| 1 | Earth Excavation of foundation in hard soil within initial lead & lift including leveling the bed & depositing the soil away working area etc completed as direction of Engineer. |
| 2 | Filling sand in foundation and plinth including cost of material with taxes , watering, ramming etc. Complete as per direction of E-I-C. |
| 3 | Cement Concrete (1:4:8) using 4cm size B.H.G. (C. B.) Metal including cost, conveyance , royalty & taxes of all materials etc. complete |
| 4 | R.C.C work M-20 grade with 20mm & down grade crusher broken hard Granite chips including hoisting & laying with cost of all labour, materials with all taxes, lead ,T & P , ,but excluding centering, shuttering cost of steel and labour required for bending, binding etc. all complete as per direction of E-I-C |
| 5 | Column up to Roof level |
| 6 | 2.5cm thick A.S. flooring with C.C.(1:2:4) with punning using 12mm. size c.b.b.h.g. chips |
| 7 | Supplying fitting fixing and placing uncoated HYSD bar reinforcement complete as per drawing and technical specification |
| 8 | Brick work with Fly Ash Brick having crossing strength between 100kg/cm2 to149kg/cm2 in C.M.( 1:4) in foundation and plinth. |
| 9 | 12mm. thick cement plastering (1:6) |
| 10 | Finishing wall surface with Wall Cement Primer water based including cost all complete.(A/R Item-1,Page- 93) |
| 11 | Wall painting two coat with Plastic Emulsion Paint of approved shade etc complete |
| 12 | Providing, spreading Quarry Rubbish in Sub-Base in layers not exceeding 22.5cm. including watering ,compacting to the required density in O.M.C. with rolling by Vibratory Roller as per O.P.W.D. specifications including cost, conveyance & royalty of all materials,cost of all labour, T & P, labour cess, watering, turfedging, hire & running charges of Vibratory Roller etc. complete. |
| 13 | Iron work wrought & put up in trusses as per direction of Engineer-in -charge including cost of all labour, T & P, cost of all materials required for the work. |
| 14 | Supplying fitting and fixing G.I. Trafford Sheet (TATA make) in Roof including fixing of ridges etc complete. Please Enable Macros to View BoQ information |