on new surface after thoroughly brushing the surface even with plaster of paris and sand paper including cost of materials labour , T&P etc. required for proper completion of the work. |
| 18 | Finishing Wall with Premium Acrylic Smooth exterior Water proof Paint With silicone additives of Required shade New work (two or More coat applied @1.43ltr/ 10Sqm ) including Cost of all Material Labours T&P etc. Complete |
| 19 | Centering & Shuttering for RCC work including all material and T&P etc all complete. |
| 20 | Supplying and Laying R.C.C work M-20 grade 1:1.5:3 with 11.20-19mm stone grit and coarse sand including cost of all material, labour and T&P etc all complete. |
| 21 | Steel reinforcement for R.C.C. work including cutting, bending, and placing with cost of all materal, labour and T&P etc. |
| 22 | Providing and Laying C.C flooring 1:2:4 mix with coarse sand and stone grit including cost of all material, labour and T&P etc all complete. |
| 23 | Providing and fixing 1 mm thick MS Sheet Shutter With frame and diagonal braces , angle iron gusset plate at the junction and corner including locking arrangement with handle etc Complete and applying one priming coat of approved lead paint. cost of all material, labour and T&P etc all complete. |
| 24 | Supplying and fixing 1st quality white glazed orissa pattern W.C pan with 10 litre low lable flushing system including fixing and cost of all material, labour and T&P etc all complete. |
| 25 | Providing and fixing fly/mosquito proof galvanized M.S. wire gauge to windows and clerestory windows using wire gauge with average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm with 2nd class teak wood beading 62 mm × 19 mm all complete. |
| 26 | Fabrication and fixing of mild steel/iron work in grill, gates, railing, door, window frames including cutting, drilling, welding, riveting and fixing hinges where necessary with fixing in position including cost of all material, labour, T&P etc. required for proper completion of work. |
| 27 | Painting Two coat of synthetic enamel paint on surface with superior quality approved make for Steel surface including cost of all material, labour T&P etc. required for proper completion of work. Please Enable Macros to View BoQ information |