| 1 | Dismembering existing BRC fabric jal by welding or cutting machine (for protection of tanks from monkeys ) to remove tanks from plateform and placing the same at proper place as per direction of Engineer-in-Charge. |
| 2 | Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead. |
| 3 | Dismanting of existing worn out /broked PVC tank i/c disconnecting all the connection and stacking of the same at proper place all complete as per direction of Engineer-in-Chrge. |
| 4 | Dismantling 15 to 40 mm dia G.I. pipe including stacking of dismantled pipes (within 50 metres lead) as per direction of Engineerin-Charge:(a) Internal Work- Exposed on wall |
| 5 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge:In cement mortar |
| 6 | Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) : a) With F.P.S.(non modular) bricks. |
| 7 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
| 8 | Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank. |
| 9 | Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. : Internal work - Exposed on wall a) 40 mm nominal outer dia. Pipes. |
| 10 | a) 20 mm nominal outer dia. Pipes. |
| 11 | Making connection of G.I./PVC distribution branch with G.I. /PVC main of following sizes by providing and fixing tee, including cutting and threading the pipe etc. complete : a) 25 to 40 mm nominal bore |
| 12 | Transportation of electric welding machine set to the site of work by machanical means up to any lead and taken back from the site of work etc. all complete as direction of Engineer-in-charge:Note:(Contractor have to bring the electric welding machine at site in the beginning of work and taken back from the site after completion of work.) |
| 13 | Refixing of existing BRC fabric jal by welding (for protection of tanks from monkeys ) to newly constructed plateform after placing tanks on the plateform all complete as per direction of Engineer-in-Charge. |
| 14 | Disposal of moorum/ building rubbish/ malba/ similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to approved municipal dumping ground for lead upto 10 km for all lifts, complete as per directions of Engineer-in-Charge. Note - Item to be applicable in urban areas having directions for restricted hours for movement/plying of load carriying motor vehicle of 3.5 cum or more.\\" |
| 15 | Grading roof for water proofing treatment with a) Cement mortar 1:3 (1 cement : 3 coarse sand) |
| 16 | Credit for the old unserviceable material: |
| 17 | i) steel received from the dismantling work. |
| 18 | ii) PVC Tank Please Enable Macros to View BoQ information |