| 1 | Appendix I-Urgent Repair works to the various bulidings |
| 2 | Dismantling old plaster or skirting raking out joints and cleaning the surface forplaster including disposal of rubbish to the dumping ground within 50 metres lead. |
| 3 | 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand) |
| 4 | Applying one coat of water thinnable cement primer of approved brand andmanufacture on wall surface:Water thinnable cement primer |
| 5 | Dismantling tile work in floors and roofs laid in cement mortar including stackingmaterial within 50 metres lead.For thickness of tiles 10 mm to 25 mm |
| 6 | Providing and laying in position cement concrete of specified grade excluding thecost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarsesand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mmnominal size derived from natural sources) |
| 7 | Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to bespecified by the manufacturer) of 1st quality conforming to IS : 15622 of approvedmake in colours such as White, Ivory, Grey, Fume Red Brown, laid on 20 mm thickcement mortar 1:4 (1 Cement : 4 Coarse sand), Jointing with grey cement slurry @3.3 kg/sqm including pointing the joints with white cement and matching pigment etc., complete |
| 8 | Structural steel work in single section, fixed with or without connecting plate,including cutting, hoisting, fixing in position and applying a priming coat of approvedsteel primer all complete. |
| 9 | Extra labour charges for strengthening existing steel Hand rail : Black smith (1stclass) |
| 10 | Providing and fixing fly proof galvanized M.S. wire gauge to windows and clerestorywindows using wire gauge with average width of aperture 1.4 mm in both directionswith wire of dia 0.63 mm all complete.With 12 mm mild steel U beading |
| 11 | Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured), Panellingfor panelled or panelled and glazed shutters 25 mm to 40 mm thick:4 mm thick glasspane (weight not less than 10kg/sqm). |
| 12 | Extra labour charges for repairing the damaged doors and windows : carpenter (avg) |
| 13 | Dismantling roofing including ridges, hips, velleys and gutters etc., and stacking thematerial within 50 metres lead of :Asbestos cement Sheet |
| 14 | Providing asbestos corrugated sheets roofing up to any pitch and fixing with polymercoated J,or L hooks, bolts and nuts 8 mm dia. G.I plain and bitumen washers or withself drilling fastener and EPDM washers etc. complete (excluding the cost of purlins,rafters and trusses), including cutting sheets to size and shape wherever required. |
| 15 | Engaged carpenter for re-nailing existing dislocated AC sheet ceiling in line and levelat eastern room : Carpenter (2nd class) |
| 16 | Providing and fixing single scaffolding system on the exterior side, upto 5m heightmade with 40 mm dia M.S. tube, 1.5 m centre to centre, horizontal & verticaltubes joining with M.S. clamps and M.S. staircase system in the scaffolding forworking platform etc.and maintaining it in a serviceble condition for the requiredduration as approved and removing it there after. |
| 17 | Appendix II-Maintance to Ground Floor north wing |
| 18 | Cleaning the old painted surface having algae and other impurity using pressure washer including labour and hire charges of pump etc complete. |
| 19 | Finishing walls with Acrylic Smooth exterior paint of required shade :Old work (Twoor more coat applied @ 0.90 ltr/ 10 sqm) |
| 20 | Painting with synthetic enamel paint of approved brand and manufacture of requiredcolour to give an even shade :One or more coats on old work |
| 21 | Extra labour charges for cleaning site : Man coolie |
| 22 | Appendix III-Maintance to First Floor north wing |
| 23 | Cleaning the old painted surface having algae and other impurity using pressure washer including labour and hire charges of pump etc complete. |
| 24 | Finishing walls with Acrylic Smooth exterior paint of required shade :Old work (Twoor more coat applied @ 0.90 ltr/ 10 sqm) |
| 25 | Painting with synthetic enamel paint of approved brand and manufacture of requiredcolour to give an even shade :One or more coats on old work |
| 26 | Appendix IV-Maintance to First Floor East wing |
| 27 | Cleaning the old painted surface having algae and other impurity using pressure washer including labour and hire charges of pump etc complete. |
| 28 | Finishing walls with Acrylic Smooth exterior paint of required shade :Old work (Twoor more coat applied @ 0.90 ltr/ 10 sqm) |
| 29 | Painting with synthetic enamel paint of approved brand and manufacture of requiredcolour to give an even shade :One or more coats on old work Please Enable Macros to View BoQ information |