| 1 | Dismentling brick or stone masonary in lime or cement mortar t including stacking the useful materials for reuse and removing the debries with 50m lead from work site etc.complete as per direction of Engineer-in-charge. |
| 2 | Earthwork in excavation of foundation & Plinth in hard soil including dressing and levelling the bed upto the reqd. depth and deposited the excavated materials with all leads and lifts T&P shoring and shuttering if reqd. etc.complete as per direction of Engineer-in-charge. |
| 3 | Filling foundation with sand well watered and rammed with appropriate rammer /Mechanical compactor and top surface dressed and levelled to proper gradient including all cost of materials and labour T&P etc. comple as directed by Engineer-in-charge. |
| 4 | Providing Plain cement concrete (1:3:6) by using 40mm size BHG(C.B) metal of appd.quality from appd.quarry including hoisting,lowering and laying concrete in layers to the reqd.levels ramming watering, curing etc. complete including cost,conveyance,royalties and taxes of all materials with all labour T&P reqd. for the work etc.complete in all respect and as per direction of Engineer-in-charge. |
| 5 | Providing Plain cement concrete (1:2:4) by using 12mm size BHG(C.B) Chips of appd.quality from appd.quarry including hoisting,lowering and laying concrete in layers to the reqd.levels ramming watering, curing etc. complete including cost,conveyance,royalties and taxes of all materials with all labour T&P reqd. for the work etc.complete in all respect and as per direction of Engineer-in-charge. |
| 6 | Fly Ash brick masonary in C.M(1:6)using bricks of size 25cmx12cmx8cm having crushing strength 75kg/cm2 after immersing the bricks for six hours in water before use in Foundation and plinth with all necessary projections, cutting,moulding,corebelling, champering, watering and curing with all cost of materials and labour T&P etc.complete as per direction of Engineer-in-charge. |
| 7 | Fly Ash brick masonary in C.M(1:6)using bricks of size 25cmx12cmx8cm having crushing strength 75kg/cm2 after immersing the bricks for six hours in water before use in Superstructure with all necessary projections, cutting,moulding,corebelling, champering, watering and curing with all cost of materials and labour T&P etc.complete as per direction of Engineer-in-charge. |
| 8 | 12mm thick Cement plaster in C.M(1:6)over brick walls after rackingout joint including watering and curing with all cost of materials and labour T&P etc.complete as per direction of Engineer-in-charge. |
| 9 | 16mm thick Cement plaster in C.M(1:6)over brick walls after rackingout joint including watering and curing with all cost of materials and labour T&P etc.complete as per direction of Engineer-in-charge. |
| 10 | 2.5cm.thick Grading concrete with C.C(1:2:4) on roof using 6mm size BHG(C.B)chips of appd.quality from appd.quarry including ,laying .in uniform thickness and compacting concrete watering and curing etc.complete as per direction of Engineer-in-charge. |
| 11 | Providing,fitting and fixing Vetrified floor tiles in floors,treads and steps over 25mm thick bed of C.M(1:1) jointed with application of Polymer modified cement based water resistant adhesive mixed with pigment to match the shades of tiles including all cost of materials and labour T&P etc. reqd. for the work complete as per direction of Engineer-in-charge. |
| 12 | Providing,fitting and fixing Vetrified tiles in dados ,skirting and steps over 12mm thick bed of C.M(1:3) jointed with neat cement slurry mixed with pigment to match the shades of tiles including all cost of materials and labour T&P etc. reqd. for the work complete as per direction of Engineer-in-charge. |
| 13 | Dessed seasoned Sal wood work (Wrought and put up) for Door and window Choukaths etc. completed with iron fittings and wooded hinged cleats etc. fixed in position including all cost of materials and labour T&P etc.complete as per direction of Engineer-in-charge. |
| 14 | Providing fitting and fixing W.I.Clamps of 33cm to 38cm long of approved design for doors and windows including all cost of materials and labour T&P etc.complete as directed by Engineer-in-charge. |
| 15 | Providing fitting and fixing 32mm thick Piasal wood or local teak wood pannelled / Glazed shutters for doors and windows including mending and cutting sizes of grooves in choukaths for over lapping portion of the shutter where necessary fitting and fixing wooden hinged cleats fitted in position including all cost of materials and labour T&P etc.complete as per direction of Engineer-in-charge. |
| 16 | Supplying fitting and fixing of M.S.Grills, Grill gate, M.S.Gates, M.S.door, M.S.Angle , M.S.Shutter with Choukaaths ,Collapsible gates with top and bottom rails,steeel windows critical frames for windows ,staircase and parapet railing made out of M.S.Square bar / flat including .as per approved drawing and design with cost of all materials and labour, taxes, labour cess, T&P sundries etc.complete in all respect as per specification and direction of the Engineer-in-charge. |
| 17 | Painting two coats with appd. shade Door/window over wood / Iron work over a coat of primer including all cost of materials and labour T&P etc.complete as directed by Engineer-in-charge. |
| 18 | Painting two coats on Iron work with appd. shade over a coat of primer including all cost of materials and labour T&P etc.complete as directed by Engineer-in-charge. |
| 19 | Painting two coats to wall surface with approved plastic paint of appd.shade including all cost of materials and labour T&P etc.complete as directed by Engineer-in-charge. |
| 20 | Finishing wall surface with water proofing weather coat paint two coats to give an even shade over the plastered surface of brick walls including all cost of materials and labour T&P etc.compete as directed by Engineer-in-charge. |
| 21 | Providing fitting and fixing of Window (Sliding type)made of Allu. Section as window frame section No.4095, 4096, &9777, 3994 with 5mm thick black glass as panel fitted with rubber beading including locking arrangement with all cost of materials and labour T&P etc.complete as per direction of Engineer-in-charge. Please Enable Macros to View BoQ information |