| 1 | Supply of following Decentralized materials at the works site as per RESSPO norms |
| 2 | X-arms holding clamps with bolts & nuts for ST/PCC pole |
| 3 | M.S clamp for T-off channel with bolts & nuts for ST/PCC pole |
| 4 | Stone pad, 300x300x75 mm |
| 5 | F-bracket with bolts & nuts for ST/PCC pole |
| 6 | Danger Board with clamps & bolts for ST/PCC pole |
| 7 | Guarding Angle Clamps for ST/PCC pole |
| 8 | E-bracket with bolts & nuts |
| 9 | Clamps with nuts & bolts for Top /Dropper Channel for ST/PCC pole |
| 10 | PG clamps |
| 11 | Stay Clamp |
| 12 | Stay Insulator |
| 13 | LT Clamp |
| 14 | LT shackle insulator |
| 15 | Suspension clamp with nuts & bolts |
| 16 | J Hook |
| 17 | Dead end clamp |
| 18 | Eye- Hook |
| 19 | Distribution Box Clamp with nuts & bolts |
| 20 | Cartage of following materials from Electricity Store Center, Mirzapur to dump site near work site including loading/ unloading and proper stocking. |
| 21 | ST/PCC Pole 11 mtr long |
| 22 | PCC Pole 8.5 mtr long |
| 23 | Line materials with ACSR Weasel Conductor/AB Cable different size etc. |
| 24 | Transformer 10 KVA |
| 25 | Transformer 25 KVA |
| 26 | Transformer 63 KVA |
| 27 | Transformer 100 KVA |
| 28 | 11 KV XLPE Cable size 3x70/120/185 mm2 |
| 29 | 11 KV Pilfer proof metering cubicle |
| 30 | 11 KV CT/PT combined unit |
| 31 | Erection of single support ST/PCC pole for construction of 11 KV/LT line including digging of pit, fitting of all accessories, back filling of earth & others required work. |
| 32 | Grouting of pole with 1:4:8 ratio of cement sand & brick ballast as per RESSPO norms. (cement sand & brick ballast wil be supplied by the constractor on his own his own cost) |
| 33 | Grouting of stay sets including digging of pit with 1:4:8 ratio of cement sand & brick ballast as per RESSPO norms, fixing binding and nuzzling of stay wire. (cement sand & brick ballast wil be supplied by the constractor on his own his own cost) |
| 34 | Earthing of Poles |
| 35 | Erection of Sectional Double Pole Structure of ST/PCC pole including digging of pit, fitting of accessories, back filling of earth, earthing, grouting of each pole & all stay sets (cement sand & brick ballast wil be supplied by the constractor on his own his own cost) & other required works. |
| 36 | Stringing & sagging of 3 phase 11 KV line upto proper sag including laying of ACSR Weasel Conductor, binding with insulators & jumpering. |
| 37 | Stringing & sagging of LT line upto proper sag including laying of ACSR Weasel/Dog Conductor, binding with insulators & jumpering. |
| 38 | Laying, Streaching of Arial Bunch Cable size 1x25+1x16/ 3x50+1x35+1x16/ 3x95+1x70+1x16/3x120+1x95+1x16 mm2 as per RESSPO norms. |
| 39 | Drill/cut of stone for erection of Pole/Stay in hilly area |
| 40 | Mounting of 10 KVA Transformer alongwith HT & LT connections as per RESSPO norms. |
| 41 | Mounting of 25 KVA Transformer alongwith HT & LT connections as per RESSPO norms. |
| 42 | Mounting of 63 KVA Transformer alongwith HT & LT connections as per RESSPO norms. |
| 43 | Mounting of 100 KVA Transformer alongwith HT & LT connections as per RESSPO norms. |
| 44 | Laying of 11 KV XLPE Cable alongwith cost of bricks & sand as per RESSPO norms |
| 45 | Gaurding of 11 KV line as per RESSPO norms |
| 46 | Filling of cable jointing kit size 3x70/120/185 mm2 11 KV indoor & outdoor type as per RESPO norms |
| 47 | Installation of 11 KV Pilfer proof metering cubicle inside meter room, by fixing rag bolts after checking alignment with trench & conneting incomming & outgoing cable in the CT chamber as per RESPO norms |
| 48 | Installation of CT/PT combined unit as per RESPO norms Installation of 11 KV Pilfer proof metering cubicle inside meter room, by fixing rag bolts after checking alignment with trench & conneting incomming & outgoing cable in the CT chamber Please Enable Macros to View BoQ information |