| 1 | Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared. Including supply of all material labour T&P etc required for proper completion of the work |
| 2 | Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction ofshoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.Ordinary soil 11-1-1-1 Upto any depth. Including supply of all material labour T&P etc required for proper completion of the work |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level: 1:3:6 (1 Cement : 3 coarse sand (zone-Ill) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources). Including supply of all material labour T&P etc required for proper completion of the work. |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level: 1:2:4 (1 cement : 2 coarse sand (zone-Ill) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) . Including supply of all material labour T&P etc required for proper completion of the work. |
| 5 | Clearance of land slides (Slip Clearance) Slip clearance (by manual means) of earth and boulders including disposal complete as directed by the Engineer-in-charge. Including supply of all material labour T&P etc required for proper completion of the work |
| 6 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete including supply of all material, labour, T&P etc. required for proper completion of the work. as per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction. Including supply of all material labour T&P etc required for proper completion of the work |
| 7 | Providing and laying of wire crates 3.00x1.50x1.50 in size with GI wire conforming to IS: 280 & IS:4826 in 150mm x 150mm mesh laid with stone boulders. as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) GI wire 10 gauge BWG. Including supply of all material labour T&P etc required for proper completion of the work |
| 8 | Providing and laying in position specified grade of reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm Nominal size). excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level. Including supply of all material labour T&P etc required for proper completion of the work. |
| 9 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Including supply of all material labour T&P etc required for proper completion of the work. |
| 10 | Centering and shuttering including strutting Foundations, footings, bases of columns, etc. for mass concrete etc. and removal of form for all heightsIncluding supply of all material labour T&P etc required for proper completion of the work. |
| 11 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.Including supply of all material labour T&P etc required for proper completion of the work. |
| 12 | Hand Packed stone filling in back of wallls including cost of all materials, royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications. Including supply of all material labour T&P etc required for proper completion of the work |
| 13 | Random Rubble Stone Masonry laid in 1:6 cement and sand mortar, in breast walls, retaining walls, parapets, scuppers, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction. Including supply of all material labour T&P etc required for proper completion of the work |
| 14 | Providing and laying of Empty Cement Bags ( Gunny Bags) filled with local sand and tightened using sutli and carriage upto site including preparing subgrade before placing in position, also including supply ofall material, labour, T&P etc required for proper completion of the work. |
| 15 | Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical specifications Clause 1302 14-5-1 Stone/Boulder. Including supply of all material labour T&P etc required for proper completion of the work |
| 16 | Dewatering of water caused dueto seepage of ground water and surface water due to rain etc. excluding excavation of foundation but during execution of civil works including supply of all machine operator, khalashi, POL, T&P, accessories required for proper completion of the work. Including supply of all material labour T&P etc required for proper completion of the work |
| 17 | Engaging & operation of one no.Hydraulic excavator cum loader machine (preferably JCB)having capacity 75 BHP with one operator and one helper, including cost of fule lubricants and repair maintenance etc. for removal of slip/landslide/excavation in dry and wet condition, complete in all respect as per direction of I/C. Including supply of all material labour T&P etc required for proper completion of the work |
| 18 | Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x 100 mm, filled with boulders with least dimension of 200 mm, all loose ends to be tied with 4 mm galvanised steel wire). Including supply of all material labour T&P etc required for proper completion of the work |
| 19 | Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification. Granular material. Including supply of all material labour T&P etc required for proper completion of the work |
| 20 | Providing Hydra crane including diesel, operator, & all necessary T&P required for proper completion of the work as per direction of Engineer-in-charge |
| 21 | Providing and laying filter material underneath pitching in slopes complete as per drawing and technical specifications Clause 1302 Please Enable Macros to View BoQ information |