| 1 | Cutting & clearance of jungle, bushes, shrubs Ankra/Ipomoea, Julicflora typna etc. on canal and bunds in dry/moist/slushy conditions including disposal as per instructions of the Engineer-in-charge. Cost of wood has been deducted from rates and thus will be property of contractor after cutting.(b) Thick |
| 2 | Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m in dry or moist including dressing of excavated area, dewatering wherever required complete in all respect. Soft soil |
| 3 | Earth work in rough (borrow area) excavation for embankments in hard soil, morrum or highly weathered strata dry or moist, including laying in 20 cm layers (before compaction) and breaking of clods, sorting of grass, pebbles etc. and dressing when compacted by vibro compactor, vibro sheep foot roller, sheep foot roller/pneumatic tyred roller to obtain dry density of at least 98% of Standard Proctor's density with initial lift of 1.5m (Excluding charges for compaction and watering) including loading and un-loading wherever required complete in all respect. with initial lead of 250 m . With lead beyond 1250 m and up to 1750 m( for average lead 1.5 Km) |
| 4 | Compaction of earth or highly weathered strata By mechanical equipment such as sheep foot roller/ pneumatic tyred roller/vibro compactor / vibro sheep foot compactor required as per site condition to obtain dry density of. (ii) at least 98% of Standard Proctor's density |
| 5 | Watering of earth including cost of carriage of water when source of water is up to 1 Km. |
| 6 | Lip cutting and final dressing as per designed section including re-handling and disposal of excavated earth in layers 20 cm on embankments etc. with cost of dewatering wherever required, and complete in all respect |
| 7 | Supplying and laying quarry spalls properly graded but not more than 10cm in size with spreading in required profile including all leads & lifts. |
| 8 | Labour charges for spreading of morrum/ quarry spall/rubbish/kanker etc. on side slope of embankment within initial lead upto 50m including dressing etc. |
| 9 | Supplying stone, spall and laying R. R. stone pitching, hammer dressed with packing of voids from small stones including all lead & lifts, in required profile of (c) 23 cm thickness (± 5 % thickness tolerance) |
| 10 | Dry boulder filling in required profile with filling of voids etc. complete including all lead & lifts, and well finished surface. |
| 11 | Providing and Laying in position of Cement concrete Nominal mix (1:2:4) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 20 mm |
| 12 | Providing and Laying in position of Cement concrete Nominal mix (1:3:6) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 40 mm |
| 13 | Random rubble stone masonry (using R. R. stones where 75 % stones to be not less than 15 cm in size in any direction and weighing not less than 23 kg.) for foundation including curing all leads of all construction materials including curing etc. complete. (c)In cement sand mortar 1:4 |
| 14 | Random rubble stone masonry (using R. R. stones where 75 % stones to be not less than 15 cm in size in any direction and weighing not less than 23 kg.) for superstructure including curing all leads of all construction materials including curing etc. complete. Add extra over item for Masonry work in superstructure for Dam and other works. (c)In cement sand mortar 1:4 |
| 15 | Supplying of M.S. reionforcement including labour charges for bending binding and placing in position all reinforcement as per drawing including cost of binding wire and all leads and lifts using.Tor or ribbed bars (IS :1786-1985) |
| 16 | Side shuttering including propping etc. complete (to achieve finish F 2 for :Retaining wall, counterfort, abutment, wing walls up stream or down- stream slope facings of dams and open faces of construction joints etc. Please Enable Macros to View BoQ information |