| 1 | Description of Material |
| 2 | 33/0.4KV 800 KVA LT STATION TRANSFORMER |
| 3 | 72.5KV, Circiut Breaker(3-Phase), 1250A, 25KA for 3 sec with support structure |
| 4 | 72.5KV, Current Transformer(1-PH), 50/1-1A, 25KA for 3 sec with 120% extended rating with support structure |
| 5 | 72.5KV/110-110V, Voltage Transformer(1-PH) with support structure |
| 6 | 72.5KV Isolator (PH), 800A, 25KA without E/S |
| 7 | 72.5KV Isolator-PIPE TYPE STR. |
| 8 | 72.5KV Bus Post Insulator with support structure |
| 9 | 1.1KV, XLPE (AL).1 C*630 SQ MM (2 runs per ph. & 1 run for neutral) |
| 10 | 33KV C&R PANEL,220V DC |
| 11 | T/C LT TRANSFORMER TO RCV 1*ACSR MOOSE |
| 12 | T/C 72.5KV PT TO RCV 1*ACSR MOOSE |
| 13 | T/C 72.5KV CT TO RCV 1*ACSR MOOSE |
| 14 | T/C 72.5KV CB TO RCV 1*ACSR MOOSE 1250A |
| 15 | T/C 72.5KV ISO TO RCV 1*ACSR MOOSE |
| 16 | T/C 72.5KV PI TO RCV 1*ACSR MOOSE |
| 17 | T/C 3\\" IPS (EH) AL Tube |
| 18 | 3\\"IPS(EH) AL TUBE (OD73.03MM THK 7.01M) |
| 19 | WELDING SLEEVES- 3\\" IPS AL TUBE |
| 20 | JUNCTION BOX |
| 21 | ACSR MOOSE CONDUCTOR |
| 22 | Earthing Material (MS ROD, GS Flat, MS Electrode,clamp for earthing, earth enhancing compound etc.) |
| 23 | Marshalling Box |
| 24 | Control Cable |
| 25 | 19*2.5 SQ MM |
| 26 | 12*2.5 SQ MM |
| 27 | 04*4 SQ MM |
| 28 | 3*2.5 SQ MM |
| 29 | Any Other item required for successful completion of work |
| 30 | 33/0.4KV 800 KVA STATION TRANSFORMER |
| 31 | 72.5KV, Circiut Breaker(3-Phase), 1250A, 25KA for 3 sec with support structure |
| 32 | 72.5KV, Current Transformer(1-PH), 50A, 25KA for 3 sec with 120% extended rating with support structure |
| 33 | 72.5KV, Voltage Transformer(1-PH) with support structure |
| 34 | 72.5KV Isolator (PH), 800A, 25KA for 3 sec without E/S support structure |
| 35 | 72.5KV- ISOLATOR-PIPE TYPE STR. |
| 36 | 72.5KV Bus Post Insulator with support structure |
| 37 | 1.1KV, XLPE (AL).1 C*630 SQ MM (2 runs per ph. & 1 run for neutral) |
| 38 | 33KV C&R PANEL, 220V DC |
| 39 | T/C LT TRANSFORMER TO RCV 1*ACSR MOOSE |
| 40 | T/C 72.5KV PT TO RCV 1*ACSR MOOSE |
| 41 | T/C 72.5KV CT TO RCV 1*ACSR MOOSE |
| 42 | T/C 72.5KV CB TO RCV 1*ACSR MOOSE 1250A |
| 43 | T/C 72.5KV ISO TO RCV 1*ACSR MOOSE |
| 44 | T/C 72.5KV PI TO RCV 1*ACSR MOOSE |
| 45 | T/C 3\\" IPS (EH) AL Tube |
| 46 | 3\\"IPS(EH) AL TUBE (OD73.03MM THK 7.01M) |
| 47 | WELDING SLEEVES- 3\\" IPS AL TUBE |
| 48 | JUNCTION BOX |
| 49 | ACSR MOOSE CONDUCTOR |
| 50 | Earthing Material (MS ROD, GS Flat, MS Electrode,clamp for earthing, earth enhancing compound etc.) |
| 51 | Marshalling Box |
| 52 | Control Cable |
| 53 | 19*2.5 SQ MM |
| 54 | 12*2.5 SQ MM |
| 55 | 04*4 SQ MM |
| 56 | 3*2.5 SQ MM |
| 57 | CIVIL WORKS |
| 58 | Foundation for 33/0.433KV, 800KVA, LT three phase station transformer Please Enable Macros to View BoQ information |
| 59 | Foundation for 33/0.433KV, 800KVA, LT three phase station transformer Please Enable Macros to View BoQ information |