| 1 | Earth work excavation of foundation trenches in all kind of soil including dressing and leavelling the bed upto the required depth and depositing the excaveted materials with all leads & Limtrs T&P shoring and shuttering watering im necessary etc. complete as per direction of EIC |
| 2 | Supplying and filling foundation and plinth with sand watered and rammed including cost, conveyance royalties and taxes of all materials and cost of all labour , T&P required mor the work etc complete as directed by the EIC |
| 3 | Cement concrete (1:3:6) using approved quality of approved quarry including lowering laying concrete watering and curing etc as required levels laid in layers not exceeding (0'-6\\") 15 cm thick including cost, conveyance , royalties and taxes of all materials and cost of all labour , T&P required mor the work etc complete in all respect as directed by the EIC |
| 4 | RCC work M-20 in grade having a minimum compressive strength in work test 150 kg/cm2 in 15 cm cubes at 28 days using 12 mm & down graded hard granite C.B chips of approved quality and approved quarry including watering , lowering laying concrete, compacting with vibrators, curing mor 28 days with smooth rigid concrete etc complete as per direction of EIC |
| 5 | Column Base |
| 6 | Grade Beam |
| 7 | Lintel Beam |
| 8 | RCC column |
| 9 | RCC Beam |
| 10 | RCC stair case |
| 11 | RCC Roof slab |
| 12 | Supplying cutting, bending un-coated HYSD bars, for reinforcement tying the grills and placing in position as required for the RCC works and for providing fan hooks hoisting and lowering , laying including cost, coveyance & taxes of SYSD bars and binding wires of 18 to 20 gauge required for the work and bending binding and tying the grills |
| 13 | Fly ash bricks masonary in cm (1:6) after immersing the bricks 6hrs in water before use in Foundation and Plinth having C.S. 75kg./cm2 including all cost, carriage, royalty etc complete |
| 14 | Fly ash bricks masonary in cm (1:6) in Superstructure after immersing the bricks 6hrs in water before use in all floors having C.S. 75Kg/cm2 including all cost, carriage, royalty etc complete |
| 15 | 12 mm thick CP with CM (1:6) including all cost, conveyance & Royalty etc all complete |
| 16 | 16 mm thick cement plaster with CM (1:6) including all cost, conveyance & Royalty etc complete |
| 17 | 6 mm thick cement plaster with C.M (1:4) on ceiling including all cost, conveyance & royalty etc complete |
| 18 | Fixing vetrified tiles in floor, treads of steps and landing on 20 mm thick bed of cement mortar (1:4) and filling joints with white cement of approved quality including cost of all materials, labour T & P, rubbing & polishing etc all complete |
| 19 | Fixing of ceramic wall tiles on wall 20 cm x 30 cm / 20 cm x 20 cm special plane / printed series of premium grade having thickness 6.55 mm to 6.7 mm confirming to IS 13753 on 12 mm thick bed of cement mortar 1:3 (1 cement : 3 sand) jointed with neat cement slury mixed with pigment to match the shades of the files including rubbing and polishing complete |
| 20 | Providing and fixing of fixed ventilators of approved make to be fabricated from roll formed section made of pre painted steel ( base steel as per IS: 513 of 0.60 mm thick \\"D\\" quality Galvanized as per IS : 277 with zinc of 120 Gm / sq.mtr.) with paint specification being with primer of 5/7 microns & finished paint with polyster paint ( Black / Peral white/ Chocolate Brown) of 12-16 microns along with the alkyd sideer at the side of 5-7 microns & the sizes of outer frame being of 46x52 mm & with all vertical & horizontal mullions are of 46 x 70 mm & fixed beading are of 18 x 25 mm. Accessories / gasket are to be used as per the manufacturers supply & specification like handle being made of hygrade aluminium powder coated & with Nylong receiver & gasket will be made of EPDM. All corner brackets are to be made of CRCA with Zinc phosphating |
| 21 | Providing MS grill made out of 12 mm Sq. bar and 25 x 6 mm MS angle of approved desing including all cost etc complete |
| 22 | Supplying, fitting and fixing of Stainless steel of 304 grade in hand railing using 50mm dia of 2 mm thick circular pipes with balustrade of size 32mm x 32mm x 2mm @ 0.90m c/c and stainless square pipe bracing of 32 mm x 32 mm x 2mm in three row in stair case as per approved design and specifications buffing, polishing inlcuding cost, carriage, royalty etc complete |
| 23 | Providing fitting & fixing of Fibre Moulded Door for Toilets including all cost etc complete |
| 24 | Finishing surface of wall with Acrilic wall putty (Water based) of approved make and finished smooth and even surface to received painting including cost of puty all labour T&P etc complete |
| 25 | Finishing wall surface with weather coat painting 2 coat over a coat of primer to the new surfaces of walls with all cost |
| 26 | Wall painting two coats with plastic emulsion paint of approved shade over a coat of primer on new work including cost of paint |
| 27 | Providing 20 mm thick cement plaster with cement mortar (1:4) with rough surface of stone masonary walls including watering and curing rounding of corners etc |
| 28 | Painting tow coats with any approved paint over one coat of primer on new wood of iron work including cost of materials |
| 29 | 1st Floor |
| 30 | RCC work M-20 in grade having a minimum compressive strength in work test 150 kg/cm2 in 15 cm cubes at 28 days using 12 mm & down graded hard granite C.B chips of approved quality and approved quarry including watering , lowering laying concrete, compacting with vibrators, curing mor 28 days with smooth rigid concrete etc complete as per direction of EIC |
| 31 | RCC columns |
| 32 | RCC chajja |
| 33 | Lintel Beam |
| 34 | RCC Beam |
| 35 | RCC Roof slab |
| 36 | Supplying cutting, bending un-coated HYSD bars, for reinforcement tying the grills and placing in position as required for the RCC works and for providing fan hooks hoisting and lowering , laying including cost, coveyance & taxes of SYSD bars and binding wires of 18 to 20 gauge required for the work and bending binding and tying the grills |
| 37 | Providing 2.5 cm thick grading concrete in C.C. (1:2:2) with 4.7 mm size CBHG chips on new roof slab including cost of materials, labour, T&P all comp. |
| 38 | Fly ash bricks masonary in cm (1:6) in Superstructure after immersing the bricks 6hrs in water before use in all floors having C.S. 75Kg/cm2 including all cost, carriage, royalty etc complete |
| 39 | 12 mm thick CP with CM (1:6) over brick wall finished smooth after raking out the joints including all cost, conveyance & Royalty etc all complete |
| 40 | 16 mm thick cement plaster with CM (1:6) over brick wall finished smooth after raking out the joints including all cost, conveyance & Royalty etc complete |
| 41 | Fixing vetrified tiles in floor, treads of steps and landing on 20 mm thick bed of cement mortar (1:4) and filling joints with white cement of approved quality including cost of all materials, labour T & P, rubbing & polishing etc all complete |
| 42 | Fixing of ceramic tiles in dados , skirting riser of steps 20 cm x 30 cm / 20 cm x 20 cm special plane / printed series of premium grade having thickness 6.5 mm to 6.7 mm confirming to IS 13753 on 12 mm thick bed of cement mortar 1:3 (1 cement : 3 sand) jointed with neat cement slury mixed with pigment to match the shades of the files including rubbing and polishing complete |
| 43 | Finishing surface of wall with Acrilic wall putty (Water based) of approved make and finished smooth and even surface to received painting including cost of puty all labour T&P etc complete |
| 44 | Finishing wall surface with weather coat painting 2 coat over a coat of primer to the new surfaces of walls with all cost |
| 45 | Wall painting two coats with plastic emulsion paint of approved shade over a coat of primer on new work including cost of paint |
| 46 | Painting two coats with any approved paint over one coat of Primer on new wood or iron work including cost of materials |
| 47 | Electrification work 5.25% |
| 48 | PH work 5.25% Please Enable Macros to View BoQ information |