| 1 | Earth work excavation of foundation in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and levelling the bed and depositing the excaveted earth away from site and as per the direction of the Engineer-in-charge. |
| 2 | Filling in foundatin and plinth with sand watered and rammed including cost, conveyance, cost of materials, T&P, royality etc complete as per direction of the Engineer-In-charge. |
| 3 | Cement concrete (1:3:6)with 4cm size hard granite metal including cost of all materials, labour T&P etc. required for the work etc. complete as per direction of the Engineer-in-charge. |
| 4 | 16mm. Thick cement plaster (1:6) for brick work including cost of all materials, labour T&P etc. required for the work etc. complete as per direction of the Engineer-in-charge. |
| 5 | Fixing tiles in floors treads or steps and landing on 25mm thick bed of cement mortar 1:1 (1cement : 1sand) jointed with neat cement slury mixed with pigment to match the shades of the tiles including rubbing and polishing complete excluding cost of precast tiles ( VETRIFIED TILES ) |
| 6 | Brick work with Fly. bricks 23cm x 11cm x 8cm size having crushing strength not less than 75 Kg/cm2 with dimensional tolerance ±8 percent in cement mortar (1:6) in foundation and plinth including cost, conveyance, royality, T&P etc complete as per direction of the Engineer in charge. |
| 7 | 12mm. Thick cement plaster (1:6) for brick work including cost of all materials, labour T&P etc. required for the work etc. complete as per direction of the Engineer-in-charge. |
| 8 | R.C.C. M-20 using 20 mm & down graded size b.h.g.c.b. chips including centering & shuttering, watering, curing with cost, conveyance, royalty and taxes of all materials and labour etc. complete.Column Base |
| 9 | Column |
| 10 | Cutting, bending and binding of M.S. rod and tor steel including cutting,bending,binding and tying the grills placing in position for R.C.C.work with cost ,conveyance,taxes of all the materials & labour (T&P)etc.complete. |
| 11 | Finishing wall surface with Acrylic wall putty(water based)of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all material, taxes, cess, labour ,T&P etc. complete. |
| 12 | Supplying fitting, fixing Chequers tile in floors trades on steps & landing on 25 mm thick cement mortar (1:1)jointed with neat cement slury mixed with pigment to match the shades of the tiles including rubbing and polishing completeincluding cost of material, labour, T&P etc., complete. |
| 13 | Supplying, fitting and fixing of flush door and shutter including cost of all materials & labours taxes T & P complete in all respect. |
| 14 | Providing, fitting & fixing of Aluminium sliding window including of all cost, conveyance etc all complete. |
| 15 | Wall painting two coats with any approved quality of Weather seal coat over a coat of priming on new work to give an even shade including cost of all materials, labour, T&p required for the work complete. |
| 16 | Providing, fitting & fixing of Gypsum ceiling to the walls including of all cost, conveyance etc all complete. |
| 17 | Providing fitting and fixing of Gypsum Ceiling Flower to be fixed by means of steel screw and PVC suspended from celling etc complete. |
| 18 | Providing, fitting & fixing of Gypsum cornices to the ceiling including of all cost, conveyance etc all complete. Please Enable Macros to View BoQ information |