| 1 | Providing one Coil Earth using No8 GI earth wire (50 mm dia,115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling |
| 2 | Providing Stay for LT poles including digging & back filling pit in ordinary soil. |
| 3 | Additional rate for providing one HT Pin withinsulator, complete on any type of HT pole |
| 4 | Providing one Earth using GI earth pipe of size 38.1mm dia2.5m length including digging separate pit (0.45 x 0.45 x 2.5 m) at a minimum distance of 1.5 m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil and backfilling |
| 5 | Fitting one Additional 2.4m/3m Channel cross arm (100x50x6mm), in existing 11KV DP incl. conveyance of materials. |
| 6 | Transporting poles by hired vehicle to a distance up to 5km and carrying up to 4 poles excluding loading & unloading |
| 7 | Transporting poles by hired vehicle to adistance beyond 5km and carrying upto 4numbers of poles. (Running km) |
| 8 | Fitting and erecting one HT DP using PSC pole in position incl. fitting 2 channel cross arms, digging & back filling pit, drawing sufficient length of GI earthing leads through all cross arms to ground for earthing (excluding provision of earthing) |
| 9 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 10 | Providing Strut using LT PSC pole including digging and back filling pit in ordinary soil. |
| 11 | Fitting and erecting one HT PSC type pole in position incl. fitting cross arm, digging & back filling pit in ordinary soil(as per standards) , drawing sufficient length of GI earthing leads from F clamp through V cross arm to ground for earthing (excluding provision of earthing),drawing earth leads |
| 12 | Providing concrete muffing (0.45x0.45x1.5m) ( 0.5m above GL and 1m below GL).Excavation 0.45x0.45x1m concrete (1:3:6 20mm) 0.45x0.45x1.5m.Plastering (1:3) 12mm 0.45mx0.45mx 5 sides |
| 13 | Fitting and erecting one HT Double pole structure using A type pole in position incl. fitting 2 No channel cross arm,digging & back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing |
| 14 | Labour charges for loading HT PSC pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 15 | Fitting and providing one HT stay for 11KV pole incl. digging and back filling pit in ordinary soil |
| 16 | Fitting one set AB switch on existing DP giving connection and drawing sufficient length of GI earthing leads to the grounf for earthing excluding provision for earthing |
| 17 | Drilling hole of various sizes on existing Channel/Cross arm |
| 18 | Drilling oval shaped hole of various sizes on existing Channel/Cross Arm/GI/MS cleat etc |
| 19 | Erecting one LT PSC Pole in positionincluding digging & back filling pit in ordinary soil. |
| 20 | Providing WP support with PSC poleincluding digging & back filling pit in ordinary soil. excluding transportation of poles. |
| 21 | Dismantling (without damage) one km LTthree phase 4 wire OH line conductor bydismantling cross arms, insulators andstacking the conductors in rolls properly |
| 22 | Stringing, shackling, fitting cross arms,insulators and binding, giving jumperconnection etc. using ACSR Rabbit, for one km LT three phase 4 wire line including cutting and removing tree branches wherever necessary and conveyance of all materials(except poles) from stacking place. |
| 23 | Additional rate refitting/redoing shackle Set including reshackling one span while renewing any type of LT pole |
| 24 | Additional rate for providing one disc set,PG clamp etc complete on any type of HT pole for making cut point |
| 25 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line incl. reconnecting the same after completing the line work |
| 26 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line incl. reconnecting the same after completing the line work |
| 27 | Dismantling one ordinary street light/CFL/LED fitting from existing pole cleaning, rewiring,repairing/replacing the holder, changing bulbs and refitting the same in position and givingconnection |
| 28 | Dismantling ( without damage) one LT PSC/RCC pole after disconnecting stays, strut, etc. and stacking the same |
| 29 | Providing Fly stay for LT pole using LT PSC pole including digging and back filling pit in ordinary soil |
| 30 | Cutting trees having girth beyond 60cm but upto and including 120cm (felling treesc including cutting of trunks and branches) and removing the root completely and stacking etc. 1 No. |
| 31 | Fitting one No. Section fuse on LT line with dropping cables, crimping sockets,connecting with bolt & nut etc. |
| 32 | Fitting one no additional section Fuse unit and giving connection from Transformer to fuse and Distribution to LT OH line |
| 33 | Transporting Transformers by hired vehicle to a distance upto 5km and carrying upto 2 numbers of 63/100/160/250kVA Transformers/ Ring Main Units excluding loading&unloading charges |
| 34 | Providing Transformer fencing to a height of 1.8 m above ground level using MS Angle frames of size ISA 50x50x6mm for outer frame, 2 runs of 40 x 6 MS flat for horizontal bracing and grills with MS rods 8 mm Dia @ 10cm c/c for verticals, providing gate with locking arrangements, providing danger board & name board, embeding the legs in cement concrete 1:2:4, footing of size 30cmx30cmx50cm, painting with synthetic enamel paint two coats over one coat of iron primer etc complete, incl cost of transportation |
| 35 | Cleaning and levelling of transformeryard/RMU, spreading 40 mm broken stone in yard for a thickness of 10 cm above bed of 10 cm thick 6 mm broken stone, after constructing a curb wall of height 20cm above ground and 10cm below level including cost of all materials and charges for conveying,spreading, consolidating etc. |
| 36 | Stringing of one km 3 PH 11 kV line with XLPE insulated ACSR Racoon or equivalent ( 3 conductors) after fitting insulators,binding conductors to pin insulators using suitable tie and anchoring with wedge type anchoring clamps including cutting and removing tree branches wherever necessary excluding cut point works |
| 37 | Providing bridging at Cut points for 3 PH11kV line with XLPE Insulated ACSR Raccoon or equalant (1 conductors) using IPC and respective conductors |
| 38 | Pole numbering using printed Aluminiumsheets of 22 SWG having size 20 x 12 cm or Painting the surface of line supports where numbers are to be inscribed, Pole numbers shall be painted in circular / rectangular background, using approved quality anti algal yellow paint in two coat after scraping and cleaning the surface at a height of 2.5 metre above ground level. The number and lettersshould be in black synthetic enamel paint.The size of the number should be at least2cm in height x 1.5cm in width. including cost of paint |
| 39 | Fitting 5 channel cross arms, AB switch,DO fuse, LA(Ord),HT & LT connections upto OH lines etc on existing DP structure,Fixing distribution box/provision for one set (3 No) of LT fuses,drawing sufficient lemgth of GI earthing leadsto the groubd for earthing excluding provision for earthing and mounting of transformer on poles |
| 40 | Erecting one 100 kVA Transformer to existing DP and giving connections including loading from TMR/SRS/other stacking places & unloading at site but excluding cost for transporting transformer |
| 41 | Fitting one Additional V cross arm in existing single pole including conveyance of materials |
| 42 | Fitting one Additional 75x40mm, 1.8mChannel cross arm in existing single poleincluding conveyance of materials. |
| 43 | Additional rate for excavation of one Pit for HT pole/ HT stay in soft rock |
| 44 | Additional rate for excavation of Pit for A type pole in hard Laterite |
| 45 | Additional rate for providing one F top bracket complete, on any type of HT pole. |
| 46 | Additional rate for excavation of one Pit for HT pole/ HT stay in laterite Please Enable Macros to View BoQ information |